Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects for the Commission Regulation (EU) 2016/631, Article 20.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.Type B power park modules shall fulfil the requirements laid down in Articles 13, except for Article 13(2)(b), and Article 14.
2.Type B power park modules shall fulfil the following additional requirements in relation to voltage stability:
(a)with regard to reactive power capability, the relevant system operator shall have the right to specify the capability of a power park module to provide reactive power;
(b)the relevant system operator in coordination with the relevant TSO shall have the right to specify that a power park module be capable of providing fast fault current at the connection point in case of symmetrical (3-phase) faults, under the following conditions:
the power park module shall be capable of activating the supply of fast fault current either by:
ensuring the supply of the fast fault current at the connection point, or
measuring voltage deviations at the terminals of the individual units of the power park module and providing a fast fault current at the terminals of these units;
the relevant system operator in coordination with the relevant TSO shall specify:
how and when a voltage deviation is to be determined as well as the end of the voltage deviation,
the characteristics of the fast fault current, including the time domain for measuring the voltage deviation and fast fault current, for which current and voltage may be measured differently from the method specified in Article 2,
the timing and accuracy of the fast fault current, which may include several stages during a fault and after its clearance;
(c)with regard to the supply of fast fault current in case of asymmetrical (1-phase or 2-phase) faults, the relevant system operator in coordination with the relevant TSO shall have the right to specify a requirement for asymmetrical current injection.
3.Type B power park modules shall fulfil the following additional requirements in relation to robustness:
(a)the relevant TSO shall specify the post-fault active power recovery that the power park module is capable of providing and shall specify:
when the post-fault active power recovery begins, based on a voltage criterion;
a maximum allowed time for active power recovery; and
a magnitude and accuracy for active power recovery;
(b)the specifications shall be in accordance with the following principles:
interdependency between fast fault current requirements according to points (b) and (c) of paragraph 2 and active power recovery;
dependence between active power recovery times and duration of voltage deviations;
a specified limit of the maximum allowed time for active power recovery;
adequacy between the level of voltage recovery and the minimum magnitude for active power recovery; and
adequate damping of active power oscillations.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: