Commission Delegated Regulation (EU) 2016/1075 of 23 March 2016 supplementing Directive 2014/59/EU of the European Parltime and of the Council with regard to regulatory technical standards specifying the content of recovery plans, resolution plans and group resolution plans, the minimum criteria that the competent authority is to assess as regards recovery plans and group recovery plans, the conditions for group financial support, the requirements for independent valuers, the contractual recognition of write-down and conversion powers, the procedures and contents of notification requirements and of notice of suspension and the operational functioning of the resolution colleges (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
Point in time view as at 23/03/2016.
Commission Delegated Regulation (EU) 2016/1075, Article 77 is up to date with all changes known to be in force on or before 31 January 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
EUR 2016 No. 1075 may be subject to amendment by EU Exit Instruments made by the Bank of England under powers set out in The Financial Regulators' Powers (Technical Standards etc.) (Amendment etc.) (EU Exit) Regulations 2018 (S.I. 2018/1115), regs. 2, 3, Sch. Pt. 3. These amendments are not currently available on legislation.gov.uk. Details of relevant amending instruments can be found on their website/s.
EUR 2016 No. 1075 may be subject to amendment by EU Exit Instruments made by both the Prudential Regulation Authority and the Financial Conduct Authority under powers set out in The Financial Regulators' Powers (Technical Standards etc.) (Amendment etc.) (EU Exit) Regulations 2018 (S.I. 2018/1115), regs. 2, 3, Sch. Pt. 4. These amendments are not currently available on legislation.gov.uk. Details of relevant amending instruments can be found on their website/s.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
1.Prior to the start of the joint decision process on measures to address or remove substantive impediments to resolvability, the group-level resolution authority and the resolution authorities of subsidiaries shall agree on a timetable of steps to be followed in the joint decision timetable.
In the case of a failure to agree on that timetable, the group-level resolution authority shall set the joint decision timetable after considering the views and any reservations expressed by the resolution authorities of subsidiaries.
2.The joint decision timetable shall include the following steps:
(a)preparation and circulation of the report on substantive impediments identified in accordance with Article 18(2) of Directive 2014/59/EU by the group-level resolution authority in consultation with the consolidating supervisor and the EBA;
(b)submission of the report pursuant to Article 18(2) of Directive 2014/59/EU from the group-level resolution authority to the Union parent undertaking, the resolution authorities of subsidiaries, and the resolution authorities of jurisdictions in which significant branches are located;
(c)date when the Union parent undertaking submits to the group-level resolution authority its observations and alternative measures to remedy the substantive impediments, if any, in accordance with Article 18(3) of Directive 2014/59/EU;
(d)dialogue between the group-level resolution authority and the resolution authorities of subsidiaries and other resolution college members, on any observations or alternative measures to remedy the substantive impediments proposed by the Union parent undertaking pursuant to Article 18(3) of Directive 2014/59/EU, as appropriate;
(e)development of the draft joint decision on measures to address or remove substantive impediments to resolvability;
(f)finalisation of the joint decision on measures to address or remove substantive impediments to resolvability; and
(g)communication of the joint decision on measures to address or remove substantive impediments to resolvability.
3.The joint decision timetable shall be reviewed and updated by the group-level resolution authority in order to reflect the extension of the joint decision process where the Union parent undertaking submits observations and proposes any alternative measures to address or remove substantive impediments to resolvability in accordance to Article 18(3) of Directive 2014/59/EU.
4.When drafting the joint decision timetable, the group-level resolution authority shall have regard to the terms and conditions of the observers' participation as set out in the resolution college written arrangements and in the respective provisions of Directive 2014/59/EU.
5.The group-level resolution authority shall communicate to the Union parent undertaking those aspects of the joint decision timetable that envisage the involvement of the Union parent undertaking.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: