Article 3.Responsibilities of the Agency and the national safety authorities
Article 10.Arrangements for visits and inspections on the sites of railway undertakings and audits
Article 11.Coordination between the Agency and national safety authorities
Article 14.Review under Article 10(12) of Directive (EU) 2016/798
4.1. After the completion of the initial screen stage, the safety...
4.2. In undertaking the detailed assessment referred to in point 4.1,...
4.3. The assessment shall determine whether the safety management system requirements...
4.4. Any type 4 issue shall be resolved to the satisfaction...
4.5. Residual concerns may be deferred for consideration to supervision, or...
4.6. The safety certification body and the national safety authorities concerned...
4.7. When identifying an issue referred to in Article 12(1), the...
4.8. If the applicant significantly delays providing the requested information, the...
4.9. The timeframe for taking the decision on the issuing of...
4.10. To be satisfactory, the applicant's written responses shall be sufficient...
4.11. Where a response is considered unsatisfactory, it shall be explained...
4.12. If concerns emerge that the application could be rejected, or...
4.13. When it is concluded that either the application meets all...
4.14. The safety certification body and the national safety authorities concerned...
7. SPECIFIC PROVISIONS FOR THE RENEWAL OF A SINGLE SAFETY CERTIFICATE...
8. SPECIFIC PROVISIONS FOR THE UPDATE OF A SINGLE SAFETY CERTIFICATE...
8.1. A single safety certificate shall be updated whenever there is...
8.3. Following the notification by the railway undertaking as referred to...
8.4. The safety certification body in coordination with the national safety...
8.5. In the case of an update application, the safety certification...
8.6. The safety certification body and the national safety authorities concerned...
8.7. An application to the safety certification body to update a...
8.8. The safety certification body shall decide at the request of...