Search Legislation

Commission Decision of 9 November 2006 amending the Annex to Regulation (EC) No 1228/2003 on conditions for access to the network for cross-border exchanges in electricity (Text with EEA relevance) (2006/770/EC)

 Help about what version

What Version

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

This version of this Decision was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

  1. Introductory Text

  2. Article 1.The Annex to Regulation (EC) No 1228/2003 is replaced by...

  3. Article 2.This Decision shall enter into force on the twentieth day...

  4. Signature

    1. ANNEX

      Guidelines on the management and allocation of available transfer capacity of interconnections between national systems

      1. 1. General Provisions

        1. 1.1. TSOs shall endeavour to accept all commercial transactions, including those...

        2. 1.2. When there is no congestion, there shall be no restriction...

        3. 1.3. Where scheduled commercial transactions are not compatible with secure network...

        4. 1.4. If structural congestion appears, appropriate congestion management rules and arrangements...

        5. 1.5. The methods adopted for congestion management shall give efficient economic...

        6. 1.6. No transaction-based distinction may be applied in congestion management. A...

        7. 1.7. When defining appropriate network areas in and between which congestion...

        8. 1.8. When balancing the network inside the control area through operational...

        9. 1.9. By not later than 1 January 2008, mechanisms for the...

        10. 1.10. The national Regulatory Authorities shall regularly evaluate the congestion management...

      2. 2. Congestion management methods

        1. 2.1. Congestion management methods shall be market-based in order to facilitate...

        2. 2.2. Depending on competition conditions, the congestion management mechanisms may need...

        3. 2.3. Each capacity allocation procedure shall allocate a prescribed fraction of...

        4. 2.4. TSOs shall optimise the degree to which capacity is firm,...

        5. 2.5. The access rights for long- and medium-term allocations shall be...

        6. 2.6. TSOs shall define an appropriate structure for the allocation of...

        7. 2.7. Capacity allocation may not discriminate between market participants that wish...

        8. 2.8. In regions where forward financial electricity markets are well developed...

        9. 2.9. Other than in the case of new interconnectors which benefit...

        10. 2.10. In principle, all potential market participants shall be permitted to...

        11. 2.11. Market participants shall firmly nominate their use of the capacity...

        12. 2.12. Capacity shall be freely tradable on a secondary basis, provided...

        13. 2.13. The financial consequences of failure to honour obligations associated with...

      3. 3. Coordination

        1. 3.1. Capacity allocation at an interconnection shall be coordinated and implemented...

        2. 3.2. A common coordinated congestion management method and procedure for the...

        3. 3.3. The regions referred to in 2.8. may allocate all interconnection...

        4. 3.4. Compatible congestion management procedures shall be defined in all these...

        5. 3.5. With a view to promoting fair and efficient competition and...

        6. 3.6. Coordination shall also include the exchange of information between TSOs....

      4. 4. Timetable for market operations

        1. 4.1. The allocation of the available transmission capacity shall take place...

        2. 4.2. Having full regard to network security, the nomination of transmission...

        3. 4.3. Successive intra-day allocations of available transmission capacity for day D...

        4. 4.4. When preparing day-ahead grid operation, the TSOs shall exchange information...

      5. 5. Transparency

        1. 5.1. TSOs shall publish all relevant data related to network availability,...

        2. 5.2. TSOs shall publish a general description of the congestion management...

        3. 5.3. The congestion management and capacity allocation procedures in use, together...

        4. 5.4. The operational and planning security standards shall form an integral...

        5. 5.5. TSOs shall publish all relevant data concerning cross-border trade on...

        6. 5.6. All relevant information shall be available for the market in...

        7. 5.7. The TSO shall publish the relevant information on forecast demand...

        8. 5.8. When forecasts are published, the ex post realised values for...

        9. 5.9. All information published by the TSOs shall be made freely...

        10. 5.10. TSOs shall exchange regularly a set of sufficiently accurate network...

      6. 6. Use of congestion income

        1. 6.1. Congestion management procedures associated with a pre-specified timeframe may generate...

        2. 6.2. National Regulatory Authorities shall be transparent regarding the use of...

        3. 6.3. The congestion income shall be shared among the TSOs involved...

        4. 6.4. TSOs shall clearly establish beforehand the use they will make...

        5. 6.5. On an annual basis, and by 31 July each year,...

        6. 6.6. The use of congestion income for investment to maintain or...

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources