Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.
1.Member States shall ensure the implementation of a system of third party access to the transmission and distribution systems based on published tariffs, applicable to all eligible customers and applied objectively and without discrimination between system users. Member States shall ensure that those tariffs, or the methodologies underlying their calculation, are approved prior to their entry into force in accordance with Article 37 and that those tariffs, and the methodologies — where only methodologies are approved — are published prior to their entry into force.
2.The transmission or distribution system operator may refuse access where it lacks the necessary capacity. Duly substantiated reasons must be given for such refusal, in particular having regard to Article 3, and based on objective and technically and economically justified criteria. The regulatory authorities where Member States have so provided or Member States shall ensure that those criteria are consistently applied and that the system user who has been refused access can make use of a dispute settlement procedure. The regulatory authorities shall also ensure, where appropriate and when refusal of access takes place, that the transmission or distribution system operator provides relevant information on measures that would be necessary to reinforce the network. The party requesting such information may be charged a reasonable fee reflecting the cost of providing such information.
1.Member States shall ensure that the eligible customers comprise:
(a)until 1 July 2004, the eligible customers as specified in Article 19(1) to (3) of Directive 96/92/EC. Member States shall publish by 31 January each year the criteria for the definition of those eligible customers;
(b)from 1 July 2004, all non-household customers;
(c)from 1 July 2007, all customers.
2.To avoid imbalance in the opening of electricity markets:
(a)contracts for the supply of electricity with an eligible customer in the system of another Member State shall not be prohibited if the customer is considered as eligible in both systems involved; and
(b)where transactions as described in point (a) are refused because the customer is eligible in only one of the two systems, the Commission may, taking into account the situation in the market and the common interest, oblige the refusing party to execute the requested supply at the request of the Member State where the eligible customer is located.
1.Member States shall take the measures necessary to enable:
(a)all electricity producers and electricity supply undertakings established within their territory to supply their own premises, subsidiaries and eligible customers through a direct line; and
(b)all eligible customers within their territory to be supplied through a direct line by a producer and supply undertakings.
2.Member States shall lay down the criteria for the grant of authorisations for the construction of direct lines in their territory. Those criteria shall be objective and non-discriminatory.
3.The possibility of supplying electricity through a direct line as referred to in paragraph 1 of this Article shall not affect the possibility of contracting electricity in accordance with Article 32.
4.Member States may issue an authorisation to construct a direct line subject either to the refusal of system access on the basis, as appropriate, of Article 32 or to the opening of a dispute settlement procedure under Article 37.
5.Member States may refuse to authorise a direct line if the granting of such an authorisation would obstruct the provisions of Article 3. Duly substantiated reasons shall be given for such refusal.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: