Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)Subject to section 249 below, a highway authority may acquire land which is required for, or for use by them in connection with, the carrying out of works authorised by section 129 above, or by an order relating to a classified road under section 14 above.
(2)Without prejudice to any other power conferred by this Act—
(a)a highway authority may acquire land which is required for use by them in connection with the construction or improvement of a highway, or with the carrying out of works authorised by an order relating to a trunk road under section 14 above or an order under section 18 or section 108(1) above; and
(b)any power of a highway authority under subsection (1) above or under any provision of this Part of this Act not contained in this section to acquire land for a purpose whose achievement involves the diversion of a navigable watercourse or the carrying out of works under section 110 above includes power to acquire land which is required for carrying out the diversion or, as the case may be, the works.
(3)Subject to section 249 below, the Minister[F1or a strategic highways company] may acquire land which is required for the purpose of—
(a)providing a trunk road picnic area; or
(b)providing public sanitary conveniences in the exercise of his[F2or its] powers under section 112(5) above.
(4)A local highway authority may acquire land which is required for the purpose of providing public sanitary conveniences in the exercise of their powers under section 114 above.
(5)Subject to section 249 below, a highway authority may acquire land which is required for the purpose of providing a lorry area in the exercise of their powers under section 115 above.
(6)Where, in exercise of any of the powers conferred by subsections (1) to (5) above, a highway authority have acquired, or propose to acquire, for any purpose land forming part of a common, open space or fuel or field garden allotment and other land is required for the purpose of being given in exchange for the first-mentioned land, the authority may acquire that other land.
Textual Amendments
F1Words in s. 240(3) inserted (5.3.2015) by Infrastructure Act 2015 (c. 7), s. 57(1), Sch. 1 para. 46(a); S.I. 2015/481, reg. 2(a)
F2Words in s. 240(3)(b) inserted (5.3.2015) by Infrastructure Act 2015 (c. 7), s. 57(1), Sch. 1 para. 46(b); S.I. 2015/481, reg. 2(a)
Modifications etc. (not altering text)
C1S. 240(1)(2)(a)(5) functions exercisable jointly (1.4.2018) by The Sub-national Transport Body (Transport for the North) Regulations 2018 (S.I. 2018/103), regs. 1(2), 9(2), 10(e)
C2S. 240(1)(2)(a)(6) functions exercisable concurrently (1.4.2018) by The Sub-national Transport Body (Transport for the North) Regulations 2018 (S.I. 2018/103), regs. 1(2), 9(3), 11(g)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: