- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
SCHEDULES
7.No phase of the authorised development is to commence until...
20.The proposed Clifton Brook Tributary Flood Storage Scheme is to...
21.The authorised development must be carried out in accordance with...
22.The rail embankment within the floodplain to the west of...
23.No phase of the authorised development is to commence until...
24.Prior to the commencement of any element of the authorised...
25.Any element of the authorised development which directly affects any...
33.A verification report demonstrating completion of the works set out...
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: