ANNEX IList of hydrogen components to be type-approved

Where fitted to a hydrogen-powered vehicle, the following hydrogen components must be type-approved:

  1. (a)

    components designed to use liquid hydrogen:

    1. 1.

      container;

    2. 2.

      automatic shut-off valve;

    3. 3.

      check valve or non-return valve (if used as a safety device);

    4. 4.

      flexible fuel line (if upstream of first automatic shut-off valve or other safety devices);

    5. 5.

      heat exchanger;

    6. 6.

      manual or automatic valve;

    7. 7.

      pressure regulator;

    8. 8.

      pressure relief valve;

    9. 9.

      pressure, temperature and flow sensors (if used as a safety device);

    10. 10.

      refuelling connection or receptacle;

    11. 11.

      hydrogen leakage detection sensors;

  2. (b)

    components designed to use compressed (gaseous) hydrogen with a nominal working pressure of over 3,0 MPa:

    1. 1.

      container;

    2. 2.

      automatic shut-off valve;

    3. 3.

      container assembly;

    4. 4.

      fittings;

    5. 5.

      flexible fuel line;

    6. 6.

      heat exchanger;

    7. 7.

      hydrogen filter;

    8. 8.

      manual or automatic valve;

    9. 9.

      non-return valve;

    10. 10.

      pressure regulator;

    11. 11.

      pressure relief device;

    12. 12.

      pressure relief valve;

    13. 13.

      refuelling connection or receptacle;

    14. 14.

      removable storage system connector;

    15. 15.

      pressure, temperature, hydrogen and flow sensors (if used as a safety device);

    16. 16.

      hydrogen leakage detection sensors.

ANNEX IIApplicable test procedures for hydrogen containers designed to use liquid hydrogen

Type of test

Burst test

Bonfire test

Maximum filling level test

Pressure test

Leak test

The test procedures to be applied for the type-approval of hydrogen containers designed to use liquid hydrogen must include:

  1. (a)

    Burst test: the purpose of the test is to provide evidence that the hydrogen container does not fail before a specified level of high pressure, the burst pressure (safety factor multiplied by the MAWP) is exceeded. In order to obtain type-approval, the value of the real burst pressure during the test must exceed the required minimum burst pressure.

  2. (b)

    Bonfire test: the purpose of the test is to provide evidence that the container with its fire protection system does not burst when tested under specified fire conditions.

  3. (c)

    Maximum filling level test: the purpose of the test is to provide evidence that the system, which prevents overfilling of the container, works adequately and that the level of hydrogen during the filling procedure never causes the opening of the pressure relief devices.

  4. (d)

    Pressure test: the purpose of the test is to provide evidence that the hydrogen container can withstand a specified level of high pressure. In order to prove this, the container is pressurised to a given value for a specified time. After the test the container must not show any signs of visible permanent deformation or visible leaks.

  5. (e)

    Leak test: the purpose of the test is to provide evidence that the hydrogen container does not show evidence of leakage under specified conditions. In order to prove this, the container is pressurised to its nominal working pressure. It must not show any evidence of leakage detected through cracks, pores or other similar defects.

ANNEX IIIApplicable test procedures for hydrogen components, other than containers, designed to use liquid hydrogen

TYPE OF TEST

HYDROGEN COMPONENT

Pressure test

External leakage test

Endurance test

Operational test

Corrosion resistance test

Resistance to dry-heat test

Ozone ageing test

Temperature cycle test

Pressure cycle test

Hydrogen compatibility test

Seat leakage test

Pressure relief devices

Image_r00001

Image_r00002

Image_r00003

Image_r00004

Image_r00005

Image_r00006

Valves

Image_r00007

Image_r00008

Image_r00009

Image_r00010

Image_r00011

Image_r00012

Image_r00013

Image_r00014

Image_r00015

Heat exchangers

Image_r00016

Image_r00017

Image_r00018

Image_r00019

Image_r00020

Image_r00021

Image_r00022

Refuelling connections or receptacles

Image_r00023

Image_r00024

Image_r00025

Image_r00026

Image_r00027

Image_r00028

Image_r00029

Image_r00030

Image_r00031

Pressure regulators

Image_r00032

Image_r00033

Image_r00034

Image_r00035

Image_r00036

Image_r00037

Image_r00038

Image_r00039

Image_r00040

Sensors

Image_r00041

Image_r00042

Image_r00043

Image_r00044

Image_r00045

Image_r00046

Image_r00047

Flexible fuel lines

Image_r00048

Image_r00049

Image_r00050

Image_r00051

Image_r00052

Image_r00053

Image_r00054

Image_r00055

Subject to specific requirements in relation to any of the hydrogen components, the test procedures to be applied for the type-approval of hydrogen components, other than containers, designed to use liquid hydrogen must include:

  1. (a)

    Pressure test: the purpose of the test is to provide evidence that the hydrogen components can withstand a level of pressure which is higher than the working pressure of the component. The hydrogen components must not show any visible evidence of leak, deformation, rupture or cracks when the pressure is increased to a certain level.

  2. (b)

    External leakage test: the purpose of the test is to provide evidence that the hydrogen components are free from external leakage. The hydrogen components must not show evidence of porosity.

  3. (c)

    Endurance test: the purpose of the test is to provide evidence that the hydrogen components are capable of continuous reliable operation. The test consists of carrying out a specific number of test cycles for the hydrogen component under specified temperature and pressure conditions. A test cycle means the normal operation (i.e. one opening and one closing) of the hydrogen component.

  4. (d)

    Operational test: the purpose of the test is to provide evidence that the hydrogen components are capable of operating reliably.

  5. (e)

    Corrosion resistance test: the purpose of the test is to provide evidence that the hydrogen components are capable of resisting corrosion. In order to prove this, the hydrogen components are submitted to contact with specified chemicals.

  6. (f)

    Resistance to dry-heat test: the purpose of the test is to provide evidence that the non-metallic hydrogen components are capable of resisting high temperature. In order to prove this, the components are exposed to air at the maximum operating temperature.

  7. (g)

    Ozone ageing test: the purpose of the test is to provide evidence that the non-metallic hydrogen components are capable of resisting ageing due to ozone. In order to prove this, the components are exposed to air with high ozone concentration.

  8. (h)

    Temperature cycle test: the purpose of the test is to provide evidence that the hydrogen components are capable of resisting high variations of temperature. In order to prove this, the hydrogen components are submitted to a temperature cycle of specified duration from the minimum operating temperature up to the maximum operating temperature.

  9. (i)

    Pressure cycle test: the purpose of the test is to provide evidence that the hydrogen components are capable of resisting high variations of pressure. In order to prove this, the hydrogen components are submitted to a pressure change from atmospheric pressure to the maximum allowable working pressure (MAWP) and then back to atmospheric pressure within a short period of time.

  10. (j)

    Hydrogen compatibility test: the purpose of the test is to provide evidence that metallic hydrogen components (i.e. cylinders and valves) are not susceptible to hydrogen embrittlement. In hydrogen components that are subjected to frequent load cycles, conditions that can lead to local fatigue and the initiation and propagation of fatigue cracks in the structure must be avoided.

  11. (k)

    Seat leakage test: the purpose of the test is to provide evidence that hydrogen components are free from leakage while installed in the hydrogen system.

ANNEX IVApplicable test procedures for hydrogen containers designed to use compressed (gaseous) hydrogen

Type of test

Applicable to container type

1

2

3

4

Burst test

Image_r00056

Image_r00057

Image_r00058

Image_r00059

Ambient temperature pressure cycle test

Image_r00060

Image_r00061

Image_r00062

Image_r00063

LBB performance test

Image_r00064

Image_r00065

Image_r00066

Image_r00067

Bonfire test

Image_r00068

Image_r00069

Image_r00070

Image_r00071

Penetration test

Image_r00072

Image_r00073

Image_r00074

Image_r00075

Chemical exposure test

Image_r00076

Image_r00077

Image_r00078

Composite flaw tolerance test

Image_r00079

Image_r00080

Image_r00081

Accelerated stress rupture test

Image_r00082

Image_r00083

Image_r00084

Extreme temperature pressure cycle test

Image_r00085

Image_r00086

Image_r00087

Impact damage test

Image_r00088

Image_r00089

Leak test

Image_r00090

Permeation test

Image_r00091

Boss torque test

Image_r00092

Hydrogen gas cycle test

Image_r00093

1.

Classification of hydrogen containers designed to use compressed (gaseous) hydrogen:

Type 1

Seamless metallic container

Type 2

Hoop wrapped container with a seamless metallic liner

Type 3

Fully wrapped container with a seamless or welded metallic liner

Type 4

Fully wrapped container with a non-metallic liner.

2.

The test procedures to be applied for the type-approval of hydrogen containers designed to use compressed (gaseous) hydrogen must include:

  1. (a)

    Burst test: the purpose of the test is to provide the value of the pressure at which the container bursts. In order to prove this, the container is pressurised to a given value, which must be higher than the nominal working pressure of the container. The burst pressure of the container must exceed a specified pressure. The burst pressure of the container must be recorded and be kept by the manufacturer throughout the service life of the container.

  2. (b)

    Ambient temperature pressure cycle test: the purpose of the test is to provide evidence that the hydrogen container is capable of resisting high variations of pressure. In order to prove this, pressure cycles are carried out on the container until a failure occurs or until a specified number of cycles is reached by increasing and decreasing the pressure to a specified value. The containers must not fail before reaching a specified number of cycles. The number of cycles to failure, along with the location and description of the failure, must be documented. The manufacturer must keep the results throughout the service life of the container.

  3. (c)

    Leak before break (LBB) performance test: the purpose of the test is to provide evidence that the hydrogen container fails by leakage before rupture. In order to prove this, pressure cycles are carried out on the container by increasing and decreasing the pressure to a specified value. The containers tested must either fail by leakage or exceed a specified number of test cycles without failure. The number of cycles to failure, along with the location and description of the failure, must be recorded.

  4. (d)

    Bonfire test: the purpose of the test is to provide evidence that the container with its fire protection system does not burst when tested under specified fire conditions. The container, pressurised to working pressure, must only vent through the pressure relief device and must not rupture.

  5. (e)

    Penetration test: the purpose of the test is to provide evidence that the container does not rupture when penetrated by a bullet. In order to prove this, the complete container with its protective coating is pressurised and penetrated by a bullet. The container must not rupture.

  6. (f)

    Chemical exposure test: the purpose of the test is to provide evidence that the container can withstand exposure to specified chemical substances. In order to prove this, the container is exposed to various chemical solutions. The pressure of the container is increased to a given value and a burst test as referred to under point (a) is carried out. The container must achieve a specified burst pressure, which must be recorded.

  7. (g)

    Composite flaw tolerance test: the purpose of the test is to provide evidence that the hydrogen container is capable of resisting exposure to high pressure. In order to prove this, flaws of specified geometry are cut into the container sidewall and a specified number of pressure cycles carried out. The container must not leak or rupture within a number of cycles, but may fail by leakage during the remaining test cycles. The number of cycles to failure, along with the location and description of the failure, must be recorded.

  8. (h)

    Accelerated stress rupture test: the purpose of the test is to provide evidence that the hydrogen container is capable of resisting exposure to high pressure and high temperatures at the limit of the allowable operating range for an extended period of time. In order to prove this, the container is exposed for a specified time to specified pressure and temperature conditions, and subsequently undergoes a burst test as referred to under point (a). The container must achieve a specified burst pressure.

  9. (i)

    Extreme temperature pressure cycle test: the purpose of the test is to provide evidence that the hydrogen container can withstand variations of pressure under different temperature conditions. In order to prove this, the container, free of any protective coating, is hydrostatically cycle tested by being subjected to extreme ambient conditions, and subsequently undergoes a burst test and a leak test as referred to under points (a) and (k). When cycle tested, the containers must not show evidence of rupture, leakage or fibre unravelling. The containers must not burst at a specified pressure.

  10. (j)

    Impact damage test: the purpose of the test is to provide evidence that the hydrogen container remains operational after being submitted to the specified mechanical impacts. In order to prove this, the container is subjected to a drop test, and a specified number of pressure cycles are carried out. The container must not leak or rupture within a specified number of cycles, but may fail by leakage during the remaining test cycles.

  11. (k)

    Leak test: the purpose of the test is to provide evidence that the hydrogen container does not show evidence of leakage under the specified conditions. In order to prove this, the container is pressurised to its nominal working pressure. It must not show any evidence of leakage detected through cracks, pores or similar defects.

  12. (l)

    Permeation test: the purpose of the test is to provide evidence that the hydrogen container does not permeate more than a specified rate. In order to prove this, the container is pressurised with hydrogen gas to nominal working pressure and then monitored for permeation in a closed chamber for a specified time under specified temperature conditions.

  13. (m)

    Boss torque test: the purpose of the test is to provide evidence that the hydrogen container is capable of resisting the specified torque. In order to prove this, a torque is applied to the container from different directions. Then a burst test and a leak test as referred to under points (a) and (k) are carried out. The container must meet the burst and leak test requirements. The applied torque, leakage and burst pressure must be recorded.

  14. (n)

    Hydrogen gas cycle test: the purpose of the test is to provide evidence that the hydrogen container is capable of resisting high variations of pressure when hydrogen gas is used. In order to prove this, the container is subjected to a number of pressure cycles with the use of hydrogen gas and a leak test as referred to under point (k). Deteriorations, such as fatigue cracking or electrostatic discharge of the container, are inspected. The container must meet leak test requirements. The container must be free of any deterioration, such as fatigue cracking or electrostatic discharge.

ANNEX VApplicable test procedures for hydrogen components, other than containers, designed to use compressed (gaseous) hydrogen

TYPE OF TEST

HYDROGEN COMPONENT

Material tests

Corrosion resistance test

Endurance test

Pressure cycle test

Internal leakage test

External leakage test

Pressure relief devices

Image_r00094

Image_r00095

Image_r00096

Image_r00097

Image_r00098

Image_r00099

Automatic valves

Image_r00100

Image_r00101

Image_r00102

Image_r00103

Image_r00104

Image_r00105

Manual valves

Image_r00106

Image_r00107

Image_r00108

Image_r00109

Image_r00110

Image_r00111

Non-return valves

Image_r00112

Image_r00113

Image_r00114

Image_r00115

Image_r00116

Image_r00117

Pressure relief valves

Image_r00118

Image_r00119

Image_r00120

Image_r00121

Image_r00122

Image_r00123

Heat exchangers

Image_r00124

Image_r00125

Image_r00126

Image_r00127

Refuelling connections or receptacles

Image_r00128

Image_r00129

Image_r00130

Image_r00131

Image_r00132

Image_r00133

Pressure regulators

Image_r00134

Image_r00135

Image_r00136

Image_r00137

Image_r00138

Image_r00139

Sensors for hydrogen systems

Image_r00140

Image_r00141

Image_r00142

Image_r00143

Image_r00144

Flexible fuel lines

Image_r00145

Image_r00146

Image_r00147

Image_r00148

Image_r00149

Fittings

Image_r00150

Image_r00151

Image_r00152

Image_r00153

Image_r00154

Hydrogen filters

Image_r00155

Image_r00156

Image_r00157

Image_r00158

Removable storage system connectors

Image_r00159

Image_r00160

Image_r00161

Image_r00162

Image_r00163

Subject to specific requirements for any of the hydrogen components, the test procedures to be applied for the type-approval of hydrogen components, other than containers, designed to use compressed (gaseous) hydrogen must include:

1.

Material tests:

  1. 1.1.

    Hydrogen compatibility test set out in point (j) of Annex III.

  2. 1.2.

    Ageing test: the purpose of the test is to check whether the non-metallic material used in a hydrogen component can withstand ageing. No visible cracking of the test samples is allowed.

  3. 1.3.

    Ozone compatibility test: the purpose of the test is to check whether the elastomer material of a hydrogen component is compatible with ozone exposure. No visible cracking of the test samples is allowed.

2.

Corrosion resistance test set out in point (e) of Annex III.

3.

Endurance test set out in point (c) of Annex III.

4.

Pressure cycle test set out in point (i) of Annex III. The hydrogen components must not show visible signs of deformation or extrusion and must fulfil the requirements of the internal and external leakage tests.

5.

Internal leakage test: the purpose of the test is to provide evidence that the specified hydrogen components are free from internal leakage. In order to prove this, the hydrogen components are pressurised under different temperature conditions and observed for leakage. The hydrogen components must stay bubble free and must not leak internally at a higher rate than a specified number.

6.

External leakage test set out in point (b) of Annex III.

ANNEX VIRequirements for the installation of hydrogen components and systems

1.

The hydrogen system must be installed in such a way that it is protected against damage.

It must be isolated from heat sources in the vehicle.

2.

The hydrogen container may only be removed for replacement with another hydrogen container, for the purpose of refuelling or for maintenance.

In the case of an internal combustion engine, the container must not be installed in the engine compartment of the vehicle.

It must be adequately protected against all kinds of corrosion.

3.

Measures must be taken to prevent misfuelling of the vehicle and hydrogen leakage during refilling and to make sure that the removal of a removable hydrogen storage system is done safely.

4.

The refuelling connection or receptacle must be secured against maladjustment and protected from dirt and water. The refuelling connection or receptacle must be integrated with a non-return valve or a valve with the same function. If the refuelling connection is not mounted directly on the container, the refuelling line must be secured by a non-return valve or a valve with the same function which is mounted directly on or within the container.

5.

The hydrogen container must be mounted and fixed so that the specified accelerations can be absorbed without damage to the safety related parts when the hydrogen containers are full.

6.

The hydrogen fuel supply lines must be secured with an automatic shut-off valve mounted directly on or within the container. The valve shall close if a malfunction of the hydrogen system so requires or any other event that results in the leakage of hydrogen occurs. When the propulsion system is switched off, the fuel supply from the container to the propulsion system must be switched off and remain closed until the system is required to operate.

7.

In the event of an accident, the automatic shut-off valve mounted directly on or within the container shall interrupt the flow of gas from the container.

8.

Hydrogen components, including any protective materials that form part of such components, must not project beyond the outline of the vehicle or protective structure. This does not apply to a hydrogen component which is adequately protected and no part of which is located outside this protective structure.

9.

The hydrogen system must be installed in such a way that it is protected against damage so far as is reasonably practicable, such as damage due to moving vehicle components, impacts, grit, the loading or unloading of the vehicle or the shifting of loads.

10.

Hydrogen components must not be located near the exhaust of an internal combustion engine or other heat source, unless such components are adequately shielded against heat.

11.

The ventilating or heating system for the passenger compartment and places where leakage or accumulation of hydrogen is possible must be designed so that hydrogen is not drawn into the vehicle.

12.

In the event of an accident, it must be ensured so far as is reasonably practicable that the pressure relief device and the associated venting system remain capable of functioning. The venting system of the pressure relief device must be adequately protected against dirt and water.

13.

The passenger compartment of the vehicle must be separated from the hydrogen system in order to avoid accumulation of hydrogen. It must be ensured that any fuel leaking from the container or its accessories does not escape to the passenger compartment of the vehicle.

14.

Hydrogen components that could leak hydrogen within the passenger or luggage compartment or other non-ventilated compartment must be enclosed by a gas-tight housing or by an equivalent solution as specified in the implementing measures.

15.

Electrically operated devices containing hydrogen must be insulated in such a manner that no current passes through hydrogen containing parts in order to prevent electric sparks in the case of a fracture.

Metallic components of the hydrogen system must have electrical continuity with the vehicle’s earth.

16.

Labels or other means of identification must be used to indicate to rescue services that the vehicle is powered by hydrogen and that liquid or compressed (gaseous) hydrogen is used.

ANNEX VIIAmendments to Directive 2007/46/EC

Directive 2007/46/EC is hereby amended as follows:

1.

In Part I of Annex IV, the following row shall be added to the table:

Item

Subject

Regulatory act reference

Official Journal reference

Applicability

M1

M2

M3

N1

N2

N3

O1

O2

O3

O4

‘62

Hydrogen system

Regulation (EC) No 79/2009

L 35, 4.2.2009, p. 32

X

X

X

X

X

X’

2.

In the Appendix to Part I of Annex IV, the following row shall be added to the table:

Subject

Regulatory act reference

Official Journal reference

M1

‘62

Hydrogen system

Regulation (EC) No 79/2009

L 35, 4.2.2009, p. 32

X’

3.

In the Appendix to Annex VI, the following row shall be added to the table:

Subject

Regulatory act reference (1)

As amended by

Applicable to versions

‘62.

Hydrogen system

Regulation (EC) No 79/2009’

4.

In Appendix 1 to Annex XI, the following row shall be added to the table:

Item

Subject

Regulatory act reference

M1 ≤ 2 500 (1) kg

M1 > 2 500 (1) kg

M2

M3

‘62

Hydrogen system

Regulation (EC) No 79/2009

Q

G + Q

G + Q

G + Q’

5.

In Appendix 2 to Annex XI, the following row shall be added to the table:

Item

Subject

Regulatory act reference

M1

M2

M3

N1

N2

N3

O1

O2

O3

O4

‘62

Hydrogen system

Regulation (EC) No 79/2009

A

A

A

A

A

A’

6.

In Appendix 3 to Annex XI, the following row shall be added to the table:

Item

Subject

Regulatory act reference

M1

‘62

Hydrogen system

Regulation (EC) No 79/2009

X’

7.

In Appendix 4 to Annex XI, the following row shall be added to the table:

Item

Subject

Regulatory act reference

M2

M3

N1

N2

N3

O1

O2

O3

O4

‘62

Hydrogen system

Regulation (EC) No 79/2009

Q

Q

Q

Q

Q’

8.

In Appendix 5 to Annex XI, the following row shall be added to the table:

Item

Subject

Regulatory act reference

Mobile crane of category N3

‘62

Hydrogen system

Regulation (EC) No 79/2009

X’