Regulation (EC) No 715/2009 of the European Parliament and of the CouncilShow full title

Regulation (EC) No 715/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the natural gas transmission networks and repealing Regulation (EC) No 1775/2005 (Text with EEA relevance)

Article 5U.K.Establishment of the ENTSO for Gas

1.By 3 March 2011, the transmission system operators for gas shall submit to the Commission and to the Agency the draft statutes, a list of members and draft rules of procedure, including the rules of procedures on the consultation of other stakeholders, of the ENTSO for Gas to be established.

2.Within two months of the day of the receipt, the Agency, after formally consulting the organisations representing all stakeholders, in particular the system users including customers, shall provide an opinion to the Commission on the draft statutes, list of members and draft rules of procedure.

3.The Commission shall deliver an opinion on the draft statutes, list of members and draft rules of procedures taking into account the opinion of the Agency provided for in paragraph 2 and within three months of the day of the receipt of the opinion of the Agency.

4.Within three months of the day of receipt of the Commission's opinion, the transmission system operators shall establish the ENTSO for Gas, adopt and publish its statutes and rules of procedure.