Search Legislation

Regulation (EC) No 714/2009 of the European Parliament and of the Council (repealed)Show full title

Regulation (EC) No 714/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation (EC) No 1228/2003 (Text with EEA relevance) (repealed)

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Status:

Point in time view as at 13/07/2009. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

There are currently no known outstanding effects for the Regulation (EC) No 714/2009 of the European Parliament and of the Council (repealed), Article 18. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 18U.K.Guidelines

1.Where appropriate, Guidelines relating to the inter-transmission system operator compensation mechanism shall specify, in accordance with the principles set out in Articles 13 and 14:

(a)details of the procedure for determining which transmission system operators are liable to pay compensation for cross-border flows including as regards the split between the operators of national transmission systems from which cross-border flows originate and the systems where those flows end, in accordance with Article 13(2);

(b)details of the payment procedure to be followed, including the determination of the first period for which compensation is to be paid, in accordance with the second subparagraph of Article 13(3);

(c)details of methodologies for determining the cross-border flows hosted for which compensation is to be paid under Article 13, in terms of both quantity and type of flows, and the designation of the magnitudes of such flows as originating and/or ending in transmission systems of individual Member States, in accordance with Article 13(5);

(d)details of the methodology for determining the costs and benefits incurred as a result of hosting cross-border flows, in accordance with Article 13(6);

(e)details of the treatment in the context of the inter-transmission system operator compensation mechanism of electricity flows originating or ending in countries outside the European Economic Area; and

(f)the participation of national systems which are interconnected through direct current lines, in accordance with Article 13.

2.Guidelines may also determine appropriate rules leading to a progressive harmonisation of the underlying principles for the setting of charges applied to producers and consumers (load) under national tariff systems, including the reflection of the inter-transmission system operator compensation mechanism in national network charges and the provision of appropriate and efficient locational signals, in accordance with the principles set out in Article 14.

The Guidelines shall make provision for appropriate and efficient harmonised locational signals at Community level.

Any such harmonisation shall not prevent Member States from applying mechanisms to ensure that network access charges borne by consumers (load) are comparable throughout their territory.

3.Where appropriate, Guidelines providing the minimum degree of harmonisation required to achieve the aim of this Regulation shall also specify:

(a)details relating to provision of information, in accordance with the principles set out in Article 15;

(b)details of rules for the trading of electricity;

(c)details of investment incentive rules for interconnector capacity including locational signals;

(d)details of the areas listed in Article 8(6).

For that purpose, the Commission shall consult the Agency and the ENTSO for Electricity.

4.Guidelines on the management and allocation of available transmission capacity of interconnections between national systems are laid down in Annex I.

5.The Commission may adopt Guidelines on the issues listed in paragraphs 1, 2 and 3 of this Article. It may amend the Guidelines referred to in paragraph 4 of this Article, in accordance with the principles set out in Articles 15 and 16, in particular so as to include detailed Guidelines on all capacity-allocation methodologies applied in practice and to ensure that congestion-management mechanisms evolve in a manner compatible with the objectives of the internal market. Where appropriate, in the course of such amendments common rules on minimum safety and operational standards for the use and operation of the network, as referred to in Article 15(2) shall be established. Those measures, designed to amend non-essential elements of this Regulation by supplementing it, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 23(2).

When adopting or amending Guidelines, the Commission shall:

(a)ensure that the Guidelines provide the minimum degree of harmonisation required to achieve the aims of this Regulation and do not go beyond what is necessary for that purpose; and

(b)indicate what actions it has taken with respect to the conformity of rules in third countries, which form part of the Community electricity system, with the Guidelines in question.

When adopting Guidelines under this Article for the first time, the Commission shall ensure that they cover in a single draft measure at least the issues referred to in points (a) and (d) of paragraph 1 and in paragraph 2.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources