Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Regulation 55
1. The name of the proposed scheme.U.K.
Commencement Information
I1Sch. 10 para. 1 in force at 1.1.2014, see reg. 1(2)
2. The name of the operator of the proposed scheme.U.K.
Commencement Information
I2Sch. 10 para. 2 in force at 1.1.2014, see reg. 1(2)
3. The address and telephone number [F1and, where available, email address] of the registered office of the operator of the proposed scheme or, if the operator is not registered in the United Kingdom, [F2the address of] the principal place of business and telephone number [F1and, where available, email address] of that operator.U.K.
Textual Amendments
F1Words in Sch. 10 para. 3 inserted (25.12.2015) by The Waste Electrical and Electronic Equipment (Amendment) Regulations 2015 (S.I. 2015/1968), regs. 1, 2(44)(b)
F2Words in Sch. 10 para. 3 inserted (25.12.2015) by The Waste Electrical and Electronic Equipment (Amendment) Regulations 2015 (S.I. 2015/1968), regs. 1, 2(44)(a)
Commencement Information
I3Sch. 10 para. 3 in force at 1.1.2014, see reg. 1(2)
4. Where the operator of the proposed scheme is a partnership, the names of all the partners.U.K.
Commencement Information
I4Sch. 10 para. 4 in force at 1.1.2014, see reg. 1(2)
5. The address for service of notices if different from that referred to in paragraph 3.U.K.
Commencement Information
I5Sch. 10 para. 5 in force at 1.1.2014, see reg. 1(2)
6. Confirmation of whether or not the operator of the proposed scheme has been convicted of an offence under these Regulations; and where a positive confirmation is given an explanation of how the contravention of these Regulations which resulted in the conviction occurred and what steps have been taken to ensure that such a contravention will not occur in the future.U.K.
Commencement Information
I6Sch. 10 para. 6 in force at 1.1.2014, see reg. 1(2)
7. The nature of the operator of the scheme’s legal personality.U.K.
Commencement Information
I7Sch. 10 para. 7 in force at 1.1.2014, see reg. 1(2)
8. The type of relationship between the operator of the proposed scheme and the scheme members (for example, contractual or partnership).U.K.
Commencement Information
I8Sch. 10 para. 8 in force at 1.1.2014, see reg. 1(2)
9. Details of how membership fees and any other sums payable to the operator of the proposed scheme by the scheme members are to be determined.U.K.
Commencement Information
I9Sch. 10 para. 9 in force at 1.1.2014, see reg. 1(2)
10. Details of any rules or regulations to be observed by the scheme members.U.K.
Commencement Information
I10Sch. 10 para. 10 in force at 1.1.2014, see reg. 1(2)
11. Details of the procedures under which the operator of the proposed scheme would enforce the rules or regulations against a scheme member.U.K.
Commencement Information
I11Sch. 10 para. 11 in force at 1.1.2014, see reg. 1(2)
12. Whether there is a minimum or maximum number of scheme members permitted.U.K.
Commencement Information
I12Sch. 10 para. 12 in force at 1.1.2014, see reg. 1(2)
13. Details of the eligibility criteria for membership of the proposed scheme.U.K.
Commencement Information
I13Sch. 10 para. 13 in force at 1.1.2014, see reg. 1(2)
14. Details of how evidence notes acquired by the operator of the proposed scheme in complying with his obligations under these Regulations will be allocated between scheme members in the event that approval of the proposed scheme is withdrawn under regulation 58.U.K.
Commencement Information
I14Sch. 10 para. 14 in force at 1.1.2014, see reg. 1(2)
15. Details of any arbitration procedure that will apply for the purpose of determining any dispute between scheme members and between scheme members and the operator of the proposed scheme.U.K.
Commencement Information
I15Sch. 10 para. 15 in force at 1.1.2014, see reg. 1(2)
16. Details of the arrangements in place for disseminating important information to scheme members in an accurate and timely manner.U.K.
Commencement Information
I16Sch. 10 para. 16 in force at 1.1.2014, see reg. 1(2)
17. That the rules or regulations of the proposed scheme or scheme provide—U.K.
(a)that a scheme member must apply to join the scheme for a relevant compliance period during which he has commenced putting EEE on the market in the United Kingdom; and
(b)that where a scheme member’s membership of the scheme is cancelled, any such cancellation cannot take effect until the end of the current compliance period.
Commencement Information
I17Sch. 10 para. 17 in force at 1.1.2014, see reg. 1(2)
18. That the proposed scheme or scheme has the necessary resources and systems in place to—U.K.
(a)maintain up to date records of its scheme members, including—
(i)their names and addresses, and
(ii)their EEE producer registration numbers;
(b)handle WEEE from private households, if it proposes to do so, (including collection and transportation to ATFs and funding of treatment, recovery and recycling) in order to discharge the operator of the scheme’s notified obligation under regulation 28 in an appropriate and timely manner;
(c)handle WEEE from users other than private households, if it proposes to do so, (including collection and transportation to ATFs and funding of treatment, recovery and recycling) in order to discharge the operator of the scheme’s obligations under regulation 29 in an appropriate and timely manner;
(d)where a proposed scheme is the subject of an application for approval made under regulation 55, or where a scheme is approved under that regulation for the purposes of regulation 28 , accept return of WEEE from private households free of charge from—
(i)distributors in accordance with regulation 43; and
(ii)final holders in accordance with regulation 52;
(e)keep, update and supply records to the appropriate authority as required under regulation 40 or 41;
(f)supply information to the appropriate authority as required under regulations 35 and 37 or 36 and 38;
(g)submit declarations of compliance and supporting evidence notes as required under regulation 39;
(h)check that the information supplied to it by its scheme members under regulation 18 is as accurate as reasonably possible and that the operator of the scheme’s submission of that information to the appropriate authority will meet a similar standard of accuracy; and
(i)maintain good environmental practices.
Commencement Information
I18Sch. 10 para. 18 in force at 1.1.2014, see reg. 1(2)
19. That the operator of the proposed scheme or scheme [F3must] co-operate with other operators of schemes in relation to developing working relationships with operators of designated collection facilities.U.K.
Textual Amendments
F3Word in Sch. 10 para. 19 substituted (25.7.2014) by virtue of The Waste Electrical and Electronic Equipment and Restriction of the Use of Certain Hazardous Substances in Electrical and Electronic Equipment (Amendment) Regulations 2014 (S.I. 2014/1771), regs. 1(b), 3(3), Sch. 2 Pt. 2
Commencement Information
I19Sch. 10 para. 19 in force at 1.1.2014, see reg. 1(2)
[F419A. That the proposed scheme or scheme, if it has been approved under regulation 55 for the purposes of regulation 28, complies with the requirement under regulation 34B to join a PBS.]U.K.
Textual Amendments
20. That the operator of the proposed scheme or scheme [F5must] co-operate with operators of designated collection facilities to comply with regulation 53.U.K.
Textual Amendments
F5Word in Sch. 10 para. 20 substituted (25.7.2014) by The Waste Electrical and Electronic Equipment and Restriction of the Use of Certain Hazardous Substances in Electrical and Electronic Equipment (Amendment) Regulations 2014 (S.I. 2014/1771), regs. 1(b), 3(3), Sch. 2 Pt. 2
Commencement Information
I20Sch. 10 para. 20 in force at 1.1.2014, see reg. 1(2)
21. That the operator of the proposed scheme or scheme is likely to be able to meet his expected treatment, recovery and recycling obligations.U.K.
Commencement Information
I21Sch. 10 para. 21 in force at 1.1.2014, see reg. 1(2)
22. That the proposed scheme or scheme is likely to assist in meeting the United Kingdom’s obligations in relation to the recovery of WEEE in respect of which an application for approval is being made or has been granted under regulation 55.U.K.
Commencement Information
I22Sch. 10 para. 22 in force at 1.1.2014, see reg. 1(2)
23. In the event that the operator of the proposed scheme or scheme contravenes any of the obligations placed on him under these Regulations, that it is likely that enforcement proceedings could be taken against the operator of the proposed scheme under these Regulations without a disproportionate cost to the enforcement authority.U.K.
Commencement Information
I23Sch. 10 para. 23 in force at 1.1.2014, see reg. 1(2)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: