Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
9.—(1) An EIA application must be accompanied by an environmental impact assessment report (“EIA report”).
(2) An EIA report is a report prepared in accordance with this rule by the applicant which assesses the environmental impact of the proposed works that are the subject of the application and which includes (at least)—
(a)a description of the works comprising information on the site, design, size and other relevant features of the works;
(b)a description of the likely significant effects of the works on the environment;
(c)a description of the features of the works and any measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;
(d)a description of the reasonable alternatives studied by the applicant, which are relevant to the works and their specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the works on the environment;
(e)a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and
(f)any other information specified in schedule 1 relevant to the specific characteristics of the works and to the environmental features likely to be affected.
(3) Where a scoping opinion has been issued, the EIA report must be based on that scoping opinion and must include the information that may reasonably be required for reaching a reasoned conclusion on the significant effects of the works on the environment, taking into account current knowledge and methods of assessment.
(4) With a view to avoiding duplication of assessments, account is to be taken of the available results of other relevant assessments under F2... national legislation in preparing the EIA report.
(5) In order to ensure the completeness and quality of the EIA report—
(a)the applicant must ensure that the EIA report is prepared by competent experts; and
(b)the EIA report must be accompanied by a statement from the applicant outlining the relevant expertise of such experts.]
Textual Amendments
F1Rule 9 substituted (16.5.2017) by The Transport and Works (Scotland) Act 2007 (Applications and Objections Procedure) Amendment Rules 2017 (S.S.I. 2017/74), rules 1, 9 (with rule 19)
F2Words in rule 9(4) omitted (31.12.2020) by virtue of The Environmental Impact Assessment (Transport) (EU Exit) (Scotland) (Amendment) Regulations 2019 (S.S.I. 2019/415), regs. 1, 4(4); 2020 c. 1, Sch. 5 para. 1(1)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: