Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Regulation 39
1.—(1) In this Schedule—
“the 2005 regime” means—
the legislation modified by Schedule 13 to these Regulations; and
the 1974 Act as it applied in relation to the legislation mentioned in paragraph (a),
to the extent that that Act and that legislation had effect in relation to external waters immediately before the commencement date;
“the 2005 Regulations” means the Offshore Installations (Safety Case) Regulations 2005 M1 as they had effect immediately before the commencement date;
“the commencement date” means 19th July 2015;
“corresponding provision” means any provision of these Regulations—
as it has effect on or after the commencement date; and
so far as it corresponds (with or without modification) to a provision of the 2005 Regulations in relation to external waters;
“current safety case,” unless the context otherwise provides, has the meaning given in the 2005 Regulations;
“the date of thorough review” means the date immediately before the fifth anniversary of—
the date on which the Executive first accepted the current safety case pursuant to the 2005 Regulations; or
where there has been at least one review of that safety case under regulation 13 of the 2005 Regulations immediately before the commencement date, the date—
of that review, or
if there has been more than one review, the last of those reviews;
“design notification”, unless the context otherwise provides, has the meaning given in the 2005 Regulations;
“duty holder”, except in paragraph 8, has the meaning given in the 2005 Regulations;
“field development programme” means a field development programme within the meaning given in the 2005 Regulations;
“existing non-production installation” means a non-production installation for which there was a current safety case immediately before 18 July 2013;
“existing production installation” means a production installation for which there was a current safety case immediately before 18 July 2013;
“operator”, has the meaning given in the 2005 Regulations;
“owner” has the meaning given in the 2005 Regulations;
“transitional period” means, in relation to an owner, operator or well-operator (as the case may be) the period for which the 2005 regime continues to apply in relation to that person.
(2) For the purposes of this Schedule—
(a)“notification” means a notification under a provision of the 2005 Regulations specified in the first column of the Table below; and
(b)a notification is completed if the event specified in the second column of the Table corresponding to the entry for that notification in the first column of the Table has occurred.
Notification under the 2005 Regulations | Event on which notification is completed |
---|---|
Regulation 6(1) (design) | Submission of the field development programme |
Regulation 6(2) (relocation of a production installation) | Submission of the field development programme |
Regulation 9 (conversion of non-production installation to operate as a production installation) | Completion of the design |
Regulation 10 (combined operation) | Engagement in the combined operation |
Regulation 17(1) (general well operation) | Commencement of well operation |
Regulation 17(2) (specific well operation) | Commencement of well operation |
Marginal Citations
M1S.I. 2005/3117, amended by S.I. 2006/336, 2007/3224, 2009/229, 2013/1471.
2. Despite the coming into force of these Regulations, the 2005 regime continues to apply in relation to external waters during the transitional period as provided for in this Part of this Schedule.
3. The 2005 regime continues to apply in relation to the owner of a non-production installation, in respect of that installation, for the period which starts on the commencement date and ends—
(a)where the installation is an existing non-production installation—
(i)immediately before 19th July 2016; or
(ii)if earlier, on the date of thorough review provided that that date falls on or after the commencement date;
(b)where the installation is not an existing non-production installation and is established on or after the commencement date but before 19th July 2016, immediately before 19th July 2016.
4. The 2005 regime continues to apply in relation to the operator of a production installation, in respect of that installation, for the period which starts on the commencement date and ends—
(a)where the production installation is an existing production installation—
(i)immediately before 19th July 2018; or
(ii)if earlier, on the date of thorough review provided that that date falls on or after the commencement date;
(b)where the production installation is not an existing production installation and is established on or after the commencement date but before 19th July 2016, immediately before 19th July 2016.
5.—(1) The 2005 regime continues to apply to the submission of a well notification by a well operator in respect of, or execution by such an operator of a well operation from—
(a)a non-production installation to which paragraph 3 applies, for the period that it applies to the owner of that installation in accordance with that paragraph;
(b)from a production installation to which paragraph 4 applies, for the period that it applies to the operator of that installation in accordance with that paragraph; and
(c)a vessel that is not an installation, for the period which starts on the commencement date and ends immediately before 19th July 2016.
(2) Despite sub-paragraph (1)(b) the 2005 regime ceases to apply to—
(a)the submission of a well notification in respect of a production installation; or
(b)the execution of a well operation from such an installation,
on 19th July 2016.
(3) Nothing in sub-paragraph (2) affects the application of paragraph 4 to the operator of the relevant production installation.
6. Where a production installation is to be established on or after the commencement date but before 19th July 2016, the 2005 regime applies to the preparation and sending to the Executive of the design notification for that installation.
7.—(1) Despite paragraph 6, the operator of a production installation which is to be established on or after the commencement date but before 19th July 2016 may elect to prepare and send a design notification to the competent authority under these Regulations.
(2) Where an operator elects to prepare and send a design notification under these Regulations, the 2005 regime ceases to apply to that operator in relation to that installation on the date on which that notification is sent to the competent authority.
8.—(1) Subject to sub-paragraph (2), nothing in paragraph 3(b), 4(b) or 5(1) prevents a duty holder who would otherwise be or continue to be subject to the 2005 regime as a consequence of any of those provisions from preparing and sending a safety case to the competent authority under these Regulations.
(2) Sub-paragraph (1) does not apply if there is a current safety case for the installation.
(3) Where a duty holder elects in accordance with sub-paragraph (1) to prepare and send a safety case to the competent authority under these Regulations—
(a)the 2005 regime ceases to apply to that operator in relation to that installation on the date on which the operator sends the safety case to the competent authority; and
(b)these Regulations apply to that operator in relation to that installation on and after that date.
9.—(1) Sub-paragraph (2) applies to the duty holder of an installation, in respect of that installation, where—
(a)paragraph 3 or 4 continues to apply to the duty holder in respect of that installation;
(b)there is a period of no more than four months, or such longer period as the competent authority may specify, remaining until the end of the transitional period;
(c)there is a current safety case; and
(d)there is an intention, after the transitional period ends—
(i)in the case of a non-production installation, to operate it in external waters or move it in external waters with a view to its being operated there; or
(ii)in the case of a production installation, to operate it in external waters.
(2) Where this sub-paragraph applies the duty holder may make revisions to the current safety case—
(a)containing particulars, not required pursuant to the 2005 Regulations, but specified in—
(i)regulation 16 of and Schedule 7 to these Regulations, in the case of a non-production installation; or
(ii)in regulation 16 of and Schedule 6 to these Regulations in relation to a production installation; and
(b)which are otherwise appropriate in consequence of any revision made under paragraph (a).
(3) Revisions made under sub-paragraph (2) which make a material change to the current safety case are not effective unless—
(a)the duty holder sends a version of the current safety case which incorporates the proposed revisions, showing clearly where they are to be made, to the competent authority at least three months, or such shorter period as the competent authority may specify, before the revisions are to be made; and
(b)the competent authority accepts the revisions.
10. Where revisions to current safety case under paragraph 9(2) may take effect without the acceptance of the competent authority or are accepted by the competent authority, the current safety case together with those revisions has effect—U.K.
(a)as a current safety case until the end of the relevant transitional period; and
(b)subject to paragraph 11, on and after the end of that transitional period for the purposes of these Regulations as a current safety case within the meaning of regulation 2(1).
11. Where paragraph 10(b) applies to a safety case, paragraph (1)(a) of regulation 23 has effect as if the reference in that paragraph to the date on which the current safety case was first accepted by the competent authority were a reference to the date on which the Executive first accepted that safety case under the 2005 Regulations.U.K.
12.—(1) An improvement notice to which this paragraph applies has effect on and after the relevant date as an improvement notice issued in respect of a contravention of a corresponding provision of these Regulations.
(2) This paragraph applies to an improvement notice if—
(a)it was in force or effective immediately before the relevant date; and
(b)it was served on an owner, operator or well operator by an inspector under the 2005 regime.
(3) In this paragraph “relevant date” means the date on which the transitional period ends.
13.—(1) Where—
(a)a prohibition notice—
(i)is served on an owner, operator or well operator by an inspector as regards activities to which the 2005 regime applied or would have applied;
(ii)is in force or effective immediately before the relevant date; and
(b)the activities mentioned in paragraph (i) are activities to which a corresponding provision of these Regulations applies, or will, if carried on, apply on and after the relevant date,
that notice continues to have effect on and after the relevant date as if served as regards activities to which these Regulations apply or will apply.
(2) In this paragraph “relevant date” means the date on which the transitional period ends.
14. A notification under the 2005 regime which is completed immediately before the date on which the transitional period ends has effect on and after that date as a notification made under the corresponding provision of these Regulations.
15. Where a notification under the 2005 regime is not completed before the date on which the transitional period ends (“the relevant date”), but particulars of it have been notified before the relevant date in accordance with the 2005 regime—U.K.
(a)the particulars notified have effect on and after the relevant date as particulars notified pursuant to the corresponding provision of these Regulations;
(b)the absence from particulars falling within paragraph (a) of any particulars required pursuant to a corresponding provision of these Regulations but not required pursuant to the 2005 regime is to take effect as a material change in those particulars on the relevant date.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: