Search Legislation

Directive 2004/17/EC of the European Parliament and of the Council (repealed)Show full title

Directive 2004/17/EC of the European Parliament and of the Council of 31 March 2004 coordinating the procurement procedures of entities operating in the water, energy, transport and postal services sectors (repealed)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes over time for: CHAPTER VI

 Help about opening options

Version Superseded: 18/04/2016

Status:

EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.

CHAPTER VIU.K.Rules on publication and transparency

Section 1U.K.Publication of notices

Article 41U.K.Periodic indicative notices and notices on the existence of a system of qualification

1.Contracting entities shall make known, at least once a year, by means of a periodic indicative notice as referred to in Annex XV A, published by the Commission or by themselves on their ‘buyer profile’, as described in point 2(b) of Annex XX:

(a)where supplies are concerned, the estimated total value of the contracts or the framework agreements by product area which they intend to award over the following 12 months, where the total estimated value, taking into account the provisions of Articles 16 and 17, is equal to or greater than EUR 750 000.

The product area shall be established by the contracting entities by reference to the CPV nomenclature:

(b)where services are concerned, the estimated total value of the contracts or the framework agreements in each of the categories of services listed in Annex XVII A which they intend to award over the following 12 months, where such estimated total value, taking into account the provisions of Articles 16 and 17, is equal to or greater than EUR 750 000;

(c)where works are concerned, the essential characteristics of the works contracts or the framework agreements which they intend to award over the following 12 months, whose estimated value is equal to or greater than the threshold specified in Article 16, taking into account the provisions of Article 17.

The notices referred to in subparagraphs (a) and (b) shall be sent to the Commission or published on the buyer profile as soon as possible after the beginning of the budgetary year.

The notice referred to in subparagraph (c) shall be sent to the Commission or published on the buyer profile as soon as possible after the decision approving the planning of the works contracts or the framework agreements that the contracting entities intend to award.

Contracting entities which publish a periodic indicative notice on their buyer profiles shall transmit to the Commission, electronically, a notice of the publication of the periodic indicative notice on a buyer profile, in accordance with the format and procedures for the electronic transmission of notices indicated in point 3 of Annex XX.

The publication of the notices referred to in subparagraphs (a), (b) and (c) shall be compulsory only where the contracting entities take the option of reducing the time limits for the receipt of tenders as laid down in Article 45(4).

This paragraph shall not apply to procedures without prior call for competition.

2.Contracting entities may, in particular, publish or arrange for the Commission to publish periodic indicative notices relating to major projects without repeating information previously included in a periodic indicative notice, provided that it is clearly pointed out that these notices are additional ones.

3.Where contracting entities choose to set up a qualification system in accordance with Article 53, the system shall be the subject of a notice as referred to in Annex XIV, indicating the purpose of the qualification system and how to have access to the rules concerning its operation. Where the system is of a duration greater than three years, the notice shall be published annually. Where the system is of a shorter duration, an initial notice shall suffice.

Article 42U.K.Notices used as a means of calling for competition

1.In the case of supply, works or service contracts, the call for competition may be made:

(a)by means of a periodic indicative notice as referred to in Annex XV A; or

(b)by means of a notice on the existence of a qualification system as referred to in Annex XIV; or

(c)by means of a contract notice as referred to in Annex XIII A, B or C.

2.In the case of dynamic purchasing systems, the system's call for competition shall be by contract notice as referred to in paragraph 1(c), whereas calls for competition for contracts based on such systems shall be by simplified contract notice as referred to in Annex XIII D.

3.When a call for competition is made by means of a periodic indicative notice, the notice shall:

(a)refer specifically to the supplies, works or services which will be the subject of the contract to be awarded;

(b)indicate that the contract will be awarded by restricted or negotiated procedure without further publication of a notice of a call for competition and invite interested economic operators to express their interest in writing; and

(c)have been published in accordance with Annex XX not more than 12 months prior to the date on which the invitation referred to in Article 47(5) is sent. Moreover, the contracting entity shall meet the time limits laid down in Article 45.

Article 43U.K.Contract award notices

1.Contracting entities which have awarded a contract or a framework agreement shall, within two months of the award of the contract or framework agreement, send a contract award notice as referred to in Annex XVI under conditions to be laid down by the Commission in accordance with the procedure referred to in Article 68(2).

In the case of contracts awarded under a framework agreement within the meaning of Article 14(2), the contracting entities shall not be bound to send a notice of the results of the award procedure for each contract based on that agreement.

Contracting entities shall send a contract award notice based on a dynamic purchasing system within two months after the award of each contract. They may, however, group such notices on a quarterly basis. In that case, they shall send the grouped notices within two months of the end of each quarter.

2.The information provided in accordance with Annex XVI and intended for publication shall be published in accordance with Annex XX. In this connection, the Commission shall respect any sensitive commercial aspects which the contracting entities may point out when forwarding this information, concerning the number of tenders received, the identity of economic operators, or prices.

3.Where contracting entities award a research-and-development service contract (‘R&D contract’) by way of a procedure without a call for competition in accordance with Article 40(3)(b), they may limit to the reference ‘research and development services’ the information to be provided in accordance with Annex XVI concerning the nature and quantity of the services provided.

Where contracting entities award an R&D contract which cannot be awarded by way of a procedure without a call for competition in accordance with Article 40(3)(b), they may, on grounds of commercial confidentiality, limit the information to be provided in accordance with Annex XVI concerning the nature and quantity of the services supplied.

In such cases, contracting entities shall ensure that any information published under this paragraph is no less detailed than that contained in the notice of the call for competition published in accordance with Article 42(1).

If they use a qualification system, contracting entities shall ensure in such cases that such information is no less detailed than the category referred to in the list of qualified service providers drawn up in accordance with Article 53(7).

4.In the case of contracts awarded for services listed in Annex XVII B, the contracting entities shall indicate in the notice whether they agree to publication.

5.Information provided in accordance with Annex XVI and marked as not being intended for publication shall be published only in simplified form and in accordance with Annex XX for statistical purposes.

Article 44U.K.Form and manner of publication of notices

1.Notices shall include the information mentioned in Annexes XIII, XIV, XV A, XV B and XVI and, where appropriate, any other information deemed useful by the contracting entity in the format of standard forms adopted by the Commission in accordance with the procedure referred to in Article 68(2).

2.Notices sent by contracting entities to the Commission shall be sent either by electronic means in accordance with the format and procedures for transmission indicated in point 3 of Annex XX, or by other means.

The notices referred to in Articles 41, 42 and 43 shall be published in accordance with the technical characteristics for publication set out in point 1(a) and (b) of Annex XX.

3.Notices drawn up and transmitted by electronic means in accordance with the format and procedures for transmission indicated in point 3 of Annex XX, shall be published no later than five days after they are sent.

Notices which are not transmitted by electronic means in accordance with the format and procedures for transmission indicated in point 3 of Annex XX shall be published not later than 12 days after they are transmitted. However, in exceptional cases, the contract notices referred to in Article 42(1)(c) shall be published within five days in response to a request by the contracting entity, provided that the notice has been sent by fax.

4.Contract notices shall be published in full in an official language of the Community as chosen by the contracting entity, this original language version constituting the sole authentic text. A summary of the important elements of each notice shall be published in the other official languages.

The costs of publication of notices by the Commission shall be borne by the Community.

5.Notices and their contents may not be published at national level before the date on which they are sent to the Commission.

Notices published at national level shall not contain information other than that contained in the notices dispatched to the Commission or published on a buyer profile in accordance with the first subparagraph of Article 41(1), but shall mention the date of dispatch of the notice to the Commission or its publication on the buyer profile.

Periodic indicative notices may not be published on a buyer profile before the dispatch to the Commission of the notice of their publication in that form; they shall mention the date of that dispatch.

6.Contracting entities shall ensure that they are able to supply proof of the dates on which notices are dispatched.

7.The Commission shall give the contracting entity confirmation of the publication of the information sent, mentioning the date of that publication. Such confirmation shall constitute proof of publication.

8.Contracting entities may publish in accordance with paragraphs 1 to 7 contract notices which are not subject to the publication requirements laid down in this Directive.

Section 2U.K.Time limits

Article 45U.K.Time limits for the receipt of requests to participate and for the receipt of tenders

1.When fixing the time limits for requests to participate and the receipt of tenders, contracting entities shall take particular account of the complexity of the contract and the time required for drawing up tenders, without prejudice to the minimum time limits set by this Article.

2.In the case of open procedures, the minimum time limit for the receipt of tenders shall be 52 days from the date on which the contract notice was sent.

3.In restricted procedures and in negotiated procedures with a prior call for competition, the following arrangements shall apply:

(a)the time limit for the receipt of requests to participate, in response to a notice published under Article 42(1)(c), or in response to an invitation by the contracting entities under Article 47(5), shall, as a general rule, be fixed at no less than 37 days from the date on which the notice or invitation was sent and may in no case be less than 22 days if the notice is sent for publication by means other than electronic means or fax, and at no less than 15 days if the notice is transmitted by such means;

(b)the time limit for the receipt of tenders may be set by mutual agreement between the contracting entity and the selected candidates, provided that all candidates have the same time to prepare and submit their tenders;

(c)where it is not possible to reach agreement on the time limit for the receipt of tenders, the contracting entity shall fix a time limit which shall, as a general rule, be at least 24 days and shall in no case be less than 10 days from the date of the invitation to tender.

4.If the contracting entities have published a periodic indicative notice as referred to in Article 41(1) in accordance with Annex XX, the minimum time limit for the receipt of tenders in open procedures shall, as a general rule, not be less than 36 days, but shall in no case be less than 22 days from the date on which the notice was sent.

These reduced time limits are permitted, provided that the periodic indicative notice has included, in addition to the information required by Annex XV A, part I, all the information required by Annex XV A, part II, insofar as the latter information is available at the time the notice is published, and that the notice has been sent for publication between 52 days and 12 months before the date on which the contract notice referred to in Article 42(1)(c) is sent.

5.Where notices are drawn up and transmitted by electronic means in accordance with the format and procedures for transmission indicated in point 3 of Annex XX the time-limits for the receipt of requests to participate in restricted and negotiated procedures, and for receipt of tenders in open procedures, may be reduced by seven days.

6.Except in the case of a time limit set by mutual agreement in accordance with paragraph 3(b), time limits for the receipt of tenders in open, restricted and negotiated procedures may be further reduced by five days where the contracting entity offers unrestricted and full direct access to the contract documents and any supplementary documents by electronic means from the date on which the notice used as a means of calling for competition is published, in accordance with Annex XX. The notice should specify the internet address at which this documentation is accessible.

7.In open procedures, the cumulative effect of the reductions provided for in paragraphs 4, 5 and 6 may in no case result in a time limit for the receipt of tenders of less than 15 days from the date on which the contract notice is sent.

However, if the contract notice is not transmitted by fax or electronic means, the cumulative effect of the reductions provided for in paragraphs 4, 5 and 6 may in no case result in a time limit for receipt of tenders in an open procedure of less than 22 days from the date on which the contract notice is transmitted.

8.The cumulative effect of the reductions provided for in paragraphs 4, 5 and 6 may in no case result in a time limit for receipt of requests to participate, in response to a notice published under Article 42(1)(c), or in response to an invitation by the contracting entities under Article 47(5), of less than 15 days from the date on which the contract notice or invitation is sent.

In restricted and negotiated procedures, the cumulative effect of the reductions provided for in paragraphs 4, 5 and 6 may in no case, except that of a time limit set by mutual agreement in accordance with paragraph 3(b), result in a time limit for the receipt of tenders of less than 10 days from the date of the invitation to tender.

9.If, for whatever reason, the contract documents and the supporting documents or additional information, although requested in good time, have not been supplied within the time limits set in Articles 46 and 47, or where tenders can be made only after a visit to the site or after on-the-spot inspection of the documents supporting the contract documents, the time limits for the receipt of tenders shall be extended accordingly, except in the case of a time-limit set by mutual agreement in accordance with paragraph 3(b), so that all economic operators concerned may be aware of all the information needed for the preparation of a tender.

10.A summary table of the time limits laid down in this Article is given in Annex XXII.

Article 46U.K.Open procedures: specifications, additional documents and information

1.In open procedures, where contracting entities do not offer unrestricted and full direct access by electronic means in accordance with Article 45(6) to the specifications and any supporting documents, the specifications and supporting documents shall be sent to economic operators within six days of receipt of the request, provided that the request was made in good time before the time limit for the submission of tenders.

2.Provided that it has been requested in good time, additional information relating to the specifications shall be supplied by the contracting entities or competent departments not later than six days before the time limit fixed for the receipt of tenders.

Article 47U.K.Invitations to submit a tender or to negotiate

1.In restricted procedures and negotiated procedures, contracting entities shall simultaneously and in writing invite the selected candidates to submit their tenders or to negotiate. The invitation to the candidates shall include either:

  • a copy of the specifications and any supporting documents, or

  • a reference to accessing the specifications and the supporting documents indicated in the first indent, when they are made directly available by electronic means in accordance with Article 45(6).

2.Where the specifications and/or any supporting documents are held by an entity other than the contracting entity responsible for the award procedure, the invitation shall state the address from which those specifications and documents may be requested and, if appropriate, the closing date for requesting such documents, the sum payable for obtaining them and any payment procedures. The competent department shall send that documentation to the economic operator immediately upon receipt of the request.

3.The additional information on the specifications or the supporting documents shall be sent by the contracting entity or the competent department not less than six days before the final date fixed for the receipt of tenders, provided that it is requested in good time.

4.In addition, the invitation shall include at least the following:

(a)where appropriate, the time limit for requesting additional documents, as well as the amount and terms of payment of any sum to be paid for such documents;

(b)the final date for receipt of tenders, the address to which they are to be sent, and the language or languages in which they are to be drawn up;

(c)a reference to any published contract notice;

(d)an indication of any documents to be attached;

(e)the criteria for the award of the contract, where they are not indicated in the notice on the existence of a qualification system used as a means of calling for competition;

(f)the relative weighting of the contract award criteria or, where appropriate, the order of importance of such criteria, if this information is not given in the contract notice, the notice on the existence of a qualification system or the specifications.

5.When a call for competition is made by means of a periodic indicative notice, contracting entities shall subsequently invite all candidates to confirm their interest on the basis of detailed information on the contract concerned before beginning the selection of tenderers or participants in negotiations.

This invitation shall include at least the following information:

(a)nature and quantity, including all options concerning complementary contracts and, if possible, the estimated time available for exercising these options for renewable contracts, the nature and quantity and, if possible, the estimated publication dates of future notices of competition for works, supplies or services to be put out to tender;

(b)type of procedure: restricted or negotiated;

(c)where appropriate, the date on which the delivery of supplies or the execution of works or services is to commence or terminate;

(d)the address and closing date for the submission of requests for tender documents and the language or languages in which they are to be drawn up;

(e)the address of the entity which is to award the contract and the information necessary for obtaining the specifications and other documents;

(f)economic and technical conditions, financial guarantees and information required from economic operators;

(g)the amount and payment procedures for any sum payable for obtaining tender documents;

(h)the form of the contract which is the subject of the invitation to tender: purchase, lease, hire or hire-purchase, or any combination of these; and

(i)the contract award criteria and their weighting or, where appropriate, the order of importance of such criteria, if this information is not given in the indicative notice or the specifications or in the invitation to tender or to negotiate.

Section 3U.K.Communication and information

Article 48U.K.Rules applicable to communication

1.All communication and information exchange referred to in this Title may be carried out by post, by fax, by electronic means in accordance with paragraphs 4 and 5, by telephone in the cases and circumstances referred to in paragraph 6, or by a combination of those means, according to the choice of the contracting entity.

2.The means of communication chosen shall be generally available and thus not restrict economic operators' access to the tendering procedure.

3.Communication and the exchange and storage of information shall be carried out in such a way as to ensure that the integrity of data and the confidentiality of tenders and requests to participate are preserved, and that the contracting entities examine the content of tenders and requests to participate only after the time limit set for submitting them has expired.

4.The tools to be used for communicating by electronic means, as well as their technical characteristics, shall be non-discriminatory, generally available and interoperable with the information and communication technology products in general use.

5.The following rules are applicable to devices for the electronic transmission and receipt of tenders and to devices for the electronic receipt of requests to participate:

(a)information regarding the specifications necessary for the electronic submission of tenders and requests to participate, including encryption, shall be available to interested parties. Moreover, the devices for the electronic receipt of tenders and requests to participate shall conform to the requirements of Annex XXIV;

(b)Member States may, in compliance with Article 5 of Directive 1999/93/EC, require that electronic tenders be accompanied by an advanced electronic signature in conformity with paragraph 1 thereof;

(c)Member States may introduce or maintain voluntary accreditation schemes aiming at enhanced levels of certification service provision for these devices;

(d)tenderers or candidates shall undertake to submit, before expiry of the time limit laid down for the submission of tenders or requests to participate, the documents, certificates and declarations mentioned in Articles 52(2), 52(3), 53 and 54 if they do not exist in electronic format.

6.The following rules shall apply to the transmission of requests to participate:

(a)requests to participate in procedures for the award of contracts may be made in writing or by telephone;

(b)where requests to participate are made by telephone, a written confirmation must be sent before expiry of the time limit set for their receipt;

(c)contracting entities may require that requests for participation made by fax should be confirmed by post or by electronic means, where this is necessary for the purposes of legal proof. Any such requirement, together with the time limit for sending confirmation by post or electronic means, should be stated by the contracting entity in the notice used as a means of calling for competition or in the invitation referred to in Article 47(5).

Article 49U.K.Information to applicants for qualification, candidates and tenderers

1.Contracting entities shall as soon as possible inform the economic operators involved of decisions reached concerning the conclusion of a framework agreement, the award of the contract, or admission to a dynamic purchasing system, including the grounds for any decision not to conclude a framework agreement or award a contract for which there has been a call for competition or to recommence the procedure, or not to implement a dynamic purchasing system; this information shall be provided in writing if the contracting entities are requested to do so.

2.On request from the party concerned, contracting entities shall, as soon as possible, inform:

  • any unsuccessful candidate of the reasons for the rejection of his application,

  • any unsuccessful tenderer of the reasons for the rejection of his tender, including, for the cases referred to in Article 34(4) and (5), the reasons for their decision of non-equivalence or their decision that the works, supplies or services do not meet the performance or functional requirements,

  • any tenderer who has made an admissible tender of the characteristics and relative advantages of the tender selected, as well as the name of the successful tenderer or the parties to the framework agreement.

The time taken to do so may under no circumstances exceed 15 days from receipt of the written enquiry.

However, contracting entities may decide that certain information on the contract award or the conclusion of the framework agreement or on admission to a dynamic purchasing system, referred to in the paragraph 1, is to be withheld where release of such information would impede law enforcement or otherwise be contrary to the public interest or would prejudice the legitimate commercial interests of a particular economic operator, public or private, including the interests of the economic operator to whom the contract has been awarded, or might prejudice fair competition between economic operators.

3.Contracting entities which establish and operate a system of qualification shall inform applicants of their decision as to qualification within a period of six months.

If the decision will take longer than four months from the presentation of an application, the contracting entity shall inform the applicant, within two months of the application, of the reasons justifying the longer period and of the date by which his application will be accepted or refused.

4.Applicants whose qualification is refused shall be informed of this decision and the reasons for refusal as soon as possible and under no circumstances more than 15 days later than the date of the decision. The reasons shall be based on the criteria for qualification referred to in Article 53(2).

5.Contracting entities which establish and operate a system of qualification may bring the qualification of an economic operator to an end only for reasons based on the criteria for qualification referred to in Article 53(2). Any intention to bring qualification to an end shall be notified in writing to the economic operator beforehand, at least 15 days before the date on which qualification is due to end, together with the reason or reasons justifying the proposed action.

Article 50U.K.Information to be stored concerning awards

1.Contracting entities shall keep appropriate information on each contract which shall be sufficient to permit them at a later date to justify decisions taken in connection with:

(a)the qualification and selection of economic operators and the award of contracts;

(b)the use of procedures without a prior call for competition by virtue of Article 40(3);

(c)the non-application of Chapters III to VI of this Title by virtue of the derogations provided for in Chapter II of Title I and in Chapter II of this Title.

Contracting entities shall take appropriate steps to document the progress of award procedures conducted by electronic means.

2.The information shall be kept for at least four years from the date of award of the contract so that the contracting entity will be able, during that period, to provide the necessary information to the Commission if the latter so requests.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Directive

The Whole Directive you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources