Search Legislation

Regulation (EU) No 528/2012 of the European Parliament and of the CouncilShow full title

Regulation (EU) No 528/2012 of the European Parliament and of the Council of 22 May 2012 concerning the making available on the market and use of biocidal products (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are outstanding changes not yet made to Regulation (EU) No 528/2012 of the European Parliament and of the Council. Any changes that have already been made to the legislation appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Chapter VI:

Changes and effects yet to be applied to the whole legislation item and associated provisions

CHAPTER VIU.K. NATIONAL AUTHORISATIONS OF BIOCIDAL PRODUCTS

Article 29U.K.Submission and validation of applications

1.Applicants wishing to apply for a national authorisation in accordance with Article 17 shall submit an application to the receiving competent authority. The receiving competent authority shall inform the applicant of the fees payable under Article 80(2), and shall reject the application if the applicant fails to pay the fees within 30 days. It shall inform the applicant accordingly. Upon receipt of the fees payable under Article 80(2), the receiving competent authority shall accept the application and inform the applicant accordingly, indicating the date of the acceptance.

2.Within 30 days of acceptance, the receiving competent authority shall validate the application if it complies with the following requirements:

(a)the relevant information referred to in Article 20 has been submitted; and

(b)the applicant states that it has not applied to any other competent authority for a national authorisation for the same biocidal product for the same use(s).

In the context of the validation referred to in the first subparagraph, the receiving competent authority shall not make an assessment of the quality or the adequacy of the data or justifications submitted.

3.Where the receiving competent authority considers that the application is incomplete, it shall inform the applicant as to what additional information is required for the validation of the application and shall set a reasonable time limit for the submission of that information. That time limit shall not normally exceed 90 days.

The receiving competent authority shall, within 30 days of receipt of the additional information, validate the application if it determines that the additional information submitted is sufficient to comply with the requirements laid down in paragraph 2.

The receiving competent authority shall reject the application if the applicant fails to submit the requested information within the deadline and shall inform the applicant accordingly.

4.Where the Register for Biocidal Products referred to in Article 71 shows that a competent authority other than the receiving competent authority is examining an application relating to the same biocidal product or has already authorised the same biocidal product, the receiving competent authority shall decline to evaluate the application. In that event, the receiving competent authority shall inform the applicant of the possibility of seeking mutual recognition in accordance with Article 33 or 34.

5.If paragraph 3 does not apply and the receiving competent authority considers that the application is complete, it shall validate the application and without delay inform the applicant accordingly, indicating the date of the validation.

Article 30U.K.Evaluation of applications

1.The receiving competent authority shall, within 365 days of the validation of an application in accordance with Article 29, decide whether to grant an authorisation in accordance with Article 19. It shall take into account the results of the comparative assessment carried out in accordance with Article 23, if applicable.

2.Where it appears that additional information is necessary to carry out the evaluation, the receiving competent authority shall ask the applicant to submit such information within a specified time limit. The 365-day period referred to in paragraph 1 shall be suspended from the date of issue of the request until the date the information is received. The suspension shall not exceed 180 days in total unless it is justified by the nature of the data requested or by exceptional circumstances.

The receiving competent authority shall reject the application if the applicant fails to submit the requested information within the deadline and shall inform the applicant accordingly.

3.Within the 365-day period referred to in paragraph 1, the receiving competent authority shall:

(a)draft a report summarising the conclusions of its assessment and the reasons for authorising the biocidal product or for refusing to grant an authorisation (the ‘assessment report’);

(b)send an electronic copy of the draft assessment report to the applicant and provide it with the opportunity to submit comments within 30 days; and

(c)take due account of those comments when finalising its assessment.

Article 31U.K.Renewal of a national authorisation

1.An application by or on behalf of an authorisation holder wishing to seek the renewal of a national authorisation for one or more product-types shall be submitted to the receiving competent authority at least 550 days before the expiry date of the authorisation. Where renewal is sought for more than one product-type, the application shall be submitted at least 550 days before the earliest expiry date.

2.The receiving competent authority shall renew the national authorisation, provided that the conditions set out in Article 19 are still satisfied. It shall take into account the results of the comparative assessment carried out in accordance with Article 23, if applicable.

3.When applying for renewal, the applicant shall submit:

(a)without prejudice to Article 21(1), all relevant data required under Article 20 that it has generated since the initial authorisation or, as appropriate, previous renewal; and

(b)its assessment of whether the conclusions of the initial or previous assessment of the biocidal product remain valid and any supporting information.

4.The receiving competent authority shall inform the applicant of the fees payable under Article 80(2) and shall reject the application if the applicant fails to pay the fees within 30 days. It shall inform the applicant accordingly.

Upon receipt of the fees payable under Article 80(2), the receiving competent authority shall accept the application and inform the applicant accordingly, indicating the date of the acceptance.

5.On the basis of an assessment of the available information and the need to review the conclusions of the initial evaluation of the application for authorisation or, as appropriate, the previous renewal, the receiving competent authority shall, within 90 days of accepting an application in accordance with paragraph 4, decide whether, in the light of current scientific knowledge, a full evaluation of the application for renewal is necessary taking account of all product-types for which renewal is requested.

6.Where the receiving competent authority decides that a full evaluation of the application is necessary, it shall decide on the renewal of the authorisation after carrying out an evaluation of the application in accordance with paragraphs 1, 2 and 3 of Article 30.

Where the receiving competent authority decides that a full evaluation of the application is not necessary, it shall decide on the renewal of the authorisation within 180 days of accepting the application in accordance with paragraph 4 of this Article.

7.Where, for reasons beyond the control of the holder of a national authorisation, no decision is taken on the renewal of that authorisation before its expiry, the receiving competent authority shall grant a renewal for the period necessary to complete the evaluation.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Regulation

The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources