Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
7(1)Construction work which has drainage implications may not be commenced unless a drainage system for the work has been approved by the approving body.E+W
(2)For the purposes of sub-paragraph (1)—
(a)construction work means anything done by way of, in connection with or in preparation for the creation of a building or other structure, and
(b)construction work has drainage implications if the building or structure will affect the ability of land to absorb rainwater.
(3)Sub-paragraph (1) does not apply to work requiring development consent under section 31 of the Planning Act 2008 (nationally significant infrastructure projects).
(4)The Minister may by order—
(a)provide that a specified class of work is to be or not to be treated as construction work;
(b)provide for work to be or not to be treated as having drainage implications in specified circumstances;
(c)provide exceptions to sub-paragraph (1).
(5)For the avoidance of doubt, anything that covers land (such as a patio or other surface) is a structure for the purposes of sub-paragraph (2)(a).
Modifications etc. (not altering text)
C1Sch. 3 para. 7 excluded (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 21 para. 6
C2Sch. 3 para. 7 excluded (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 5(1)(d) (with art. 37(2))
C3Sch. 3 para. 7 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 21 para. 6
C4Sch. 3 para. 7 excluded (3.11.2022) by The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order 2022 (S.I. 2022/1067), arts. 1, 5(1)(d)
C5Sch. 3 para. 7 excluded (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 5 (with art. 34(2), Sch. 12 paras. 5, 47, 79)
C6Sch. 3 para. 7 excluded (25.4.2024) by The Network Rail (Church Fenton Level Crossing Reduction) Order 2024 (S.I. 2024/526), arts. 1, 5(1)
Commencement Information
I1Sch. 3 para. 7 in force at 2.5.2018 for specified purposes for W. by S.I. 2018/557, art. 2(b)
I2Sch. 3 para. 7 in force at 7.1.2019 for W. in so far as not already in force by S.I. 2018/557, art. 3(b)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: