Directive 2014/24/EU of the European Parliament and of the CouncilShow full title

Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (Text with EEA relevance)

Article 71U.K.Subcontracting

1.Observance of the obligations referred to in Article 18(2) by subcontractors is ensured through appropriate action by the competent national authorities acting within the scope of their responsibility and remit.

2.In the procurement documents, the contracting authority may ask or may be required by a Member State to ask the tenderer to indicate in its tender any share of the contract it may intend to subcontract to third parties and any proposed subcontractors.

3.Member States may provide that at the request of the subcontractor and where the nature of the contract so allows, the contracting authority shall transfer due payments directly to the subcontractor for services, supplies or works provided to the economic operator to whom the public contract has been awarded (the main contractor). Such measures may include appropriate mechanisms permitting the main contractor to object to undue payments. The arrangements concerning that mode of payment shall be set out in the procurement documents.

4.Paragraphs 1 to 3 shall be without prejudice to the question of the main contractor’s liability.

5.In the case of works contracts and in respect of services to be provided at a facility under the direct oversight of the contracting authority, after the award of the contract and at the latest when the performance of the contract commences, the contracting authority shall require the main contractor to indicate to the contracting authority the name, contact details and legal representatives of its subcontractors, involved in such works or services, in so far as known at this point in time. The contracting authority shall require the main contractor to notify the contracting authority of any changes to this information during the course of the contract as well as of the required information for any new subcontractors which it subsequently involves in such works or services.

Notwithstanding the first subparagraph, Member States may impose the obligation to deliver the required information directly on the main contractor.

Where necessary for the purposes of point (b) of paragraph 6 of this Article, the required information shall be accompanied by the subcontractors’ self-declarations as provided for in Article 59. The implementing measures pursuant to paragraph 8 of this Article may provide that subcontractors which are presented after the award of the contract shall provide the certificates and other supporting documents instead of the self-declaration.

The first subparagraph shall not apply to suppliers.

Contracting authorities may extend or may be required by Member States to extend the obligations provided for in the first subparagraph to for instance:

(a)supply contracts, to services contracts other than those concerning services to be provided at the facilities under the direct oversight of the contracting authority or to suppliers involved in works or services contracts;

(b)subcontractors of the main contractor’s subcontractors or further down the subcontracting chain.

6.With the aim of avoiding breaches of the obligations referred to in Article 18(2), appropriate measures may be taken, such as:

(a)Where the national law of a Member State provides for a mechanism of joint liability between subcontractors and the main contractor, the Member State concerned shall ensure that the relevant rules are applied in compliance with the conditions set out in Article 18(2).

(b)Contracting authorities may, in accordance with Articles 59, 60 and 61, verify or may be required by Member States to verify whether there are grounds for exclusion of subcontractors pursuant to Article 57. In such cases, the contracting authority shall require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are compulsory grounds for exclusion. The contracting authority may require or may be required by a Member State to require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are non-compulsory grounds for exclusion.

7.Member States may provide for more stringent liability rules under national law or to go further under national law on direct payments to subcontractors, for instance by providing for direct payments to subcontractors without it being necessary for them to request such direct payment.

8.Member States having chosen to provide for measures pursuant to paragraphs 3, 5 or 6 shall, by law, regulation or administrative provisions and having regard for Union law, specify the implementing conditions for those measures. In so doing, Member States may limit their applicability, for instance in respect of certain types of contracts, certain categories of contacting authorities or economic operators or as of certain amounts.