Commission Implementing Regulation (EU) 2018/920 of 28 June 2018 amending Implementing Regulation (EU) No 180/2014 as regards certain provisions on checks, notifications and annual reporting and on amendments to the POSEI programmes
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This version of this Regulation was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Implementing Regulation (EU) No 180/2014 is amended as follows:
Article 2 is amended as follows:
paragraph 2 is replaced by the following:
‘2.Import licences shall be drawn up in accordance with the specimen set out in Annex I to Commission Implementing Regulation (EU) 2016/1239(1).
Article 4 of Commission Delegated Regulation (EU) 2016/1237(2) and Articles 2 and 3, Article 4(1), Article 5 and 7 and 13 to 16 of Implementing Regulation (EU) 2016/1239 shall apply mutatis mutandis, without prejudice to this Regulation.
The negative tolerance provided for in Article 5(4) of Delegated Regulation (EU) 2016/1237 and Article 8(1) of Implementing Regulation (EU) 2016/1239 shall apply mutatis mutandis.’;
paragraph 6 is replaced by the following:
‘6.Import duties shall be levied on quantities which exceed those stated on the import licence. The positive tolerance of 5 % provided for in Article 5(4) of Delegated Regulation (EU) 2016/1237 and Article 8(1) of Implementing Regulation (EU) 2016/1239 shall apply, provided that the import duties relating thereto are paid.’;
in Article 3, paragraph 2 is replaced by the following:
‘2.Exemption certificates shall be drawn up on the basis of the specimen import licence set out in Annex I to Implementing Regulation (EU) 2016/1239.
Article 4 of Delegated Regulation (EU) 2016/1237 and Articles 2 and 3, Article 4(1), Articles 5 and 7 and 13 to 16 of Implementing Regulation (EU) 2016/1239 shall apply mutatis mutandis, without prejudice to this Regulation.
The negative tolerance provided for in Article 5(4) of Delegated Regulation (EU) 2016/1237 and Article 8(1) of Implementing Regulation (EU) 2016/1239 shall apply mutatis mutandis.’;
in Article 5, paragraph 2 is replaced by the following:
‘2.Aid certificates shall be drawn up on the basis of the specimen import licence set out in Annex I to Implementing Regulation (EU) 2016/1239.
Article 4 of Delegated Regulation (EU) 2016/1237 and Articles 2 and 3, Article 4(1), Articles 5 and 7 and 13 to 16 of Implementing Regulation (EU) 2016/1239 shall apply mutatis mutandis, without prejudice to this Regulation.
The negative tolerance provided for in Article 5(4) of Delegated Regulation (EU) 2016/1237 and Article 8(1) of Implementing Regulation (EU) 2016/1239 shall apply mutatis mutandis.’;
Article 8(1) is amended as follows:
the first subparagraph is amended as follows:
the introductory sentence is replaced by the following:
‘Subject to Articles 2(5), 3(6), 5(7) and Articles 11 and 12, the competent authorities shall accept the import licence, exemption certificate or aid certificate application presented by operators for each consignment. Those applications shall be accompanied by the original or a certified copy of the purchase invoice and the original, a certified copy or an authenticated electronic equivalent of the following documents:’;
point (b) is replaced by the following:
the means of proof of the customs status of Union goods referred to in Article 199(1)(b) of Commission Implementing Regulation (EU) 2015/2447(3); or
a declaration type CO pursuant to Chapters 2 and 3 of Title VIII of Commission Delegated Regulation (EU) 2015/2446(4) in accordance with data elements No 1/1, 1/2 and 1/3 referred to in the data requirements table set out in Section 1 of Chapter 3 of Title I of Annex B to that Regulation.’;
the second subparagraph is replaced by the following:
‘Those accompanying documents may take the form of an electronic message. In case the verifying competent authority has no access to the IT system managing and producing such electronic document, it shall be replaced by a duly certified true copy or its authenticated electronic equivalent print-out.’;
in Article 12, the third paragraph is replaced by the following:
‘The notification referred to in this Article shall be made in accordance with Commission Delegated Regulation (EU) 2017/1183(5) and Commission Implementing Regulation (EU) 2017/1185(6).’;
in Article 16, paragraph 2 is replaced by the following:
‘2.The physical checks carried out in the outermost region concerned on the import or entry of agricultural products shall involve a representative sample amounting to at least 5 % of the licences and certificates presented in accordance with Article 9.
The physical checks carried out in the outermost region concerned on the export or dispatch provided for in Section 5 shall involve a representative sample of at least 5 % of the operations, based on the risk profiles established by the Member States.
Commission Regulation (EC) No 1276/2008(7) shall apply mutatis mutandis to those physical checks.
In addition, in special cases the Commission may request that physical checks cover different percentages.’;
in Article 22, the third paragraph is replaced by the following:
‘On the basis of a risk analysis in accordance with Article 24(1) of this Regulation, the competent authorities shall perform on-the-spot checks by sampling, for each action, at least 5 % of aid applications. The sample shall also represent at least 5 % of the amounts covered by the aid for each action.’;
in the second subparagraph of Article 24(1), the following sentence is added:
‘When the minimum number of aid applicants to be subjected to on-the-spot checks is lower than 12, Member States shall randomly select at least one applicant.’;
Articles 28 and 29 are replaced by the following:
1.In the event of undue payment, Article 7 of Commission Implementing Regulation (EU) No 809/2014(8) shall apply mutatis mutandis.
2.Where the undue payment has been made as a result of a false declaration, false documents or serious negligence on the part of the aid applicant, a penalty shall be imposed equal to the amount unduly paid, with interest calculated in accordance with Article 7(2) of Implementing Regulation (EU) No 809/2014.
In cases of force majeure or exceptional circumstances within the meaning of Article 2(2) of Regulation (EU) No 1306/2013, Article 4 of Commission Delegated Regulation (EU) No 640/2014(9) shall apply mutatis mutandis.’;
in Article 32(3), the second subparagraph is replaced by the following:
‘The notification referred to in this paragraph shall be made in accordance with Delegated Regulation (EU) 2017/1183 and Implementing Regulation (EU) 2017/1185.’;
in Article 35, paragraph 2 is replaced by the following:
‘2.The competent authorities shall ensure that the products listed in Annex VII are used in compliance with the relevant Union rules, and in particular Articles 211, 214, 215, 218, 219 and 254 of Regulation (EU) No 952/2013 of the European Parliament and of the Council(10), Articles 161 to 164, 171 to 175, 178, 179 and 239 of Delegated Regulation (EU) 2015/2446 and Articles 260 to 269 of Implementing Regulation (EU) 2015/2447.’;
Article 38 is amended as follows:
paragraph 1 is amended as follows:
in the first subparagraph, the introductory sentence is replaced by the following:
‘As regards the specific supply arrangements, the competent authorities shall notify the Commission, no later than 31 May each year, of the following data relating to the operations carried out in the previous year with respect to the supply balance of the reference calendar year, broken down by product and CN code and, where applicable, by individual destination:’;
in the second subparagraph, the second sentence is deleted;
paragraphs 3 and 4 are replaced by the following:
‘3.The notifications referred to in this Article shall be made in accordance with Delegated Regulation (EU) 2017/1183 and Implementing Regulation (EU) 2017/1185.
4.The notifications referred to in Article 23(3) and 32(1) of Regulation (EU) No 228/2013 shall also be made in accordance with Delegated Regulation (EU) 2017/1183 and Implementing Regulation (EU) 2017/1185.’;
Article 39 is replaced by the following:
1.The structure and content of the annual report referred to in Article 32(2) of Regulation (EU) No 228/2013 shall be as set out in Annex IX to this Regulation.
2.The report referred to in paragraph 1 shall be submitted to the Commission in accordance with Delegated Regulation (EU) 2017/1183 and Implementing Regulation (EU) 2017/1185.’;
Article 40 is amended as follows:
paragraphs 1 and 2 are replaced by the following:
‘1.Amendments made to each POSEI programme shall be submitted by Member States to the Commission once per calendar year and per programme, except in cases of force majeure or exceptional circumstances. They shall be sent to the Commission no later than 31 July of the year prior to their application. The amendments shall be duly substantiated, in particular by giving the following information:
(a)the reasons for any implementation problems justifying the amendment of the programme;
(b)the expected effects of the amendment;
(c)the implications for financing and eligibility conditions.
The Commission shall inform the Member State if it considers that the amendments do not comply with Union legislation, in particular with Article 4 of Regulation (EU) No 228/2013, without prejudice to the Articles 51 and 52 of Regulation (EU) No 1306/2013.
The amendments shall apply from 1 January of the year following that in which they were notified. In case an earlier application is deemed necessary, such amendments may apply earlier, unless the Commission objects.
2.By way of derogation from paragraph 1, the Commission shall evaluate separately the following amendments proposed by the Member States and decide on their approval within five months of their submission at the latest in accordance with the procedure referred to in Article 34(2) of Regulation (EU) No 228/2013:
(a)the accession of a new outermost region;
(b)the introduction into the general programme of new groups of products to be supported under the specific supply arrangements or of new measures to assist the local agricultural production.
The amendments thus approved shall apply from 1 January of the year following that in which the proposal for an amendment was made or as from the date explicitly indicated in the approval decision.’;
in paragraph 3, point (b) is replaced by the following:
in paragraph 5, point (a) is replaced by the following:
‘measure’ means the grouping of actions necessary to achieve one or more objectives for the programme constituting a line for which a financial allocation is defined in the financing table referred to in Article 5(a) of Regulation (EU) No 228/2013;’;
paragraph 6 is replaced by the following:
‘6.The notifications referred to in this Article shall be made in accordance with Delegated Regulation (EU) 2017/1183 and Implementing Regulation (EU) 2017/1185.’;
Annex IX is added, the text of which is set out in the Annex to this Regulation.
Commission Implementing Regulation (EU) 2016/1239 of 18 May 2016 laying down rules for the application of Regulation (EU) No 1308/2013 of the European Parliament and of the Council with regard to the system of import and export licences (OJ L 206, 30.7.2016, p. 44).
Commission Delegated Regulation (EU) 2016/1237 of 18 May 2016 supplementing Regulation (EU) No 1308/2013 of the European Parliament and of the Council with regard to the rules for applying the system of import and export licences and supplementing Regulation (EU) No 1306/2013 of the European Parliament and of the Council with regard to the rules on the release and forfeit of securities lodged for such licences, amending Commission Regulations (EC) No 2535/2001, (EC) No 1342/2003, (EC) No 2336/2003, (EC) No 951/2006, (EC) No 341/2007 and (EC) No 382/2008 and repealing Commission Regulations (EC) No 2390/98, (EC) No 1345/2005, (EC) No 376/2008 and (EC) No 507/2008 (OJ L 206, 30.7.2016, p. 1).’;
Commission Implementing Regulation (EU) 2015/2447 of 24 November 2015 laying down detailed rules for implementing certain provisions of Regulation (EU) No 952/2013 of the European Parliament and of the Council laying down the Union Customs Code (OJ L 343, 29.12.2015, p. 558).
Commission Delegated Regulation (EU) 2015/2446 of 28 July 2015 supplementing Regulation (EU) No 952/2013 of the European Parliament and of the Council as regards detailed rules concerning certain provisions of the Union Customs Code (OJ L 343, 29.12.2015, p. 1).’;
Commission Delegated Regulation (EU) 2017/1183 of 20 April 2017 on supplementing Regulations (EU) No 1307/2013 and (EU) No 1308/2013 of the European Parliament and of the Council with regard to the notifications to the Commission of information and documents (OJ L 171, 4.7.2017, p. 100).
Commission Implementing Regulation (EU) 2017/1185 of 20 April 2017 laying down rules for the application of Regulations (EU) No 1307/2013 and (EU) No 1308/2013 of the European Parliament and of the Council as regards notifications to the Commission of information and documents and amending and repealing several Commission Regulations (OJ L 171, 4.7.2017, p. 113).’;
Commission Regulation (EC) No 1276/2008 of 17 December 2008 on the monitoring by physical checks of exports of agricultural products receiving refunds or other amounts (OJ L 339, 18.12.2008, p. 53).’;
Commission Implementing Regulation (EU) No 809/2014 of 17 July 2014 laying down rules for the application of Regulation (EU) No 1306/2013 of the European Parliament and of the Council with regard to the integrated administration and control system, rural development measures and cross compliance (OJ L 227, 31.7.2014, p. 69).
Commission Delegated Regulation (EU) No 640/2014 of 11 March 2014 supplementing Regulation (EU) No 1306/2013 of the European Parliament and of the Council with regard to the integrated administration and control system and conditions for refusal or withdrawal of payments and administrative penalties applicable to direct payments, rural development support and cross compliance (OJ L 181, 20.6.2014, p. 48).’;
Regulation (EU) No 952/2013 of the European Parliament and of the Council of 9 October 2013 laying down the Union Customs Code (OJ L 269, 10.10.2013, p. 1).’;
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: