Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
SCHEDULES
ACQUISITION OF LAND AND OF SUBSOIL OF LAND ONLY AND POWER TO IMPOSE RESTRICTIVE COVENANTS
FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
1.(1) The following provisions, unless otherwise agreed in writing between...
2.(1) In this Schedule— “alternative apparatus” means alternative apparatus adequate...
3.This Schedule does not apply to apparatus in respect of...
5.Regardless of any provision in this Order or anything shown...
7.(1) Where, in accordance with the provisions of this Schedule,...
8.(1) Not less than 28 days before starting the execution...
9.(1) Subject to the following provisions of this paragraph, the...
10.(1) Subject to sub-paragraphs (2) and (3), if by reason...
FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
1.(1) The following provisions of this Schedule, unless otherwise agreed...
2.(1) Before beginning to construct any specified work, the Company...
3.Without limitation on the scope of paragraph 2, the requirements...
4.(1) Subject to sub-paragraph (2), any specified work, and all...
5.(1) Subject to the provisions of this Schedule and except...
6.Subject to paragraph 7, if by reason of the construction...
7.Nothing in paragraphs 4(4), 5(3) and 6 authorises the Agency...
8.The Company must indemnify the Agency in respect of all...
9.(1) Without affecting the other provisions of this Schedule, the...
11.Any dispute arising between the Company and the Agency under...
FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORK
FOR THE PROTECTION OF THE CITY OF LONDON CORPORATION
1.(1) The following provisions of this Schedule have effect, unless...
2.Before commencing to construct any work which will involve highway...
4.Before commencing to construct any authorised work which will involve...
5.Any highway which has been subject to highway operations must...
6.Except as expressly authorised by this Order the Company must...
7.Except in an emergency or where reasonably necessary to secure...
8.The Company must, if reasonably so required by the Corporation,...
9.The Company must indemnify the Corporation against any claim which...
11.Wherever in this Schedule provision is made with respect to...
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: