Search Legislation

The Flood and Water Management Act 2010 (Commencement No. 2, Transitional and Savings Provisions) (England) Order 2013

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

Changes over time for: Section 4

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Flood and Water Management Act 2010 (Commencement No. 2, Transitional and Savings Provisions) (England) Order 2013, Section 4. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Transitional and savings provisionsE+W+S

4.—(1) Until paragraphs 2, 10 and 25 of Schedule 4 to the 2010 Act are brought fully into force in relation to England, references in sections A1(3) and (6), 6(6A) and 13(1) and (3) of the 1975 Act to “10,000” are to be read as references to “25,000”.

(2) For the relevant period, sections 11, 12 and 21(5) of the 1975 Act continue to apply in relation to a large raised reservoir in England as though paragraphs 16, 17 and 18 of Schedule 4 to the 2010 Act had not been brought into force in relation to England.

(3) In paragraph (2), “the relevant period” means the period beginning on 30th July 2013 and ending on the first date on which the Environment Agency gives notice to the undertaker of the large raised reservoir—

(a)that it has designated the reservoir as high-risk under section 2B(1) of the 1975 Act; or

(b)that it has not designated the reservoir as high-risk (whether or not having made a provisional designation under section 2A of the 1975 Act).

(4) But where the undertaker of a large raised reservoir who has been given a notice under section 2B(1) of the 1975 Act brings an appeal against the designation of the reservoir as high-risk, “the relevant period” in relation to that reservoir ends on the date on which the First-tier Tribunal either confirms or cancels the designation.

(5) In this article, “large raised reservoir” and “undertaker” have the same meanings as in section 1(1) and (4) respectively of the 1975 Act(1) as in force immediately before 30th July 2013.

(1)

Section 1(4) is amended by the Water Act 1989 (c. 15), Schedule 25, paragraph 49, and S.I. 1996/593, regulation 2 and Schedule 1.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources