Regulation (EU, Euratom) 2018/1046 of the European Parliament and of the Council of 18 July 2018 on the financial rules applicable to the general budget of the Union, amending Regulations (EU) No 1296/2013, (EU) No 1301/2013, (EU) No 1303/2013, (EU) No 1304/2013, (EU) No 1309/2013, (EU) No 1316/2013, (EU) No 223/2014, (EU) No 283/2014, and Decision No 541/2014/EU and repealing Regulation (EU, Euratom) No 966/2012
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
Version Superseded: 31/12/2020
Point in time view as at 31/01/2020.
There are currently no known outstanding effects by UK legislation for Regulation (EU, Euratom) 2018/1046 of the European Parliament and of the Council, SECTION 1 .
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Specific contracts based on framework contracts shall be awarded in accordance with the terms of the framework contract.
When concluding specific contracts, the parties shall not substantially deviate from the framework contract.
In such circumstances and where duly justified, contracting authorities may request the contractor in writing to supplement its tender if necessary.
Specific contracts based on multiple framework contracts shall be implemented in one of the following ways:
in accordance with the terms of the framework contract: without reopening of competition, where it sets out all the terms governing the provision of the works, supplies or services concerned and the objective conditions for determining which of the contractors shall perform them;
where not all the terms governing the provision of the works, supplies or services concerned are laid down in the framework contract: through reopening of competition among the contractors, in accordance with point 1.4 and on the basis of any of the following:
the same terms, where necessary more precisely formulated;
where appropriate, on the basis of other terms referred to in the procurement documents relating to the framework contract.
partly without reopening of competition in accordance with point (a) and partly with reopening of competition amongst the contractors in accordance with point (b), where that possibility has been stipulated by the contracting authority in the procurement documents relating to the framework contract.
The procurement documents referred to in point (c) of the second subparagraph shall also specify which terms may be subject to reopening of competition.
When awarding a specific contract through reopening of competition among the contractors, the contracting authority shall consult them in writing and fix a time limit which is sufficiently long to allow specific tenders to be submitted. Specific tenders shall be submitted in writing. The contracting authority shall award each specific contract to the tenderer who has submitted the most economically advantageous specific tender on the basis of the award criteria set out in the procurement documents relating to the framework contract.
The contracting authority may publish the prior information notice either in the Official Journal of the European Union or on its buyer profile. In the latter case, a notice of publication on the buyer profile shall be published in the Official Journal of the European Union.
Notwithstanding the first subparagraph, award notices relating to contracts based on a dynamic purchasing system may be grouped together on a quarterly basis. In such cases, the contracting authority shall send the award notice no later than 30 days after the end of each quarter.
Award notices shall not be published for specific contracts based on a framework contract.
before concluding a contract or a framework contract with a value equal to or greater than the thresholds referred to in Article 175(1) and awarded in accordance with point (b) of the second subparagraph of point 11.1;
after concluding a contract or a framework contract with a value equal to or greater than the thresholds referred to in Article 175(1), including contracts awarded in accordance with point (a) and points (c) to (f) of the second subparagraph of point 11.1.
The contracting authority shall publish a list of contracts on its website no later than 30 June of the following financial year for:
contracts below the thresholds referred to in Article 175(1);
contracts awarded in accordance with point (h) and points (j) to (m) of the second subparagraph of point 11.1;
modifications of contracts as set out in point (c) of the first subparagraph of Article 172(3);
modifications of contracts as set out in points (a) and (b) of the first subparagraph of Article 172(3) where the value of the modification is below the thresholds referred to in Article 175(1);
specific contracts under a framework contract.
For the purposes of point (e) of the second subparagraph, the published information may be aggregated per contractor for specific contracts under the same framework contract.
seven days after their dispatch if the contracting authority uses the electronic system for filling out the standard forms referred to in point 2.1 and limits free text to 500 words;
12 days after their dispatch in all other cases.
In addition to the advertising provided for in points 2 and 3 procurement procedures may be advertised in any other way, in particular in electronic form. Any such advertising shall refer to the notice published in the Official Journal of the European Union, if the notice has been published, and shall not precede the publication of that notice, which alone is authentic.
Such advertising shall not introduce any discrimination between candidates or tenderers nor contain details other than those contained in the contract notice, if the notice has been published.
The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Regulation you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Regulation without Annexes you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: