Search Legislation

The Sustainable Drainage (Approval and Adoption Procedure) (Wales) Regulations 2018

 Help about what version

What Version

 Help about opening options

Opening Options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

PART 2Determination of applications for approval

Refusal to determine application for approval

3.—(1) An approving body(1) may refuse to determine an application for approval which is not made in accordance with paragraph 9(2) or 10(2) (as the case may be) of Schedule 3.

(2) Where an approving body refuses to determine an application pursuant to paragraph (1), it must as soon as practicable—

(a)inform the applicant of the refusal and the reasons for it, and

(b)return any application fee accompanying the application.

Duty to consult before determining application for approval

4.—(1) An approving body, when requesting a response from a person consulted under paragraph 11(3) of Schedule 3 (a “consultee”), must specify a date for response which is within 3 weeks beginning on the first working day after sending the request.

(2) Before the end of the period specified under paragraph (1) the approving body and consultee may agree a different date for response.

(3) The approving body may disregard a response that is received from a consultee after the relevant time limit.

(4) In this regulation, “relevant time limit” means—

(a)a period specified under paragraph (1), or

(b)any other period agreed under paragraph (2).

Time limits for determining applications for approval

5.—(1) An approving body must determine—

(a)an application for approval that relates to a development that is the subject of an Environmental Impact Assessment under the Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2017(2)(“the 2017 Regulations”) within the period of 12 weeks beginning on the first working day after it receives a valid application, or

(b)any other application for approval within the period of 7 weeks beginning on the first working day after it receives a valid application.

(2) Before the end of the period specified in sub-paragraph (a) or (b) (as the case may be) of paragraph (1), the approving body and applicant may agree a longer time for determining an application.

(3) An approving body which fails to determine an application within the relevant time limit is deemed to have refused the application.

(4) In this regulation—

“development” (“datblygiad”) has the meaning given in section 55(1) of the Town and Country Planning Act 1990(3);

“Environmental Impact Assessment” (“Asesiad o’r Effaith Amgylcheddol”) has the meaning given in regulation 2 of the 2017 Regulations;

“relevant time limit” (“terfyn amser perthnasol”) means—

(a)

a period specified in paragraph (1), or

(b)

any longer period agreed under paragraph (2).

(1)

“Approving body” is defined in paragraph 6 of Schedule 3.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.

Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources