TITLE IIIU.K. AID FOR PRIVATE STORAGE

CHAPTER I U.K. Specific rules for aid for private storage

Section I U.K. General provisions

Article 39U.K.Opening of tendering procedures and fixing aid in advance

1.[F1Any tendering procedure (where tendering applies) or Regulations] fixing the amount of aid in advance may contain the following information:

(a)the products, or types of products, covered with their relevant CN codes, if applicable;

(b)in the case of aid fixed in advance, the amount of aid for storage per unit of measurement for the products covered;

(c)the unit of measurement of the quantities;

(d)if the tender or aid fixed in advance relates to products that have already been placed in storage;

(e)in the case of tenders, the period covered (‘tendering period’) and, if necessary, the different sub-periods during which tenders can be submitted, and in the case of aid fixed in advance the period for submitting an application;

(f)the period of storage;

(g)the global quantity, if applicable;

(h)the minimum quantity per tender or application;

(i)the amount of the security per unit of measurement in the case of tenders and, where applicable, for applications;

(j)the periods of placing into store and of removal from store;

(k)the specifications that have to appear on the packaging, if applicable.

F22.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3.In the case of tenders, at least six days shall elapse between F3... opening the tendering procedure and the first date for the submission of tenders.