Commission Regulation (EU) 2017/1485Show full title

Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance)

Article 2U.K.Scope

1.The rules and requirements set out in this Regulation shall apply to the following SGUs [F1within the jurisdiction of Great Britain]:

(a)existing and new power generating modules that are, or would be, classified as type B, C and D in accordance with the criteria set out in Article 5 of Commission Regulation (EU) 2016/631(1);

(b)existing and new transmission-connected demand facilities;

(c)existing and new transmission-connected closed distribution systems;

(d)existing and new demand facilities, closed distribution systems and third parties if they provide demand response directly to the TSO F2...;

(e)providers of redispatching of power generating modules or demand facilities by means of aggregation and providers of active power reserve in accordance with Title 8 of Part IV of this Regulation; and

(f)existing and new high voltage direct current (‘HVDC’) systems in accordance with the criteria in Article 3(1) of Commission Regulation (EU) 2016/1447(2).

2.[F3Except for Article 13,] this Regulation shall apply to all transmission systems, distribution systems and interconnections [F4within the jurisdiction of Great Britain], except transmission systems and distribution systems or parts of the transmission systems and distribution systems located in islands [F5which are not part of the GB synchronous area].

3.[F6Except for Article 13, this Regulation applies to all TSOs that are certified by the regulatory authority, to the extent they are operating within the jurisdiction of Great Britain.] Where a TSO does not have a function relevant to one or more obligations under this Regulation, [F7the regulatory authority may] provide that the responsibility of a TSO to comply with one or some or all obligations under this Regulation is assigned to one or more specific TSOs.

F84.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

5.Where the requirements under this Regulation are to be established by a relevant system operator that is not a TSO, [F9the regulatory authority] may provide that instead the TSO be responsible for establishing the relevant requirements.

Textual Amendments

(1)

Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (OJ L 112, 27.4.2016, p. 1).

(2)

Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (OJ L 241, 8.9.2016, p. 1).