Temporary use of land for construction of works

24.—(1) Network Rail may, in connection with the carrying out of the authorised works—

(a)enter upon and take temporary possession of—

(i)the land specified in columns (1) and (2) of Schedule 10 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the authorised works specified in column (4) of that Schedule; and

(ii)any other land within Order limits in respect of which no notice of entry has been served under section 11 of the 1965 Act (other than in connection with the acquisition of rights only) or no declaration has been made under section 4 of the Compulsory Purchase (Vesting Declaration) Act 1981(1);

(b)remove any buildings and vegetation from that land; and

(c)construct temporary works (including the provision of means of access) and buildings on the land.

(2) Not less than 14 days before entering upon and taking temporary possession of land under this article Network Rail shall serve notice of the intended entry on the owners and occupiers of the land.

(3) Network Rail may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of the land specified in columns (1) and (2) of Schedule 10, after the end of the period of 2 years beginning with the date of completion of the work specified in relation to that land in column (4) of that Schedule; or

(b)in the case of the land referred to in paragraph (1)(a) or (b) of article 17 (power to acquire land), after the end of the period of 2 years beginning with the date of completion of the work for which temporary possession of the land was taken unless Network Rail has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 in relation to that land.

(4) Subject to paragraph (5), before giving up possession of land of which temporary possession has been taken under this article, Network Rail shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but Network Rail shall not be required to replace a building removed under this article.

(5) Network Rail shall not be obliged to reinstate plot number 40 (the existing access road through the National Grid Operational Centre) following the completion of Work No. 5.

(6) Network Rail shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(8) Without affecting article 44 (no double recovery), nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (6).

(9) The powers of compulsory acquisition of land conferred by this Order shall not apply in relation to the land referred to in paragraph (1)(a)(i) except that Network Rail shall not be precluded from—

(a)acquiring new rights over, or imposing restrictive covenants affecting, any part of that land under article 20 (power to acquire new rights) or article 21 (new rights, etc., only to be acquired in certain lands); or

(b)acquiring any part of the subsoil (or rights in the subsoil) of that land under article 22 (power to acquire subsoil only).

(10) Where Network Rail takes possession of land under this article, it shall not be required to acquire the land or any interest in it.

(11) Section 13 of the 1965 Act shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 18(1) (application of Part 1 of the Compulsory Purchase Act 1965).