10.—(1) Article 26 (renewable output of a qualifying combined heat and power generating station) is amended as follows.
(2) In paragraph (1)—
(a)after “permitted ancillary purposes” insert “or is an advanced fuel”; and
(b)omit “gasification, pyrolysis or”.
(3) In paragraph (2) (modification of article 25 of the 2009 order) in substitute paragraph (ii)—
(a)in sub-paragraph (aa) for “sub-paragraph (bb) or (cc)” substitute “sub-paragraph (cc)”; and
(b)omit sub-paragraph (bb).
(4) For paragraph (3) substitute—
“(3) For paragraphs (5)(a) and (5)(b) of that article, substitute—
“(a)F is the energy content of the renewable sources used when generating electricity in that way during that month less the energy content of—
(i)any fossil fuel from which those renewable sources are in part composed (other than fossil fuel from which a fuel the energy content of which is deducted by virtue of paragraph (ii) is in part composed);
(ii)except in the case of an excepted generating station, any of those renewable sources which is a gaseous fuel produced by means of gasification or pyrolysis and which has a gross calorific value when measured at 25 degrees Celsius and 0.1 megapascals at the inlet to the station of less than two megajoules per metre cubed;
(b)G is the energy content of all of the renewable sources used in generating the station’s gross output during that month less the energy content of—
(i)any fossil fuel from which those renewable sources are in part composed (other than fossil fuel from which a fuel the energy content of which is deducted by virtue of paragraph (ii) is in part composed);
(ii)except in the case of an excepted generating station, any of those renewable sources which is a gaseous fuel produced by means of gasification or pyrolysis and which has a gross calorific value when measured at 25 degrees Celsius and 0.1 megapascals at the inlet to the station of less than two megajoules per metre cubed;”.”.
(5) Omit paragraph (4).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: