The Clocaenog Forest Wind Farm Order 2014

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Clocaenog Forest Wind Farm Order 2014. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.

View outstanding changes

Changes and effects yet to be applied to :

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

  1. Introductory Text

  2. PART 1

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. PART 2

    1. 3.Development consent etc granted by the Order

    2. 4.Procedure in relation to approvals etc under Requirements

    3. 5.Maintenance of authorised project

    4. 6.Power to deviate

    5. 7.Operation of generating station

    6. 8.Benefit of Order

    7. 9.Defence to proceedings in respect of statutory nuisance

    8. 10.Street works

    9. 11.Stopping up of streets

    10. 12.Public rights of way

    11. 13.Application of the 1991 Act

    12. 14.Temporary stopping up of streets

    13. 15.Access to works

    14. 16.Construction and maintenance of new or altered streets

    15. 17.Agreements with street authorities

    16. 18.Discharge of water

    17. 19.Authority to survey and investigate the land

  4. PART 3

    1. 20.Compulsory acquisition of land and rights

    2. 21.Time limit for exercise of authority to acquire land compulsorily

    3. 22.Application and modification of legislative provisions

    4. 23.Compulsory acquisition of rights

    5. 24.Private rights

    6. 25.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

  5. PART 4

    1. 26.Application of landlord and tenant law

    2. 27.Operational land for purposes of the 1990 Act

    3. 28.Felling or lopping of trees

    4. 29.Statutory undertakers

    5. 30.Apparatus and rights of statutory undertakers in stopped-up streets

    6. 31.Recovery of costs of new connections

    7. 32.Removal of human remains

    8. 33.Crown rights

    9. 34.Service of notices

    10. 35.Protection of interests

    11. 36.Certification of plans etc

    12. 37.Arbitration

  6. Signature

    1. SCHEDULE 1

      Authorised project

      1. PART 1 Authorised development

        1. In the County of Denbighshire and in the County Borough of Conwy—

      2. PART 2 Ancillary works

        1. 1.Highway works

      3. PART 3 Requirements

        1. 1.Definitions

        2. 2.Submission and approval of details

        3. 3.Time limits

        4. 4.Expiry of development consent

        5. 5.Decommissioning and site restoration

        6. 6.Failure of turbines

        7. 7.Plans

        8. 8.Construction traffic management plan

        9. 9.Construction method statement

        10. 10.Highways

        11. 11.The authorised development may not commence until, following consultation with...

        12. 12.The authorised development may not commence until following consultation with...

        13. 13.Construction hours

        14. 14.With respect to paragraph (2) of Requirement 13, such approval...

        15. 15.Habitat management plan

        16. 16.Access management plan

        17. 17.Felling

        18. 18.Appearance

        19. 19.Notwithstanding any design or colour approved by the relevant planning...

        20. 20.(1) No wind turbine may display any name, sign, symbol...

        21. 21.All wind turbines’ blades are to rotate in the same...

        22. 22.Before construction of Work No. 5A or 5B, details of...

        23. 23.Shadow flicker

        24. 24.Archaeology

        25. 25.Ecological clerk of works

        26. 26.Surface water drainage

        27. 27.Accumulation and deposits

        28. 28.Infra-red aviation lighting

        29. 29.Defence Geographic Centre

        30. 30.Noise

        31. 31.Within 21 days from the receipt of a written request...

        32. 32.The undertaker must, if directed by the relevant planning authority,...

        33. 33.The undertaker must provide to the relevant planning authority the...

        34. 34.The undertaker must continuously log wind speed wind direction and...

        35. 35.(1) No authorised development may commence until an assessment demonstrating...

      4. PART 4 Noise Guidance for Requirements 30 to 35

        1. 1.(1) Values of the LA90,10min noise statistic shall be measured...

        2. 2.(1) The noise measurements shall be made so as to...

        3. 3.Where, in the opinion of the relevant planning authority, noise...

        4. 4.If the measured noise level from the authorised development (including...

    2. SCHEDULE 2

      Streets subject to street works

    3. SCHEDULE 3

      Streets to be stopped up

    4. SCHEDULE 4

      Streets to be temporarily stopped up

    5. SCHEDULE 5

      Access to works

    6. SCHEDULE 6

      Land subject to acquisition of new rights and interference with private rights

      1. PART 1

      2. PART 2 Land subject to interference with private rights

    7. SCHEDULE 7

      Modification of compensation and compulsory purchase enactments for creation of new rights

      1. 1.Compensation enactments

      2. 2.(1) Without prejudice to the generality of paragraph 1, the...

      3. 3.Application of the 1965 Act

      4. 4.For section 7 of the 1965 Act (measure of compensation)...

      5. 5.For section 8 of the 1965 Act (provisions as to...

      6. 6.The following provisions of the 1965 Act (which state the...

      7. 7.Section 11 of the 1965 Act (powers of entry) shall...

      8. 8.Section 20 of the 1965 Act (protection for interests of...

      9. 9.Section 22 of the 1965 Act (protection of acquiring authority’s...

    8. SCHEDULE 8

      Protection for electricity, gas, water and sewerage undertakers

      1. 1.For the protection of the utility undertakers referred to in...

      2. 2.In this Schedule— “alternative apparatus” means alternative apparatus adequate to...

      3. 3.This Schedule does not apply to apparatus in respect of...

      4. 4.Regardless of any provision in this Order or anything shown...

      5. 5.(1) If, in the exercise of the powers conferred by...

      6. 6.(1) Where, in accordance with the provisions of this Schedule,...

      7. 7.(1) Not less than 28 days before starting the execution...

      8. 8.(1) Subject to the following provisions of this paragraph, the...

      9. 9.(1) Subject to sub-paragraphs (2) and (3), if by reason...

      10. 10.Nothing in this Schedule shall affect the provisions of any...

  7. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources