Article 35Defined sequence of interruptions
1.The order in which interruptions shall be performed, if the total of nominations exceeds the quantity of gas that can flow at a certain interconnection point, shall be determined based on the contractual time stamp of the respective transport contracts on an interruptible basis. In case of an interruption, transport contract coming into force earlier shall prevail over transport contract coming into force later.
2.If, after applying the procedure provided for in paragraph 1, two or more nominations are ranked at the same position within the interruption order and the transmission system operator does not interrupt all of them, a pro rata reduction of these specific nominations shall apply.
3.To accommodate the differences between the various interruptible capacity services within the Union, the adjacent transmission system operators shall implement and coordinate the joint procedures provided for in this Article on an interconnection point by interconnection point basis.