22.—(1) Subject to the following provisions of this article, Network Rail may at its own expense and from time to time carry out such protective works to any building within the Order limits and lying within 35 metres of any of the authorised works as Network Rail considers to be necessary or expedient.
(2) Protective works may be carried out—
(a)at any time before or during the construction in the vicinity of the building of any part of the authorised works; or
(b)after the completion of the construction of that part of the authorised works, at any time up to the end of the period of 5 years beginning with the day on which that part of the authorised works is first opened for use.
(3) For the purpose of determining how the functions under this article are to be exercised Network Rail may enter and survey any building falling within paragraph (1) and any land belonging to it.
(4) For the purpose of carrying out protective works under this article to a building Network Rail may (subject to paragraphs (5) and (6))—
(a)enter the building and any land belonging to it; and
(b)where the works cannot be carried out reasonably conveniently without entering land adjacent to the building, enter the adjacent land (but not any building erected on it).
(5) Before exercising—
(a)a right under paragraph (1) to carry out protective works to a building;
(b)a right under paragraph (3) to enter a building and any land belonging to it;
(c)a right under paragraph (4)(a) to enter a building or land; or
(d)a right under paragraph (4)(b) to enter land,
Network Rail shall, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days' notice of its intention to exercise that right and, in a case falling within sub-paragraph (a) or (c), specifying the protective works proposed to be carried out.
(6) Where notice is served under paragraph (5)(a), (c) or (d), the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the protective works or to enter the building or land to be referred to arbitration under article 51 (arbitration).
(7) Network Rail shall compensate the owners and occupiers of any building or land in relation to which the powers of this article have been exercised for any loss or damage arising to them by reason of the exercise of those powers.
(8) Where—
(a)protective works are carried out under this article to a building; and
(b)within the period of 5 years beginning with the day on which the part of the authorised works constructed within the vicinity of the building is first opened for use it appears that the protective works are inadequate to protect the building against damage caused by the construction or operation of that part of the works,
Network Rail shall compensate the owners and occupiers of the building for any damage sustained by them.
(9) Nothing in this article shall relieve Network Rail from any liability to pay compensation under section 10(2) of the 1965 Act.
(10) Any compensation payable under paragraph (7) or (8) shall be determined, in case of dispute, under Part 1 of the 1961 Act.
(11) In this article—
(a)“building” includes any structure or erection or any part of a building, structure or erection;
(b)any reference to a building within a specified distance of a work includes—
(i)in the case of a work under the surface of the ground, a reference to any building within the specified distance of the point on the surface below which the work is situated, and
(ii)where a work has not commenced, a reference to a building within the specified distance of the proposed site of the work, and
(c)“protective works”, in relation to a building, means—
(i)underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the construction, maintenance or operation of the authorised works, and
(ii)any works the purpose of which is to remedy any damage which has been caused to the building by the construction, maintenance or operation of the authorised works.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: