- Latest available (Revised)
- Original (As enacted)
Gas Act 1986, Section 7B is up to date with all changes known to be in force on or before 30 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)An application for a licence or an extension or restriction of a licence shall be made in such form and manner, and shall contain, or be accompanied by, such information and documents and such fee (if any), as may be prescribed.
(2)Within the prescribed period after the making of an application for a licence or an extension or restriction of a licence, the applicant shall—
(a)publish a notice of the application in the prescribed manner; and
(b)in the case of an application for a licence or extension under section 7 above, give notice of the application to any [F2gas transporters] whose authorised area includes the whole or any part of the area to which the application relates.
[F3(2A)Where the Authority proposes to refuse the application, it shall give to the applicant a notice—
(a)stating that it proposes to refuse the application;
(b)stating the reasons why it proposes to refuse the application; and
(c)specifying the time within which representations with respect to the proposed refusal may be made,
and shall consider any representations which are duly made and not withdrawn.]
[F4(2B)At any time when regulations made under section 41HC are in force, subsections (1) to (2A) do not apply to an application for a smart meter communication licence.]
[F5(2C)Subsections (1) to (2A) do not apply to an application for a code manager licence.]
(3)A licence or an extension or restriction of a licence shall be in writing and, unless revoked or suspended in accordance with any term contained in it [F6and subject to subsection (3A)], a licence shall continue in force for such period as may be specified in or determined by or under the licence.
[F7(3A)If a person who holds a gas system planner licence ceases at any time to hold a licence under section 6(1)(da) of the Electricity Act 1989, the person is to be treated as ceasing to hold the gas system planner licence at the same time.]
(4)A licence may include—
(a)such conditions (whether or not relating to the activities authorised by the licence) as appear to the [F8grantor] to be requisite or expedient having regard to the duties imposed by [F9sections 4AA, 4AB and 4A];
F10(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(c)conditions requiring the rendering to the Director of a payment on the grant of the licence or payments during the currency of the licence or both of such amount or amounts as may be determined by or under the licence; F11. . .
F11(d). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
[F12(4A)Without prejudice to the generality of paragraph (a) of subsection (4), conditions included in a licence under section 7 by virtue of that paragraph—
(a)may require the licence holder to enter into agreements with other persons for the use of any pipe-line system of his (wherever situated and whether or not used for the purpose of carrying on the activities authorised by the licence) for such purposes as may be specified in the conditions;
(b)may include provision for determining the terms on which such agreements are to be entered into.]
(5)Without prejudice to the generality of paragraph (a) of subsection (4) above—
(a)conditions included by virtue of that paragraph in a licence may—
(i)require the holder to comply with any direction given by the Director or the Secretary of State as to such matters as are specified in the licence or are of a description so specified;
(ii)require the holder, except in so far as the Director or the Secretary of State consents to his doing or not doing them, not to do or to do such things as are specified in the licence or are of a description so specified; and
(iii)provide for the determination by the Director, the Secretary of State or the Health and Safety Executive of such questions arising under the licence, or under any document [F13referred to] in the licence, as are specified in the licence or are of a description so specified; and
(b)conditions included by virtue of that paragraph in a licence under section 7 [F14or 7AA] above may require the holder, in such circumstances as are specified in the licence—
(i)so to increase [F15the charges payable to the holder in connection with the conveyance of gas, or in connection with the exercise of any other functions under or by virtue of the licence,] as to raise such amounts as may be determined by or under the conditions; and
(ii)to pay the amounts so raised to such holders of [F16licences under this Part or under section 6 of the Electricity Act 1989] as may be so determined.
[F17(5ZA)Without prejudice to the generality of paragraph (a) of subsection (4), conditions for or in connection with the purpose set out in subsection (5ZB) may be included in a licence under section 7AA by virtue of that paragraph.
(5ZB)The purpose is to facilitate or ensure the effective performance (whether in relation to Northern Ireland or any other part of the United Kingdom), at relevant times, of functions of a hydrogen production allocation body under Chapter 1 of Part 2 of the Energy Act 2023.
(5ZC)In subsection (5ZB) “relevant times” means times when the hydrogen production allocation body holds a licence under section 7AA.]
[F18(5A)Without prejudice to the generality of paragraph (a) of subsection (4), conditions which are described in subsection (5B) may be included in a smart meter communication licence [F19or in a code manager licence] by virtue of that paragraph, in respect of circumstances where a person holds such a licence (the “licence holder”), and another person has applied or is considering whether to apply for a [F20a licence of the same type] (“the applicant”).
(5B)The conditions in this subsection are conditions which require the licence holder to comply with a direction given by the [F21relevant authority] requiring the licence holder to provide to the applicant—
(a)information in relation to the activities authorised by the licence; or
(b)such other assistance as may be reasonably required by the applicant, including access to any facilities or equipment being used in connection with the activities authorised by the licence, in order that the applicant can—
(i)determine whether to apply for a licence; or
(ii)take part in a competition for a licence [F22or (in the case of an application for a code manager licence) apply for a licence otherwise than as part of a competition].
(5C)Subject to subsection (5E) and without prejudice to the generality of paragraph (a) of subsection (4), conditions which are described in subsection (5D) may be included in a smart meter communication licence [F23or in a code manager licence] by virtue of that paragraph, in respect of circumstances where such a licence held by a person (the “first licensee”) will cease to have effect, and another such licence is to be granted or has been granted to a different person (the “second licensee”).
(5D)The conditions in this subsection are conditions which require compliance with a direction given by [F24the relevant authority] requiring—
(a)the transfer of property, rights or liabilities from the first licensee to the second licensee;
(b)the creation of rights in relation to property, rights or liabilities in favour of the second licensee;
(c)the creation of other rights and liabilities as between the first and second licensee;
(d)the first or second licensee to enter into a written agreement with each other, or the first licensee to execute an instrument of another kind in favour of the second licensee;
(e)the first or second licensee to pay compensation to the other, or to any third party who is affected by any of the matters referred to in paragraphs (a) to (d).
(5E)Conditions included in a licence by virtue of subsection (5C) must provide that the licensee does not have a duty to comply with a direction of the kind referred to in subsection (5D) unless, in relation to that direction, the following conditions have been satisfied prior to it being given—
(a)the [F25relevant authority] has given written notice to the first licensee, the second licensee and any other person who would potentially be affected by the direction, including a copy of the proposed direction and inviting them to submit written representations, giving a minimum period of 21 days in which those representations can be made; and
(b)after the end of the period set out in the notice under paragraph (a), the [F26relevant authority] has considered those representations and determined that—
(i)it is appropriate in all the circumstances that the proposed direction is given; and
(ii)the arrangements of a type referred to in paragraphs (a) to (d) of subsection (5D) in the direction are necessary or expedient for the operational purposes of the second licensee, or are agreed by the first licensee and the second licensee to be necessary or expedient for those purposes.
(5F)For the purposes of subsection (5E), the operational purposes of the second licensee are the purposes of performing any functions which the second licensee has, or will have—
(a)under or by virtue of the smart meter communication licence which has been, or is to be, granted; or
(b)under or by virtue of any enactment, in the second licensee’s capacity as holder of that licence.]
[F27(5FA)In subsections (5B) to (5E), “the relevant authority” means—
(a)in relation to a smart meter communication licence, the Secretary of State or the Authority;
(b)in relation to a code manager licence, the Authority.]
(6)Conditions included in a licence may—
(a)impose requirements by reference to designation, acceptance or approval by the Director, the Secretary of State or the Health and Safety Executive; and
(b)provide for references in the conditions to any document F28. . . to operate as references to that document as revised or re-issued from time to time.
(7)Conditions included in a licence may contain provision for the conditions to—
(a)have effect or cease to have effect at such times and in such circumstances as may be determined by or under the conditions; or
(b)be modified in such manner as may be specified in the conditions at such times and in such circumstances as may be so determined.
(8)Any provision included in a licence by virtue of subsection (7) above shall have effect in addition to the provision made by this Part with respect to the modification of the conditions of a licence.
(9)As soon as practicable after granting a licence or an extension or restriction of a licence, the Director shall send a copy of the licence or extension or restriction—
(a)to the Health and Safety Executive; F29. . .
(b)in the case of a licence [F30, extension or restriction] under section 7 above, to any public gas transporter whose authorised area [F31includes] the whole or any part of the area specified in the licence [F30, extension or restriction] [F32; and
(c)to any other person who holds a licence and whose interests may, in the opinion of the Authority, be affected by the grant.]
(10)Any sums received by the Director under or by virtue of this section shall be paid into the Consolidated Fund.]
[F33(11)In this section “prescribed” means prescribed in regulations made by the Authority.]
Textual Amendments
F1S. 7B inserted (1.3.1996) by 1995 c. 45, s. 7; S.I. 1996/218, art. 2
F2Words in s. 7B(2)(b)(9)(b) substituted (16.5.2001 for certain purposes and otherwise 1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. I para. 2(1); S.I. 2001/1781, art. 2, Sch. (subject to transitional provisions in arts. 3-10); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F3S. 7B(2A) inserted (1.10.2001) by 2000 c. 27, s. 74(2); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F4S. 7B(2B) inserted (19.9.2012) by The Electricity and Gas (Smart Meters Licensable Activity) Order 2012 (S.I. 2012/2400), arts. 1, 22(2)
F5S. 7B(2C) inserted (25.5.2024) by The Energy Act 2023 (Consequential Amendments) Regulations 2024 (S.I. 2024/706), regs. 1(2), 2(3)
F6Words in s. 7B(3) inserted (31.1.2024) by Energy Act 2023 (c. 52), ss. 168(4)(a), 334(1); S.I. 2024/32, reg. 3(a)(v)
F7S. 7B(3A) inserted (31.1.2024) by Energy Act 2023 (c. 52), ss. 168(4)(b), 334(1); S.I. 2024/32, reg. 3(a)(v)
F8Word in s. 7B(4)(a) substituted (19.9.2012) by virtue of The Electricity and Gas (Smart Meters Licensable Activity) Order 2012 (S.I. 2012/2400), arts. 1, 22(3)
F9Words in s. 7B(4)(a) substituted (20.12.2000) by 2000 c. 27, s. 74(3)(a); S.I. 2000/3343, art. 2, Sch. (subject to transitional provisions in arts. 3-15)
F10S. 7B(4)(b) omitted (20.12.2000) by virtue of 2000 c. 27, s. 74(3)(b); S.I. 2000/3343, art. 2, Sch. (subject to transitional provisions in arts. 3-15) and repealed (1.10.2001) by 2000 c. 27, s. 108, Sch. 8; S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F11S. 7B(4)(d) and word “and”preceding it repealed (7.11.2000) by 2000 c. 27, s. 108, Sch. 6 Pt. I para. 5, Sch. 8; S.I. 2000/2974, art. 2, Sch. (subject to transitional provisions in arts. 3-12)
F12S. 7B(4A) inserted (16.5.2001 for certain purposes and otherwise 1.10.2001) by 2000 c. 27, s. 74(4); S.I. 2001/1781, art. 2, Sch. (subject to transitional provisions in arts. 3-10); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F13Words s. 7B(5)(a)(iii) substituted (16.5.2001 for certain purposes and otherwise 1.10.2001) by 2000 c. 27, s. 74(5); S.I. 2001/1781, art. 2, Sch. (subject to transitional provisions in arts. 3-10); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F14Words in s. 7B(5)(b) inserted (31.1.2024) by Energy Act 2023 (c. 52), ss. 177(3)(a), 334(1); S.I. 2024/32, reg. 3(a)(vii)
F15Words in s. 7B(5)(b)(i) substituted (31.1.2024) by Energy Act 2023 (c. 52), ss. 177(3)(b), 334(1); S.I. 2024/32, reg. 3(a)(vii)
F16Words in s. 7B(5)(b)(ii) substituted (31.1.2024) by Energy Act 2023 (c. 52), ss. 177(3)(c), 334(1); S.I. 2024/32, reg. 3(a)(vii)
F17S. 7B(5ZA)-(5ZC) inserted (26.12.2023) by Energy Act 2023 (c. 52), ss. 80(1), 334(3)(b)
F18S. 7B(5A)-(5F) inserted (19.9.2012) by The Electricity and Gas (Smart Meters Licensable Activity) Order 2012 (S.I. 2012/2400), arts. 1, 22(5)
F19Words in s. 7B(5A) inserted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(8)(a), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F20Words in s. 7B(5A) substituted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(8)(b), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F21Words in s. 7B(5B) substituted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(9)(a), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F22Words in s. 7B(5B)(b)(ii) inserted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(9)(b), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F23Words in s. 7B(5C) inserted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(10), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F24Words in s. 7B(5D) substituted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(11), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F25Words in s. 7B(5E)(a) substituted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(12)(a), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F26Words in s. 7B(5E)(b) substituted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(12)(b), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F27S. 7B(5FA) inserted (10.9.2024) by Energy Act 2023 (c. 52), ss. 185(13), 334(1); S.I. 2024/890, reg. 2(b)(ii)
F28Words in s. 7B(6) shall cease to have effect (16.5.2001 for certain purposes and otherwise 1.10.2001) by 2000 c. 27, s. 74(6); S.I. 2001/1781, art. 2, Sch. (subject to transitional provisions in arts. 3-10); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20) and are repealed (1.10.2001) by 2000 c. 27, s. 108, Sch. 8; S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F29S. 7B(9): word “and”preceding para. (b) repealed (1.10.2001) by 2000 c. 27, s. 108, Sch. 8; S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)
F30Words in s. 7B(9)(b) substituted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6, Pt. I para. 6(a)(i); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F31Word in s. 7B(9)(b) substituted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. I para. 6(a)(ii); S.I. 2001/3266, arts. 1(2), 2, Sch. (subject to transitional provisions in arts. 3-20)
F32S. 7B(9)(c) and the word “and”immediately preceding (1.10.2001) by 2000 c. 27, s. 108, Sch. 6, Pt. I para. 6(b); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)
F33S. 7B(10) inserted (16.5.2001 for certain purposes, otherwise 1.10.2001) by 2000 c. 27, s. 74(7); S.I. 2001/1781, art. 2, Sch. (subject to transitional provisions in arts. 3-10); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)
Modifications etc. (not altering text)
C1S. 7B applied (with modifications) (1.3.1996) by S.I. 1996/399, art. 2(2)
C2S. 7B applied (with modifications) (8.11.1995 ) by 1995 c. 45, s. 17(1), Sch. 5 Pt. II para. 15(1)(4); S.I. 1996/218, art. 2
C3S. 7B applied (with modifications) (1.12.2004) by Energy Act 2004 (c. 20), ss. 152(3), 198(2); S.I. 2004/2575, art. 2(2), Sch. 2
C4S. 7B modified (26.12.2023) by Energy Act 2023 (c. 52), ss. 134, 334(3)(c)
C5S. 7B(1)-(2A) excluded (26.12.2023) by Energy Act 2023 (c. 52), ss. 135(6), 334(3)(c)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: