ANNEXInterest Rate Benchmark Reform

Amendments to IFRS 9, IAS 39 and IFRS 7

Chapter 6 Hedge accounting

...

6.8TEMPORARY EXCEPTIONS FROM APPLYING SPECIFIC HEDGE ACCOUNTING REQUIREMENTS
6.8.1.An entity shall apply paragraphs 6.8.4–6.8.12 and paragraphs 7.1.8 and 7.2.26(d) to all hedging relationships directly affected by interest rate benchmark reform. These paragraphs apply only to such hedging relationships. A hedging relationship is directly affected by interest rate benchmark reform only if the reform gives rise to uncertainties about:
(a)

the interest rate benchmark (contractually or non-contractually specified) designated as a hedged risk; and/or

(b)

the timing or the amount of interest rate benchmark-based cash flows of the hedged item or of the hedging instrument.

6.8.2.For the purpose of applying paragraphs 6.8.4–6.8.12, the term ‘interest rate benchmark reform’ refers to the market-wide reform of an interest rate benchmark, including the replacement of an interest rate benchmark with an alternative benchmark rate such as that resulting from the recommendations set out in the Financial Stability Board’s July 2014 report ‘Reforming Major Interest Rate Benchmarks’.(1)
6.8.3.Paragraphs 6.8.4–6.8.12 provide exceptions only to the requirements specified in these paragraphs. An entity shall continue to apply all other hedge accounting requirements to hedging relationships directly affected by interest rate benchmark reform.
Highly probable requirement for cash flow hedges
6.8.4.For the purpose of determining whether a forecast transaction (or a component thereof) is highly probable as required by paragraph 6.3.3, an entity shall assume that the interest rate benchmark on which the hedged cash flows (contractually or non-contractually specified) are based is not altered as a result of interest rate benchmark reform.
Reclassifying the amount accumulated in the cash flow hedge reserve
6.8.5.For the purpose of applying the requirement in paragraph 6.5.12 in order to determine whether the hedged future cash flows are expected to occur, an entity shall assume that the interest rate benchmark on which the hedged cash flows (contractually or non-contractually specified) are based is not altered as a result of interest rate benchmark reform.
Assessing the economic relationship between the hedged item and the hedging instrument
6.8.6.For the purpose of applying the requirements in paragraphs 6.4.1(c)(i) and B6.4.4–B6.4.6, an entity shall assume that the interest rate benchmark on which the hedged cash flows and/or the hedged risk (contractually or non-contractually specified) are based, or the interest rate benchmark on which the cash flows of the hedging instrument are based, is not altered as a result of interest rate benchmark reform.
Designating a component of an item as a hedged item
6.8.7.Unless paragraph 6.8.8 applies, for a hedge of a non-contractually specified benchmark component of interest rate risk, an entity shall apply the requirement in paragraphs 6.3.7(a) and B6.3.8—that the risk component shall be separately identifiable—only at the inception of the hedging relationship.
6.8.8.When an entity, consistent with its hedge documentation, frequently resets (ie discontinues and restarts) a hedging relationship because both the hedging instrument and the hedged item frequently change (ie the entity uses a dynamic process in which both the hedged items and the hedging instruments used to manage that exposure do not remain the same for long), the entity shall apply the requirement in paragraphs 6.3.7(a) and B6.3.8—that the risk component is separately identifiable—only when it initially designates a hedged item in that hedging relationship. A hedged item that has been assessed at the time of its initial designation in the hedging relationship, whether it was at the time of the hedge inception or subsequently, is not reassessed at any subsequent redesignation in the same hedging relationship.
End of application
6.8.9.An entity shall prospectively cease applying paragraph 6.8.4 to a hedged item at the earlier of:
(a)

when the uncertainty arising from interest rate benchmark reform is no longer present with respect to the timing and the amount of the interest rate benchmark-based cash flows of the hedged item; and

(b)

when the hedging relationship that the hedged item is part of is discontinued.

6.8.10.An entity shall prospectively cease applying paragraph 6.8.5 at the earlier of:
(a)

when the uncertainty arising from interest rate benchmark reform is no longer present with respect to the timing and the amount of the interest rate benchmark-based future cash flows of the hedged item; and

(b)

when the entire amount accumulated in the cash flow hedge reserve with respect to that discontinued hedging relationship has been reclassified to profit or loss.

6.8.11.An entity shall prospectively cease applying paragraph 6.8.6:
(a)

to a hedged item, when the uncertainty arising from interest rate benchmark reform is no longer present with respect to the hedged risk or the timing and the amount of the interest rate benchmark-based cash flows of the hedged item; and

(b)

to a hedging instrument, when the uncertainty arising from interest rate benchmark reform is no longer present with respect to the timing and the amount of the interest rate benchmark-based cash flows of the hedging instrument.

If the hedging relationship that the hedged item and the hedging instrument are part of is discontinued earlier than the date specified in paragraph 6.8.11(a) or the date specified in paragraph 6.8.11(b), the entity shall prospectively cease applying paragraph 6.8.6 to that hedging relationship at the date of discontinuation.

6.8.12.When designating a group of items as the hedged item, or a combination of financial instruments as the hedging instrument, an entity shall prospectively cease applying paragraphs 6.8.4–6.8.6 to an individual item or financial instrument in accordance with paragraphs 6.8.9, 6.8.10, or 6.8.11, as relevant, when the uncertainty arising from interest rate benchmark reform is no longer present with respect to the hedged risk and/or the timing and the amount of the interest rate benchmark-based cash flows of that item or financial instrument.
(1)

The report, ‘Reforming Major Interest Rate Benchmarks’, is available at http://www.fsb.org/wp-content/uploads/r_140722.pdf.