Search Legislation

Directive 2004/18/EC of the European Parliament and of the Council (repealed)Show full title

Directive 2004/18/EC of the European Parliament and of the Council of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts (repealed)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Status:

EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.

Article 31U.K.Cases justifying use of the negotiated procedure without publication of a contract notice

Contracting authorities may award public contracts by a negotiated procedure without prior publication of a contract notice in the following cases:

(1)

for public works contracts, public supply contracts and public service contracts:

(a)

when no tenders or no suitable tenders or no applications have been submitted in response to an open procedure or a restricted procedure, provided that the initial conditions of contract are not substantially altered and on condition that a report is sent to the Commission if it so requests;

(b)

when, for technical or artistic reasons, or for reasons connected with the protection of exclusive rights, the contract may be awarded only to a particular economic operator;

(c)

insofar as is strictly necessary when, for reasons of extreme urgency brought about by events unforeseeable by the contracting authorities in question, the time limit for the open, restricted or negotiated procedures with publication of a contract notice as referred to in Article 30 cannot be complied with. The circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authority;

(2)

for public supply contracts:

(a)

when the products involved are manufactured purely for the purpose of research, experimentation, study or development; this provision does not extend to quantity production to establish commercial viability or to recover research and development costs;

(b)

for additional deliveries by the original supplier which are intended either as a partial replacement of normal supplies or installations or as the extension of existing supplies or installations where a change of supplier would oblige the contracting authority to acquire material having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance; the length of such contracts as well as that of recurrent contracts may not, as a general rule, exceed three years;

(c)

for supplies quoted and purchased on a commodity market;

(d)

for the purchase of supplies on particularly advantageous terms, from either a supplier which is definitively winding up its business activities, or the receivers or liquidators of a bankruptcy, an arrangement with creditors, or a similar procedure under national laws or regulations;

(3)

for public service contracts, when the contract concerned follows a design contest and must, under the applicable rules, be awarded to the successful candidate or to one of the successful candidates, in the latter case, all successful candidates must be invited to participate in the negotiations;

(4)

for public works contracts and public service contracts:

(a)

for additional works or services not included in the project initially considered or in the original contract but which have, through unforeseen circumstances, become necessary for the performance of the works or services described therein, on condition that the award is made to the economic operator performing such works or services:

  • when such additional works or services cannot be technically or economically separated from the original contract without major inconvenience to the contracting authorities,

    or

  • when such works or services, although separable from the performance of the original contract, are strictly necessary for its completion.

However, the aggregate value of contracts awarded for additional works or services may not exceed 50 % of the amount of the original contract;

(b)

for new works or services consisting in the repetition of similar works or services entrusted to the economic operator to whom the same contracting authorities awarded an original contract, provided that such works or services are in conformity with a basic project for which the original contract was awarded according to the open or restricted procedure.

As soon as the first project is put up for tender, the possible use of this procedure shall be disclosed and the total estimated cost of subsequent works or services shall be taken into consideration by the contracting authorities when they apply the provisions of Article 7.

This procedure may be used only during the three years following the conclusion of the original contract.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Directive

The Whole Directive you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources