Commission Regulation (EU) No 651/2014 of 17 June 2014 declaring certain categories of aid compatible with the internal market in application of Articles 107 and 108 of the Treaty (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
Version Superseded: 31/12/2020
Point in time view as at 10/07/2017. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the Commission Regulation (EU) No 651/2014, Article 53.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.Aid for culture and heritage conservation shall be compatible with the internal market within the meaning of Article 107(3) of the Treaty and shall be exempted from the notification requirement of Article 108(3) of the Treaty, provided the conditions laid down in this Article and in Chapter I are fulfilled.
2.The aid shall be granted for the following cultural purposes and activities:
[F1(a) museums, archives, libraries, artistic and cultural centres or spaces, theatres, cinemas, opera houses, concert halls, other live performance organisations, film heritage institutions and other similar artistic and cultural infrastructures, organisations and institutions;]
(b)tangible heritage including all forms of movable or immovable cultural heritage and archaeological sites, monuments, historical sites and buildings; natural heritage linked to cultural heritage or if formally recognized as cultural or natural heritage by the competent public authorities of a Member State;
(c)intangible heritage in any form, including folklorist customs and crafts;
(d)art or cultural events and performances, festivals, exhibitions and other similar cultural activities;
(e)cultural and artistic education activities as well as promotion of the understanding of the importance of protection and promotion of the diversity of cultural expressions through educational and greater public awareness programs, including with the use of new technologies;
(f)writing, editing, production, distribution, digitisation and publishing of music and literature, including translations.
3.The aid may take the form of:
(a)investment aid, including aid for the construction or upgrade of culture infrastructure;
(b)operating aid.
4.For investment aid, the eligible costs shall be the investment costs in tangible and intangible assets, including:
(a)costs for the construction, upgrade, acquisition, conservation or improvement of infrastructure, if at least 80 % of either the time or the space capacity per year is used for cultural purposes;
(b)costs for the acquisition, including leasing, transfer of possession or physical relocation of cultural heritage;
(c)costs for safeguarding, preservation, restoration and rehabilitation of tangible and intangible cultural heritage, including extra costs for storage under appropriate conditions, special tools, materials and costs for documentation, research, digitalisation and publication;
(d)costs for improving the accessibility of cultural heritage to the public, including costs for digitisation and other new technologies, costs to improve accessibility for persons with special needs (in particular, ramps and lifts for disabled persons, braille indications and hands-on exhibits in museums) and for promoting cultural diversity with respect to presentations, programmes and visitors;
(e)costs for cultural projects and activities, cooperation and exchange programmes and grants including costs for selection procedures, costs for promotion and costs incurred directly as a result of the project;
5.For operating aid, the eligible costs shall be the following:
(a)the cultural institution's or heritage site's costs linked to continuous or periodic activities including exhibitions, performances and events and similar cultural activities that occur in the ordinary course of business;
(b)costs of cultural and artistic education activities as well as promotion of the understanding of the importance of protection and promotion of the diversity of cultural expressions through educational and greater public awareness programs, including with the use of new technologies;
(c)costs of the improvement of public access to the cultural institution or heritage sites and activities including costs of digitisation and of use of new technologies as well as costs of improving accessibility for persons with disabilities;
(d)operating costs directly relating to the cultural project or activity, such as rent or lease of real estate and cultural venues, travel expenses, materials and supplies directly related to the cultural project or activity, architectural structures for exhibitions and stage sets, loan, lease and depreciation of tools, software and equipment, costs for access rights to copyright works and other related intellectual property rights protected contents, costs for promotion and costs incurred directly as a result of the project or activity; depreciation charges and the costs of financing are only eligible if they have not been covered by investment aid;
(e)costs for personnel working for the cultural institution or heritage site or for a project;
(f)costs for advisory and support services provided by outside consultants and service providers, incurred directly as a result of the project.
6.For investment aid, the aid amount shall not exceed the difference between the eligible costs and the operating profit of the investment The operating profit shall be deducted from the eligible costs ex ante, on the basis of reasonable projections, or through a claw-back mechanism. The operator of the infrastructure is allowed to keep a reasonable profit over the relevant period.
7.For operating aid, the aid amount shall not exceed what is necessary to cover the operating losses and a reasonable profit over the relevant period. This shall be ensured ex ante, on the basis of reasonable projections, or through a claw-back mechanism.
[F18. For aid not exceeding EUR 2 million, the maximum amount of aid may be set at 80 % of eligible costs, as an alternative to application of the method referred to in paragraphs 6 and 7.]
9.[F1For the activities defined in paragraph 2(f), the maximum aid amount shall not exceed either the difference between the eligible costs and the project's discounted revenues or 70 % of the eligible costs.] The revenues shall be deducted from the eligible costs ex ante or through a clawback mechanism. The eligible costs shall be the costs for publishing of music and literature, including the authors' fees (copyright costs), translators' fees, editors' fees, other editorial costs (proofreading, correcting, reviewing), layout and pre-press costs and printing or e-publication costs.
10.Aid to press and magazines, whether they are published in print or electronically, shall not be eligible under this Article.
Textual Amendments
F1 Substituted by Commission Regulation (EU) 2017/1084 of 14 June 2017 amending Regulation (EU) No 651/2014 as regards aid for port and airport infrastructure, notification thresholds for aid for culture and heritage conservation and for aid for sport and multifunctional recreational infrastructures, and regional operating aid schemes for outermost regions and amending Regulation (EU) No 702/2014 as regards the calculation of eligible costs (Text with EEA relevance).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: