Search Legislation

Directive 2014/24/EU of the European Parliament and of the CouncilShow full title

Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Status:

EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.

CHAPTER IV U.K. Contract performance

Article 70U.K.Conditions for performance of contracts

Contracting authorities may lay down special conditions relating to the performance of a contract, provided that they are linked to the subject-matter of the contract within the meaning of Article 67(3) and indicated in the call for competition or in the procurement documents. Those conditions may include economic, innovation-related, environmental, social or employment-related considerations.

Article 71U.K.Subcontracting

1.Observance of the obligations referred to in Article 18(2) by subcontractors is ensured through appropriate action by the competent national authorities acting within the scope of their responsibility and remit.

2.In the procurement documents, the contracting authority may ask or may be required by a Member State to ask the tenderer to indicate in its tender any share of the contract it may intend to subcontract to third parties and any proposed subcontractors.

3.Member States may provide that at the request of the subcontractor and where the nature of the contract so allows, the contracting authority shall transfer due payments directly to the subcontractor for services, supplies or works provided to the economic operator to whom the public contract has been awarded (the main contractor). Such measures may include appropriate mechanisms permitting the main contractor to object to undue payments. The arrangements concerning that mode of payment shall be set out in the procurement documents.

4.Paragraphs 1 to 3 shall be without prejudice to the question of the main contractor’s liability.

5.In the case of works contracts and in respect of services to be provided at a facility under the direct oversight of the contracting authority, after the award of the contract and at the latest when the performance of the contract commences, the contracting authority shall require the main contractor to indicate to the contracting authority the name, contact details and legal representatives of its subcontractors, involved in such works or services, in so far as known at this point in time. The contracting authority shall require the main contractor to notify the contracting authority of any changes to this information during the course of the contract as well as of the required information for any new subcontractors which it subsequently involves in such works or services.

Notwithstanding the first subparagraph, Member States may impose the obligation to deliver the required information directly on the main contractor.

Where necessary for the purposes of point (b) of paragraph 6 of this Article, the required information shall be accompanied by the subcontractors’ self-declarations as provided for in Article 59. The implementing measures pursuant to paragraph 8 of this Article may provide that subcontractors which are presented after the award of the contract shall provide the certificates and other supporting documents instead of the self-declaration.

The first subparagraph shall not apply to suppliers.

Contracting authorities may extend or may be required by Member States to extend the obligations provided for in the first subparagraph to for instance:

(a)supply contracts, to services contracts other than those concerning services to be provided at the facilities under the direct oversight of the contracting authority or to suppliers involved in works or services contracts;

(b)subcontractors of the main contractor’s subcontractors or further down the subcontracting chain.

6.With the aim of avoiding breaches of the obligations referred to in Article 18(2), appropriate measures may be taken, such as:

(a)Where the national law of a Member State provides for a mechanism of joint liability between subcontractors and the main contractor, the Member State concerned shall ensure that the relevant rules are applied in compliance with the conditions set out in Article 18(2).

(b)Contracting authorities may, in accordance with Articles 59, 60 and 61, verify or may be required by Member States to verify whether there are grounds for exclusion of subcontractors pursuant to Article 57. In such cases, the contracting authority shall require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are compulsory grounds for exclusion. The contracting authority may require or may be required by a Member State to require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are non-compulsory grounds for exclusion.

7.Member States may provide for more stringent liability rules under national law or to go further under national law on direct payments to subcontractors, for instance by providing for direct payments to subcontractors without it being necessary for them to request such direct payment.

8.Member States having chosen to provide for measures pursuant to paragraphs 3, 5 or 6 shall, by law, regulation or administrative provisions and having regard for Union law, specify the implementing conditions for those measures. In so doing, Member States may limit their applicability, for instance in respect of certain types of contracts, certain categories of contacting authorities or economic operators or as of certain amounts.

Article 72U.K.Modification of contracts during their term

1.Contracts and framework agreements may be modified without a new procurement procedure in accordance with this Directive in any of the following cases:

(a)where the modifications, irrespective of their monetary value, have been provided for in the initial procurement documents in clear, precise and unequivocal review clauses, which may include price revision clauses, or options. Such clauses shall state the scope and nature of possible modifications or options as well as the conditions under which they may be used. They shall not provide for modifications or options that would alter the overall nature of the contract or the framework agreement;

(b)for additional works, services or supplies by the original contractor that have become necessary and that were not included in the initial procurement where a change of contractor:

(i)

cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement; and

(ii)

would cause significant inconvenience or substantial duplication of costs for the contracting authority.

However, any increase in price shall not exceed 50 % of the value of the original contract. Where several successive modifications are made, that limitation shall apply to the value of each modification. Such consecutive modifications shall not be aimed at circumventing this Directive;

(c)where all of the following conditions are fulfilled:

(i)

the need for modification has been brought about by circumstances which a diligent contracting authority could not foresee;

(ii)

the modification does not alter the overall nature of the contract;

(iii)

any increase in price is not higher than 50 % of the value of the original contract or framework agreement. Where several successive modifications are made, that limitation shall apply to the value of each modification. Such consecutive modifications shall not be aimed at circumventing this Directive;

(d)where a new contractor replaces the one to which the contracting authority had initially awarded the contract as a consequence of either:

(i)

an unequivocal review clause or option in conformity with point (a);

(ii)

universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Directive; or

(iii)

in the event that the contracting authority itself assumes the main contractor’s obligations towards its subcontractors where this possibility is provided for under national legislation pursuant to Article 71;

(e)where the modifications, irrespective of their value, are not substantial within the meaning of paragraph 4.

Contracting authorities having modified a contract in the cases set out under points (b) and (c) of this paragraph shall publish a notice to that effect in the Official Journal of the European Union. Such notice shall contain the information set out in Annex V part G and shall be published in accordance with Article 51.

2.Furthermore, and without any need to verify whether the conditions set out under points (a) to (d) of paragraph 4 are met, contracts may equally be modified without a new procurement procedure in accordance with this Directive being necessary where the value of the modification is below both of the following values:

(i)

the thresholds set out in Article 4; and

(ii)

10 % of the initial contract value for service and supply contracts and below 15 % of the initial contract value for works contracts.

However, the modification may not alter the overall nature of the contract or framework agreement. Where several successive modifications are made, the value shall be assessed on the basis of the net cumulative value of the successive modifications.

3.For the purpose of the calculation of the price mentioned in paragraph 2 and points (b) and (c) of paragraph 1, the updated price shall be the reference value when the contract includes an indexation clause.

4.A modification of a contract or a framework agreement during its term shall be considered to be substantial within the meaning of point (e) of paragraph 1, where it renders the contract or the framework agreement materially different in character from the one initially concluded. In any event, without prejudice to paragraphs 1 and 2, a modification shall be considered to be substantial where one or more of the following conditions is met:

(a)the modification introduces conditions which, had they been part of the initial procurement procedure, would have allowed for the admission of other candidates than those initially selected or for the acceptance of a tender other than that originally accepted or would have attracted additional participants in the procurement procedure;

(b)the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement;

(c)the modification extends the scope of the contract or framework agreement considerably;

(d)where a new contractor replaces the one to which the contracting authority had initially awarded the contract in other cases than those provided for under point (d) of paragraph 1.

5.A new procurement procedure in accordance with this Directive shall be required for other modifications of the provisions of a public contract or a framework agreement during its term than those provided for under paragraphs 1 and 2.

Article 73U.K.Termination of contracts

Member States shall ensure that contracting authorities have the possibility, at least under the following circumstances and under the conditions determined by the applicable national law, to terminate a public contract during its term, where:

(a)

the contract has been subject to a substantial modification, which would have required a new procurement procedure pursuant to Article 72;

(b)

the contractor has, at the time of contract award, been in one of the situations referred to in Article 57(1) and should therefore have been excluded from the procurement procedure;

(c)

the contract should not have been awarded to the contractor in view of a serious infringement of the obligations under the Treaties and this Directive that has been declared by the Court of Justice of the European Union in a procedure pursuant to Article 258 TFEU.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Directive

The Whole Directive you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources