The Brechfa Forest West Wind Farm Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. 1.Citation and Commencement

  3. 2.Interpretation

  4. 3.Development consent etc. granted by the Order

  5. 4.Procedure in relation to approvals etc under Requirements

  6. 5.Maintenance of authorised project

  7. 6.Power to deviate

  8. 7.Operation of generating station

  9. 8.Benefit of Order

  10. 9.Nuisance

  11. 10.Street works

  12. 11.Temporary stopping up of streets

  13. 12.Discharge of water

  14. 13.Application of landlord and tenant law

  15. 14.Operational land for purposes of the 1990 Act

  16. 15.Felling or lopping of trees etc

  17. 16.Removal of human remains

  18. 17.Service of notices

  19. 18.Certification of plans etc

  20. 19.Arbitration

  21. Signature

    1. Expand +/Collapse -

      SCHEDULE 1

      AUTHORISED PROJECT

      1. Expand +/Collapse -

        PART 1 AUTHORISED DEVELOPMENT

        1. In the County of Carmarthenshire

      2. Expand +/Collapse -

        PART 2 ANCILLARY WORKS

        1. 1.Removal of hedgerows

      3. Expand +/Collapse -

        PART 3 REQUIREMENTS

        1. 1.Definitions

        2. 2.Submission and approval of details

        3. 3.Time limits

        4. 4.Expiry of development consent

        5. 5.Decommissioning and site restoration

        6. 6.Failure of turbines

        7. 7.Plans

        8. 8.Construction traffic management plan

        9. 9.Construction method statement

        10. 10.Highways

        11. 11.No authorised development shall commence until details of temporary or...

        12. 12.No authorised development shall commence until details of the reinstatement...

        13. 13.Construction hours

        14. 14.Notwithstanding the provisions of Requirement 13, delivery of turbine and...

        15. 15.Habitat management plan

        16. 16.European protected species

        17. 17.Access management plan

        18. 18.Felling

        19. 19.Appearance

        20. 20.Notwithstanding any design or colour approved by the relevant planning...

        21. 21.(1) No wind turbines shall display any name, sign, symbol...

        22. 22.All wind turbines’ blades shall rotate in the same direction....

        23. 23.Before construction of Work No. 5, details of the external...

        24. 24.Shadow flicker

        25. 25.TV interference

        26. 26.Archaeology

        27. 27.Ecological clerk of works

        28. 28.Surface water drainage

        29. 29.Accumulation and deposits

        30. 30.Infra-red aviation lighting

        31. 31.Defence Geographic Centre

        32. 32.Noise

        33. 33.Within 21 days from the receipt of a written request...

        34. 34.The undertaker shall, if directed by the relevant planning authority,...

        35. 35.The undertaker shall provide to the relevant planning authority the...

        36. 36.The undertaker shall continuously log wind speed wind direction at...

        37. 37.Community liaison

      4. PART 4 NOISE GUIDANCE NOTES

    2. Expand +/Collapse -

      SCHEDULE 2

      STREET SUBJECT TO STREET WORKS

    3. Expand +/Collapse -

      SCHEDULE 3

      STREETS TO BE TEMPORARILY STOPPED UP

  22. Explanatory Note