Council Regulation (EC) No 6/2002 of 12 December 2001 on Community designs
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
Point in time view as at 01/01/2007.
There are currently no known outstanding effects for the Council Regulation (EC) No 6/2002, TITLE VI.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.The surrender of a registered Community design shall be declared to the Office in writing by the right holder. It shall not have effect until it has been entered in the register.
2.If a Community design which is subject to deferment of publication is surrendered it shall be deemed from the outset not to have had the effects specified in this Regulation.
3.A registered Community design may be partially surrendered provided that its amended form complies with the requirements for protection and the identity of the design is retained.
4.Surrender shall be registered only with the agreement of the proprietor of a right entered in the register. If a licence has been registered, surrender shall be entered in the register only if the right holder in the registered Community design proves that he has informed the licensee of his intention to surrender. This entry shall be made on expiry of the period prescribed by the implementing regulation.
5.If an action pursuant to Article 14 relating to the entitlement to a registered Community design has been brought before a Community design court, the Office shall not enter the surrender in the register without the agreement of the claimant.
1.Subject to Article 25(2), (3), (4) and (5), any natural or legal person, as well as a public authority empowered to do so, may submit to the Office an application for a declaration of invalidity of a registered Community design.
2.The application shall be filed in a written reasoned statement. It shall not be deemed to have been filed until the fee for an application for a declaration of invalidity has been paid.
3.An application for a declaration of invalidity shall not be admissible if an application relating to the same subject matter and cause of action, and involving the same parties, has been adjudicated on by a Community design court and has acquired the authority of a final decision.
1.If the Office finds that the application for a declaration of invalidity is admissible, the Office shall examine whether the grounds for invalidity referred to in Article 25 prejudice the maintenance of the registered Community design.
2.In the examination of the application, which shall be conducted in accordance with the implementing regulation, the Office shall invite the parties, as often as necessary, to file observations, within a period to be fixed by the Office, on communications from the other parties or issued by itself.
3.The decision declaring the registered Community design invalid shall be entered in the register upon becoming final.
1.In the event of an application for a declaration of invalidity of a registered Community design being filed, and as long as no final decision has been taken by the Office, any third party who proves that proceedings for infringement of the same design have been instituted against him may be joined as a party in the invalidity proceedings on request submitted within three months of the date on which the infringement proceedings were instituted.
The same shall apply in respect of any third party who proves both that the right holder of the Community design has requested that he cease an alleged infringement of the design and that he has instituted proceedings for a court ruling that he is not infringing the Community design.
2.The request to be joined as a party shall be filed in a written reasoned statement. It shall not be deemed to have been filed until the invalidity fee, referred to in Article 52(2), has been paid. Thereafter the request shall, subject to any exceptions laid down in the implementing regulation, be treated as an application for a declaration of invalidity.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: