TITLE IIREQUIREMENTS FOR TERMS, CONDITIONS AND METHODOLOGIES CONCERNING CAPACITY ALLOCATION AND CONGESTION MANAGEMENT

CHAPTER 1Capacity calculation

Section 4The capacity calculation process

Article 28Creation of a common grid model

1

For each capacity calculation time-frame referred to in Article 14(1), each generator or load unit subject to Article 16 shall provide the data specified in the generation and load data provision methodology to the TSO responsible for the respective control area within the specified deadlines.

2

Each generator or load unit providing information pursuant to Article 16(3) shall deliver the most reliable set of estimations practicable.

3

For each capacity calculation time-frame, each TSO shall establish the individual grid model for each scenario in accordance with Article 19, in order to merge individual grid models into a common grid model.

4

Each TSO shall deliver to the TSOs responsible for merging the individual grid models into a common grid model the most reliable set of estimations practicable for each individual grid model.

5

For each capacity calculation time-frame a single, Union-wide common grid model shall be created for each scenario as set out in Article 18 by merging inputs from all TSOs applying the capacity calculation process as set out in paragraph 3 of this Article.