Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
2(1)In its application by virtue of section 4(3), the Compulsory Purchase Act 1965 has effect as if it were subject to the following modifications.U.K.
(2)Omit section 4 (time for exercise of compulsory purchase powers).
[F1(3)In section 11(1B) (power to enter on and take possession of land the subject of a notice to treat after giving the specified notice)—
(a)in a case where the notice to treat relates only to one or more of the following—
(i)the acquisition of subsoil or under-surface of land, where the subsoil or under-surface lies more than 9 metres below the surface;
(ii)the acquisition of airspace over land;
(iii)an easement, restrictive covenant or other right over land,
for ““3 months”” substitute “ 1 month ”, and
(b)after ““11A(4)”” insert “ or (6) and (7) ”.]
[F2(3A)In section 11A (powers of entry: further notices of entry)—
(a)in subsection (1)(a), after ““land”” insert “ under that provision ”,
(b)in subsection (2), after ““land”” insert “ under that provision, to the extent that the newly identified person is the owner, lessee or occupier of the land, ”,
(c)in subsection (4)(a), for ““14 days”” substitute “ 7 days ”, and
(d)at the end insert—
“(5)Subsections (6) and (7) apply for the purposes of determining the period to be specified in the notice of entry under section 11(1) served on the newly identified person in a case where subsection (4) does not apply.
(6)The period specified in the notice must be—
(a)in a case where the notice to treat relates only to one or more of the following—
(i)the acquisition of subsoil or under-surface of land, where the subsoil or under-surface lies more than 9 metres below the surface;
(ii)the acquisition of airspace over land;
(iii)an easement, restrictive covenant or other right over land,
a period that ends no earlier than the end of the period of 7 days beginning with the day on which the notice of entry is served, and
(b)in any other case, a period that ends no earlier than the end of the period of 28 days beginning with the day on which the notice of entry is served.
(7)The period specified in the notice must end no earlier than the end of the period specified in any previous notice of entry given by the acquiring authority in respect of the land.”]
(4)In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for ““section 4 of this Act”” substitute “ section 10(1) of the High Speed Rail (London - West Midlands) Act 2017 ”.
[F3(4A)In Schedule 2A (proposal to acquire part only of a house, building or factory)—
(a)omit paragraphs 1(2) and 14(2), and
(b)at the end insert—
30In this Schedule, references to entering on and taking possession of land do not include doing so under Schedule 16 to the High Speed Rail (London - West Midlands) Act 2017 (temporary possession and use of land).”]
F4(5). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F1Sch. 6 para. 2(3) substituted (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 5(2); S.I. 2017/209, reg. 2
F2Sch. 6 para. 2(3A) inserted (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 5(3); S.I. 2017/209, reg. 2
F3Sch. 6 para. 2(4A) inserted (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 5(4); S.I. 2017/209, reg. 2
F4Sch. 6 para. 2(5) omitted (24.2.2017) by virtue of High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 5(5); S.I. 2017/209, reg. 2
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: