Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
3.—(1) The Agency may—
(a)construct and maintain the scheduled works; and
(b)break out and remove such structures that are contained within the limits of deviation as may be necessary or expedient for or in connection with the construction or maintenance of the scheduled works.
(2) Subject to article 4 (power to deviate), the scheduled works may only be constructed in the lines or situations shown on the works plans and in accordance with the levels shown on the sections.
(3) Subject to paragraph (6), the Agency may carry out and maintain such of the following works as may be necessary or expedient for the purpose of, or for purposes ancillary, to the construction of the scheduled works, namely—
(a)works for the strengthening, alteration or demolition, in whole or in part, of any building, structure or erection;
(b)works for the removal or retention, with such modifications as the Agency sees fit, of the existing velocity control structure in the river;
(c)works to alter the position of any street furniture or apparatus, including mains, sewers, drains, pipes, cables and lights;
(d)works to alter the course of, or otherwise interfere with, watercourses;
(e)landscaping, ecological and other works to mitigate any adverse effects of the construction, maintenance or operation of the other authorised works; and
(f)facilities and works for the benefit or protection of land or premises affected by the authorised works.
(4) Subject to paragraph (6) the Agency may carry out and maintain such other works (of whatever nature) as may be necessary or expedient for the purposes of, or for purposes ancillary to, the construction of the scheduled works.
(5) Where the Agency lays down conduits for the accommodation of cables or other apparatus for the purposes of or associated with the authorised works it may provide in, or in connection with, such conduits, accommodation for the apparatus of any other person, and manholes and other facilities for access to such accommodation, and may permit the use of such conduits and facilities on such terms and conditions as may be agreed between it and such other person.
(6) Paragraphs (3) and (4) only authorise the carrying out or maintenance of works within the limits of deviation.
(7) Section 9 of the Salmon and Freshwater Fisheries Act 1975(1) does not apply to the construction of the authorised works or to their alteration.
Commencement Information
I1Art. 3 in force at 7.8.2012, see art. 1
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: