Highways Act 1980, Section 105A is up to date with all changes known to be in force on or before 27 February 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

[F1[F2105A Screening of projects for constructing or improving highwaysE+W

(1)If a project authority is considering a project for constructing or improving a highway for which it is the highway authority, the project authority must, before details of the project are published, determine—

(a)whether or not the project [F3is of a type specified in] Annex I or Annex II, and

(b)if it considers the project is a relevant project [F4of a type specified in] Annex II, whether it should be made subject to an environmental impact assessment.

(2)In this Part “project authority” means—

(a)the Secretary of State,

(b)the Welsh Ministers, or

(c)a strategic highways company.

(3)When making a determination under subsection (1)(b), a project authority must have regard to the following—

(a)the information [F5described in] Annex II.A,

(b)the selection criteria [F6set out] in Annex III,

(c)any features of the project or measures envisaged to avoid or prevent what might otherwise be significant adverse effects on the environment, and

(d)the results of any relevant environmental assessment which are reasonably available to the authority.

(4)The project authority must make a determination under subsection (1)(b)—

(a)as soon as possible, and

(b)in any event within the period of 90 days beginning with the day on which it has access to the information mentioned in paragraphs (a), (c) and (d) of subsection (3).

(5)If the project authority is satisfied that it is appropriate to do so by reason of exceptional circumstances relating to a project (including circumstances relating to the nature, complexity, location or size of project), it may extend the period specified in subsection (4)(b).]]

Back to top

Options/Help

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?