2.—(1) In their application to the works, article 3 of, and Part 11 of Schedule 2 to, the 1995 Order shall have effect as if the planning permission granted by that Order were subject to the restrictions contained in paragraphs 3 to 11 below.
(2) In their application to other development carried out on land which falls to be treated as operational land of a dock or harbour undertaker by virtue of this Order, article 3 of, and Part 17 of Schedule 2 to, the 1995 Order shall have effect as if the planning permission granted by that Order, were subject to the restrictions contained in paragraphs 3 to 11 below.
(3) The restrictions contained in paragraphs 3 to 8 below do not apply to temporary construction activity.
(4) For the purpose of the Town and Country Planning Act 1990(1), the restrictions contained in paragraphs 3 to 11 below shall be deemed to be conditions imposed on the grant of planning permission.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: