Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
The Building Regulations 2010, Section 6 is up to date with all changes known to be in force on or before 12 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
6.—(1) Where there is a material change of use of the whole of a building, such work, if any, shall be carried out as is necessary to ensure that the building complies with the applicable requirements of the following paragraphs of Schedule 1—
(a)in all cases, B1 (means of warning and escape)
B2 (internal fire spread—linings)
B3 (internal fire spread—structure)
B4(2) (external fire spread—roofs)
B5 (access and facilities for the fire service)
C2(c) (interstitial and surface condensation)
F1 (ventilation)
G1 (cold water supply)
G3(1) to (3) (hot water supply and systems)
G4 (sanitary conveniences and washing facilities)
G5 (bathrooms)
G6 (kitchens and food preparation areas)
F1...
H1 (foul water drainage)
H6 (solid waste storage)
J1 to J4 (combustion appliances)
L1 (conservation of fuel and power)
P1 (electrical safety);
[F2S2 (infrastructure for the charging of electric vehicles)]
[F3T1 (Toilet Accommodation)]
(b)in the case of a material change of use described in regulation 5(c), (d), (e) or (f), A1 to A3 (structure);
(c)in the case of a building exceeding [F4eleven] metres in height, B4(1) (external fire spread—walls);
(d)in the case of a material change of use described in regulation 5(a), (b), (c), (d), (g), (h), (i) or, where the material change provides new residential accommodation, (f), C1(2) (resistance to contaminants);
(e)in the case of a material change of use described in regulation 5(a), C2 (resistance to moisture);
(f)in the case of a material change of use described in regulation 5(a), (b), (c), (g), (h) or (i), E1 to E3 (resistance to the passage of sound);
(g)in the case of a material change of use described in regulation 5(e), where the public building consists of or contains a school, E4 (acoustic conditions in schools);
(h)in the case of a material change of use described in regulation 5(a) or (b), G2 (water efficiency) and G3(4) (hot water supply and systems: hot water supply to fixed baths);
(i)in the case of a material change of use described in regulation 5(c), (d), (e) or (j), [F5M1 (access to and use of buildings other than dwellings)];
[F6(j)in the case of a material change of use described in regulation 5(a), (b) or (g), Q1 (security)].
(2) Where there is a material change of use of part only of a building, such work, if any, shall be carried out as is necessary to ensure that—
(a)that part complies in all cases with any applicable requirements referred to in paragraph (1)(a);
(b)in a case in which sub-paragraphs (b), (e), (f), (g) or (h) of paragraph (1) apply, that part complies with the requirements referred to in the relevant sub-paragraph;
(c)in a case to which sub-paragraph (c) of paragraph (1) applies, the whole building complies with the requirement referred to in that sub-paragraph; F7...
(d)in a case to which sub-paragraph (i) of paragraph (1) applies—
(i)that part and any sanitary conveniences provided in or in connection with that part comply with the requirements referred to in that sub-paragraph; and
(ii)the building complies with requirement M1(a) of Schedule 1 to the extent that reasonable provision is made to provide either suitable independent access to that part or suitable access through the building to that part;
[F8(e)in a case to which subparagraph (j) applies in respect of a material change of use described in regulation 5(b) or (g), that part complies with the requirement referred to in that subparagraph].
[F9(3) Subject to paragraph (4), where there is a material change of use described in regulation 5(k), such work, if any, shall be carried out as is necessary to ensure that any external wall, or specified attachment, of the building only contains materials of European Classification A2-s1, d0 or A1 (classified in accordance with the reaction to fire classification).]
[F10(4) Paragraph (3) does not apply to the items listed in regulation 7(3).]
Extent Information
E1This version of this provision applies to England only; a separate version has been created for Wales only
Textual Amendments
F1Words in reg. 6(1)(a) omitted (15.7.2011) by virtue of The Building (Amendment) Regulations 2011 (S.I. 2011/1515), regs. 1(2), 3(3)
F2Words in reg. 6(1)(a) inserted (E.) (15.6.2022) by The Building Regulations etc. (Amendment) (England) (No. 2) Regulations 2021 (S.I. 2021/1392), regs. 1(2), 2(2) (with regs. 1(4), 4)
F3Words in reg. 6(1)(a) inserted (E.) (1.10.2024) by The Building (Amendment) (England) Regulations 2024 (S.I. 2024/645), regs. 1(2), 2(3) (with reg. 3)
F4Word in reg. 6(1)(c) substituted (E.) (1.12.2022) by The Building etc. (Amendment) (England) Regulations 2022 (S.I. 2022/603), regs. 1(4), 2(3)(a) (with reg. 4)
F5Words in reg. 6(1)(i) substituted (E., but only in relation to excepted energy buildings in W.) (1.10.2015) by The Building Regulations &c. (Amendment) Regulations 2015 (S.I. 2015/767), regs. 1(4)(b), 2(4)(a) (with regs. 1(3), 5) [Editorial note: This amendment no longer applies at all in relation to W. from 8.6.2018]
F6Reg. 6(1)(j) inserted (E., but only in relation to excepted energy buildings in W.) (1.10.2015) by The Building Regulations &c. (Amendment) Regulations 2015 (S.I. 2015/767), regs. 1(4)(b), 2(4)(b) (with regs. 1(3), 5) [Editorial note: This amendment no longer applies at all in relation to W. from 8.6.2018]
F7Word in reg. 6(2) omitted (E., but only in relation to excepted energy buildings in W.) (1.10.2015) by virtue of The Building Regulations &c. (Amendment) Regulations 2015 (S.I. 2015/767), regs. 1(4)(b), 2(4)(c)(i) (with regs. 1(3), 5) [Editorial note: This amendment no longer applies at all in relation to W. from 8.6.2018]
F8Reg. 6(2)(e) inserted (E., but only in relation to excepted energy buildings in W.) (1.10.2015) by The Building Regulations &c. (Amendment) Regulations 2015 (S.I. 2015/767), regs. 1(4)(b), 2(4)(c)(ii) (with regs. 1(3), 5) [Editorial note: This amendment no longer applies at all in relation to W. from 8.6.2018]
F9Reg. 6(3) substituted (E.) (1.12.2022) by The Building etc. (Amendment) (England) Regulations 2022 (S.I. 2022/603), regs. 1(4), 2(3)(b) (with reg. 4)
F10Reg. 6(3)(4) inserted (E.) (21.12.2018) by The Building (Amendment) Regulations 2018 (S.I. 2018/1230), regs. 1(4), 2(5) (with regs. 1(3), 3)
6.—(1) Where there is a material change of use of the whole of a building, such work, if any, shall be carried out as is necessary to ensure that the building complies with the applicable requirements of the following paragraphs of Schedule 1—
(a)in all cases, B1 (means of warning and escape)
B2 (internal fire spread—linings)
B3 (internal fire spread—structure)
B4(2) (external fire spread—roofs)
B5 (access and facilities for the fire service)
C2(c) (interstitial and surface condensation)
F1 (ventilation)
G1 (cold water supply)
G3(1) to (3) (hot water supply and systems)
G4 (sanitary conveniences and washing facilities)
G5 (bathrooms)
G6 (kitchens and food preparation areas)
F11...
H1 (foul water drainage)
H6 (solid waste storage)
J1 to J4 (combustion appliances)
L1 (conservation of fuel and power)
P1 (electrical safety);
(b)in the case of a material change of use described in regulation 5(c), (d), (e) or (f), A1 to A3 (structure);
(c)in the case of a building exceeding fifteen metres in height, B4(1) (external fire spread—walls);
(d)in the case of a material change of use described in regulation 5(a), (b), (c), (d), (g), (h), (i) or, where the material change provides new residential accommodation, (f), C1(2) (resistance to contaminants);
(e)in the case of a material change of use described in regulation 5(a), C2 (resistance to moisture);
(f)in the case of a material change of use described in regulation 5(a), (b), (c), (g), (h) or (i), E1 to E3 (resistance to the passage of sound);
(g)in the case of a material change of use described in regulation 5(e), where the public building consists of or contains a school, E4 (acoustic conditions in schools);
(h)in the case of a material change of use described in regulation 5(a) or (b), G2 (water efficiency) and G3(4) (hot water supply and systems: hot water supply to fixed baths);
(i)in the case of a material change of use described in regulation 5(c), (d), (e) or (j), M1 (access and use);
(2) Where there is a material change of use of part only of a building, such work, if any, shall be carried out as is necessary to ensure that—
(a)that part complies in all cases with any applicable requirements referred to in paragraph (1)(a);
(b)in a case in which sub-paragraphs (b), (e), (f), (g) or (h) of paragraph (1) apply, that part complies with the requirements referred to in the relevant sub-paragraph;
(c)in a case to which sub-paragraph (c) of paragraph (1) applies, the whole building complies with the requirement referred to in that sub-paragraph; and
(d)in a case to which sub-paragraph (i) of paragraph (1) applies—
(i)that part and any sanitary conveniences provided in or in connection with that part comply with the requirements referred to in that sub-paragraph; and
(ii)the building complies with requirement M1(a) of Schedule 1 to the extent that reasonable provision is made to provide either suitable independent access to that part or suitable access through the building to that part;
[F12(3) Subject to paragraph (4), where there is a material change of use described in regulation 5(k), such work, if any, must be carried out as is necessary to ensure that any external wall, or specified attachment, of the building only contains materials of a minimum European Classification A2-s1, d0 or A1, classified in accordance with BS EN 13501-1:2018 entitled “Fire classification of construction products and building elements. Classification using test data from reaction to fire tests” (ISBN 978 0 580 95726 0) published by the British Standards Institution on 14th January 2019.
(4) Paragraph (3) does not apply to the items listed in regulation 7(3).]
Extent Information
E2This version of this provision applies to Wales only; a separate version has been created for England only
Textual Amendments
F11Words in reg. 6(1)(a) omitted (15.7.2011) by virtue of The Building (Amendment) Regulations 2011 (S.I. 2011/1515), regs. 1(2), 3(3)
F12Reg. 6(3)(4) inserted (with a difference in the wording of reg. 6(3)) (W.) (13.1.2020) by The Building (Amendment) (Wales) Regulations 2019 (S.I. 2019/1499), regs. 1(4), 2(5) (with reg. 3)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: