Commission Regulation (EU) No 312/2014 of 26 March 2014 establishing a Network Code on Gas Balancing of Transmission Networks (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are outstanding changes by UK legislation not yet made to Commission Regulation (EU) No 312/2014. Any changes that have already been made to the legislation appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
1.With the view to foster the liquidity of the short term wholesale gas market, the national regulatory authority can incentivise the transmission system operator to undertake balancing actions efficiently or to maximise the undertaking of balancing actions through the trade in short term standardised products.
2.The transmission system operator may submit for approval to the national regulatory authority an incentive mechanism that shall be consistent with the general principles set out in this Regulation.
3.Prior to submitting the proposal referred to in paragraph 2, the transmission system operator may consult stakeholders upon the transmission system operator’s own initiative or upon the national regulatory authority’s request.
4.The incentive mechanism shall:
(a)be based on the transmission system operator’s performance via capped payments to the transmission system operator for outperformance and by the transmission system operator for underperformance, that are measured against predetermined performance targets which may include, inter alia, costs targets;
(b)take into account the means available to the transmission system operator to control the performance;
(c)ensure that its application accurately reflects the allocation of responsibilities between the parties involved;
(d)be adapted to the state of development of the relevant gas market where it is to be implemented;
(e)be subject to a regular review by the national regulatory authority in close cooperation with the transmission system operator to evaluate where and to what extent changes thereto may be needed.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: