[F1Article 114a U.K. Performance and modifications of the contract

1. Performance of the contract shall not start before the contract is signed.

2. The contracting authority may modify a contract or framework contract without a procurement procedure only in the cases provided for in paragraph 3 and provided the modification does not alter the subject matter of the contract or framework contract.

3. A contract or a specific contract under a framework contract may be modified without a new procurement procedure in any of the following cases:

(a) for additional works, supplies or services by the original contractor that have become necessary and that were not included in the initial procurement, where the following conditions are fulfilled:

(i)

a change of contractor cannot be made for technical reasons linked to interchangeability or interoperability requirements with existing equipment, services or installations;

(ii)

a change of contractor would cause substantial duplication of costs for the contracting authority; and

(iii)

any increase in price, including the net cumulative value of successive modifications, does not exceed 50 % of the initial contract value;

(b) where the following conditions are fulfilled:

(i)

the need for modification has been brought about by circumstances which a diligent contracting authority could not foresee; and

(ii)

any increase in price does not exceed 50 % of the initial contract value;

(c) where the value of the modification is below the following thresholds:

(i)

the thresholds referred to in Article 118(1) and the delegated acts adopted pursuant to Article 190(2) in the field of external actions applicable at the time of the modification; and

(ii)

10 % of the initial contract value for public service and supply contracts and works or services concession contracts and 15 % of the initial contract value for public works contracts;

(d) where the minimum requirements of the initial procurement procedure are not altered. In that case any ensuing modification of value shall comply with the conditions set under point (c) of this subparagraph, unless such modification of value results from the strict application of the procurement documents or contractual provisions.

Points (a), (c) and (d) of the first subparagraph of this paragraph may also apply to framework contracts.

The initial contract value shall not take into account price revisions.

The net cumulative value of several successive modifications under point (c) of the first subparagraph of this paragraph shall not exceed any threshold referred to therein.

The contracting authority shall apply the ex post publicity measures set out in Article 103.]