xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

TITLE IIU.K.RULES APPLICABLE TO CONTRACTS

CHAPTER VIU.K.Rules on publication and transparency

Section 3U.K.Communication and information

Article 49U.K.Information to applicants for qualification, candidates and tenderers

1.Contracting entities shall as soon as possible inform the economic operators involved of decisions reached concerning the conclusion of a framework agreement, the award of the contract, or admission to a dynamic purchasing system, including the grounds for any decision not to conclude a framework agreement or award a contract for which there has been a call for competition or to recommence the procedure, or not to implement a dynamic purchasing system; this information shall be provided in writing if the contracting entities are requested to do so.

2.On request from the party concerned, contracting entities shall, as soon as possible, inform:

The time taken to do so may under no circumstances exceed 15 days from receipt of the written enquiry.

However, contracting entities may decide that certain information on the contract award or the conclusion of the framework agreement or on admission to a dynamic purchasing system, referred to in the paragraph 1, is to be withheld where release of such information would impede law enforcement or otherwise be contrary to the public interest or would prejudice the legitimate commercial interests of a particular economic operator, public or private, including the interests of the economic operator to whom the contract has been awarded, or might prejudice fair competition between economic operators.

3.Contracting entities which establish and operate a system of qualification shall inform applicants of their decision as to qualification within a period of six months.

If the decision will take longer than four months from the presentation of an application, the contracting entity shall inform the applicant, within two months of the application, of the reasons justifying the longer period and of the date by which his application will be accepted or refused.

4.Applicants whose qualification is refused shall be informed of this decision and the reasons for refusal as soon as possible and under no circumstances more than 15 days later than the date of the decision. The reasons shall be based on the criteria for qualification referred to in Article 53(2).

5.Contracting entities which establish and operate a system of qualification may bring the qualification of an economic operator to an end only for reasons based on the criteria for qualification referred to in Article 53(2). Any intention to bring qualification to an end shall be notified in writing to the economic operator beforehand, at least 15 days before the date on which qualification is due to end, together with the reason or reasons justifying the proposed action.