Commission Regulation (EU) 2017/459Show full title

Commission Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and repealing Regulation (EU) No 984/2013 (Text with EEA relevance)

Article 23U.K.The f-factor

1.When applying the economic test referred to in Article 22, the national regulatory authority shall set the level of the f-factor for a given offer level, taking into account the following:

(a)the amount of technical capacity set aside in accordance with Article 8(8) and (9);

(b)positive externalities of the incremental capacity project on the market or the transmission network, or both;

(c)the duration of binding commitments of network users for contracting capacity compared to the economic life of the asset;

(d)the extent to which the demand for the capacity established in the incremental capacity project can be expected to continue after the end of the time horizon used in the economic test.

2.If the economic test has a positive outcome then the investment costs associated with the incremental capacity shall be reflected in an increase in the allowed or target revenue in accordance with the applicable national rules.