Commission Regulation (EU) 2017/2195 of 23 November 2017 establishing a guideline on electricity balancing (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are outstanding changes not yet made to Commission Regulation (EU) 2017/2195. Any changes that have already been made to the legislation appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Article 62:

Changes and effects yet to be applied to the whole legislation item and associated provisions

Article 62U.K.Derogations

1.A regulatory authority in accordance with Article 37 of Directive 2009/72/EC may, at the request of a TSO or at its own initiative, grant the relevant TSOs a derogation from one or more provisions of this Regulation in accordance with paragraphs 2 to 12.

2.A TSO may request a derogation from the following requirements:

(a)the deadlines by which a TSO shall use the European platforms pursuant to Articles 19(5), 20(6), 21(6) and 22(5);

(b)the definition of the integrated scheduling process gate closure time in a central dispatching model pursuant to Article 24(5) and the possibility to change the integrated scheduling process bids pursuant to Article 24(6);

(c)the maximum volume of cross-zonal capacity allocated on a market-based process pursuant to Article 41(2) or a process based an economic efficiency analysis pursuant to Article 42(2);

(d)the harmonisation of the imbalance settlement period in Article 53(1);

(e)the implementation of the requirements pursuant to Articles 45, 46, 47, 48, 49, 50, 51, 54, 55, 56 and 57.

3.The derogation process shall be transparent, non-discriminatory, non-biased, well documented and based on a reasoned request.

4.TSOs shall file a written request for derogation to the relevant regulatory authority at the latest six months prior to the day of application of the provisions from which the derogation is requested.

5.The request for derogation shall include the following information:

(a)the provisions from which a derogation is requested;

(b)the requested derogation period;

(c)a detailed plan and timeline specifying how to address and ensure the implementation of the concerned provisions of this Regulation after expiration of the derogation period;

(d)an assessment of the consequences of requested derogation on adjacent markets;

(e)an assessment of the possible risks for the integration of balancing markets across Europe caused by the requested derogation.

6.The relevant regulatory authority shall adopt a decision concerning any request for derogation within six months from the day after it receives the request. That time limit may be extended by three months before its expiry where the relevant regulatory authority requires further information from the TSO requesting the derogation. The additional period shall begin when the complete information has been received.

7.The TSO requesting the derogation shall submit any additional information requested by the relevant regulatory authority within two months of such request. If the TSO does not supply the requested information within that time limit, the request for a derogation shall be deemed withdrawn unless, before its expiry, alternatively:

(a)the relevant regulatory authority decides to provide an extension;

(b)the TSO informs the relevant regulatory authority by means of a reasoned submission that the request for a derogation is complete.

8.When assessing the request for derogation or before granting a derogation at its own initiative, the relevant regulatory authority shall consider the following aspects:

(a)the difficulties related to the implementation of the concerned provision or provisions;

(b)the risks and the implications of the concerned provision or provisions, in terms of operational security;

(c)the actions taken to facilitate the implementation of the concerned provision or provisions;

(d)the impacts of non-implementation of the concerned provision or provisions, in terms of non-discrimination and competition with other European market participants, in particular as regards demand response and renewable energy sources;

(e)the impacts on overall economic efficiency and smart grid infrastructure;

(f)the impacts on other scheduling areas and overall consequences on the European market integration process.

9.The relevant regulatory authority shall issue a reasoned decision concerning a request for a derogation or a derogation granted at its own initiative. Where the relevant regulatory authority grants a derogation, it shall specify its duration. The derogation may be granted only once and for a maximum period of two years, except for the derogations in paragraphs 2(c) and 2(d) which may be granted until 1 January 2025.

10.The relevant regulatory authority shall notify its decision to the TSO, the Agency and the European Commission. The decision shall also be published on its website.

11.The relevant regulatory authorities shall maintain a register of all derogations they have granted or refused and shall provide the Agency with an updated and consolidated register at least once every six months, a copy of which shall be given to ENTSO-E.

12.The register shall contain, in particular:

(a)the provisions from which the derogation is granted or refused;

(b)the content of the derogation;

(c)the reasons for granting or refusing the derogation;

(d)the consequences resulting from granting the derogation.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources