Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
3E+WFor section 66D of the Water Industry Act 1991 (determinations and agreements) there is substituted—
(1)On the application of—
(a)a water supply licensee that has made a request under sections 66A to 66C, or
(b)a water undertaker to which such a request has been made,
the Authority may by order require a water undertaker to perform the duty in question under sections 66A to 66C, for such period and on such terms and conditions as may be specified in the order.
(2)The Authority may make an order under subsection (1) only if—
(a)in the case of an application relating to a duty under section 66A, 66AA, 66B or 66C, it appears to the Authority that the water undertaker is required to perform that duty under that section, or
(b)in the case of an application relating to duties under section 66C, it appears to the Authority that both water undertakers in question are required to perform duties under that section,
and it is satisfied that the parties cannot reach agreement within a reasonable time.
(3)An order under subsection (1) has effect as an agreement between—
(a)the water supply licensee, and
(b)the water undertaker required to perform the duty in question.
(4)On the application of a party to a section 66D agreement, and if the Authority is satisfied that the parties cannot reach agreement on the variation or termination of the agreement within a reasonable time, the Authority may by order vary or terminate the agreement.
(5)If an order under subsection (4) is made in relation to a section 66D agreement, the agreement—
(a)has effect subject to the provision made by the order, or
(b)ceases to have effect, as the case may be.
(6)An order under subsection (4) may require one party to the agreement to pay compensation to the other.
(7)Neither the CMA nor the Authority may exercise, in respect of an agreement for the performance of a duty under sections 66A to 66C by a water undertaker, the powers conferred by—
(a)section 32 of the Competition Act 1998 (directions in relation to agreements);
(b)section 35(2) of that Act (interim directions).
(8)Subsection (7)(b) does not apply to the exercise of powers in respect of conduct—
(a)which is connected with an agreement for the performance of a duty under sections 66A to 66C by a water undertaker, and
(b)in respect of which section 35(1) of the Competition Act 1998 applies because of an investigation under section 25 of that Act relating to a suspected infringement of the Chapter 2 prohibition imposed by section 18(1) of that Act.
(9)In this Chapter a reference to a section 66D agreement is a reference to—
(a)an agreement for the performance of a duty under sections 66A to 66C by a water undertaker, or
(b)an order deemed to be such an agreement under subsection (3), or
(c)an agreement varied by order under subsection (4).”
Commencement Information
I1Sch. 2 para. 3 in force at 1.4.2017 by S.I. 2017/462, art. 3(i)(iii) (with arts. 6-9)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: