26.—(1) The Secretary of State may, in connection with the carrying out of the authorised development—
(a)enter on and take temporary possession of—
(i)the land specified in columns (1) and (2) of Schedule 7 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the part of the authorised development specified in column (4) of that Schedule; and
(ii)any other Order land in respect of which no notice of entry has been served under section 11 of the 1965 Act (powers of entry) (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 of the 1981 Act (execution of declaration);
(b)remove any buildings and vegetation from that land;
(c)construct temporary works (including the provision of means of access) and buildings on that land;
(d)construct any permanent works specified in relation to that land in column (3) of Schedule 7, or any other mitigation works; and
(e)construct Works Nos. 5, 6 and 7 on that land.
(2) Not less than 14 days before entering on and taking temporary possession of land under this article the Secretary of State must serve notice of the intended entry on the owners and occupiers of the land.
(3) The Secretary of State may not, without the agreement of the owners of the land, remain in possession of any land under this article—
(a)in the case of the plots with reference numbers 2/1i, 2/2i, 2/4e and 2/4h, after the new rights have been created pursuant to article 20 (compulsory acquisition of rights);
(b)in the case of other land specified in paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (4) of Schedule 7; or
(c)in the case of any land referred to in paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken unless the Secretary of State has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.
(4) Before giving up possession of land of which temporary possession has been taken under this article, the Secretary of State must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the Secretary of State is not required to—
(a)replace a building removed under this article;
(b)restore the land on which any permanent works have been constructed under paragraphs (1)(d) or (1)(e); or
(c)remove any ground strengthening works which have been placed on the land to facilitate construction of the authorised development.
(5) The Secretary of State must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
(6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.
(7) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (5).
(8) The Secretary of State may not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i) except that the Secretary of State is not precluded from—
(a)acquiring new rights over any part of that land under article 20; or
(b)acquiring any part of the subsoil (or rights in the subsoil of or air-space over) that land under article 23 (acquisition of subsoil or air-space only).
(9) Where the Secretary of State takes possession of land under this article, the Secretary of State is not required to acquire the land or any interest in it.
(10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
(11) Paragraph (1)(a)(ii) does not authorise the Secretary of State to take temporary possession of any land which the Secretary of State is not authorised to acquire under article 18 (compulsory acquisition of land) or any land specified in Schedule 5 (land in which only new rights etc. may be acquired).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: