Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (Text with EEA relevance)

 Help about what version

What Version

 Help about opening options

Opening Options

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are outstanding changes not yet made to Commission Regulation (EU) 2016/631. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made to the legislation appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.

View outstanding changes

Changes and effects yet to be applied to :

Changes and effects yet to be applied to the whole legislation item and associated provisions

  1. Introductory Text

  2. TITLE I GENERAL PROVISIONS

    1. Article 1.Subject matter

    2. Article 2.Definitions

    3. Article 3.Scope of application

    4. Article 4.Application to existing power-generating modules

    5. Article 5.Determination of significance

    6. Article 6.Application to power-generating modules, pump-storage power-generating modules, combined heat and power facilities, and industrial sites

    7. Article 7.Regulatory aspects

    8. Article 8.Multiple TSOs

    9. Article 9.Recovery of costs

    10. Article 10.Public consultation

    11. Article 11.Stakeholder involvement

    12. Article 12.Confidentiality obligations

  3. TITLE II REQUIREMENTS

    1. CHAPTER 1 General requirements

      1. Article 13.General requirements for type A power-generating modules

      2. Article 14.General requirements for type B power-generating modules

      3. Article 15.General requirements for type C power-generating modules

      4. Article 16.General requirements for type D power-generating modules

    2. CHAPTER 2 Requirements for synchronous power-generating modules

      1. Article 17.Requirements for type B synchronous power-generating modules

      2. Article 18.Requirements for type C synchronous power-generating modules

      3. Article 19.Requirements for type D synchronous power-generating modules

    3. CHAPTER 3 Requirements for power park modules

      1. Article 20.Requirements for type B power park modules

      2. Article 21.Requirements for type C power park modules

      3. Article 22.Requirements for type D power park modules

    4. CHAPTER 4 Requirements for offshore power park modules

      1. Article 23.General provisions

      2. Article 24.Frequency stability requirements applicable to AC-connected offshore power park modules

      3. Article 25.Voltage stability requirements applicable to AC-connected offshore power park modules

      4. Article 26.Robustness requirements applicable to AC-connected offshore power park modules

      5. Article 27.System restoration requirements applicable to AC-connected offshore power park modules

      6. Article 28.General system management requirements applicable to AC-connected offshore power park modules

  4. TITLE III OPERATIONAL NOTIFICATION PROCEDURE FOR CONNECTION

    1. CHAPTER 1 Connection of new power-generating modules

      1. Article 29.General provisions

      2. Article 30.Operational notification of type A power-generating modules

      3. Article 31.Operational notification of type B, C and D power-generating modules

      4. Article 32.Procedure for type B and C power-generating modules

      5. Article 33.Procedure for type D power-generating modules

      6. Article 34.Energisation operational notification for type D power-generating modules

      7. Article 35.Interim operational notification for type D power-generating modules

      8. Article 36.Final operational notification for type D power-generating modules

      9. Article 37.Limited operational notification for type D power-generating modules

    2. CHAPTER 2 Cost-benefit analysis

      1. Article 38.Identification of costs and benefits of application of requirements to existing power-generating modules

      2. Article 39.Principles of cost-benefit analysis

  5. TITLE IV COMPLIANCE

    1. CHAPTER 1 Compliance monitoring

      1. Article 40.Responsibility of the power-generating facility owner

      2. Article 41.Tasks of the relevant system operator

      3. Article 42.Common provisions for compliance testing

      4. Article 43.Common provisions on compliance simulation

    2. CHAPTER 2 Compliance testing for synchronous power-generating modules

      1. Article 44.Compliance tests for type B synchronous power-generating modules

      2. Article 45.Compliance tests for type C synchronous power-generating modules

      3. Article 46.Compliance tests for type D synchronous power-generating modules

    3. CHAPTER 3 Compliance testing for power park modules

      1. Article 47.Compliance tests for type B power park modules

      2. Article 48.Compliance tests for type C power park modules

      3. Article 49.Compliance tests for type D power park modules

    4. CHAPTER 4 Compliance testing for offshore power park modules

      1. Article 50.Compliance tests for offshore power park modules

    5. CHAPTER 5 Compliance simulations for synchronous power-generating modules

      1. Article 51.Compliance simulations for type B synchronous power-generating modules

      2. Article 52.Compliance simulations for type C synchronous power-generating modules

      3. Article 53.Compliance simulations for type D synchronous power-generating modules

    6. CHAPTER 6 Compliance simulations for power park modules

      1. Article 54.Compliance simulations for type B power park modules

      2. Article 55.Compliance simulations for type C power park modules

      3. Article 56.Compliance simulations for type D power park modules

    7. CHAPTER 7 Compliance simulations for offshore power park modules

      1. Article 57.Compliance simulations applicable to offshore power park modules

    8. CHAPTER 8 Non-binding guidance and monitoring of implementation

      1. Article 58.Non-binding guidance on implementation

      2. Article 59.Monitoring

  6. TITLE V DEROGATIONS

    1. Article 60.Power to grant derogations

    2. Article 61.General provisions

    3. Article 62.Request for a derogation by a power-generating facility owner

    4. Article 63.Request for a derogation by a relevant system operator or relevant TSO

    5. Article 64.Register of derogations from the requirements of this Regulation

    6. Article 65.Monitoring of derogations

  7. TITLE VI TRANSITIONAL ARRANGEMENTS FOR EMERGING TECHNOLOGIES

    1. Article 66.Emerging technologies

    2. Article 67.Establishment of thresholds for classification as emerging technologies

    3. Article 68.Application for classification as an emerging technology

    4. Article 69.Assessment and approval of requests for classification as an emerging technology

    5. Article 70.Withdrawal of classification as an emerging technology

  8. TITLE VII FINAL PROVISIONS

    1. Article 71.Amendment of contracts and general terms and conditions

    2. Article 72.Entry into force

  9. Signature

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources